Municipal Land Use Planning


Swartland
South Africa

Municipal Land Use Planning By-law, 2017

Chapter I
INTERPRETATION AND APPLICATION

1. Definitions

In this by-law, unless the context indicates otherwise, any word or expression to which a meaning has been assigned in the Western Cape Land Use Planning Act, 2014 (Act 3 of 2014), has the meaning assigned to it in that Act and—"adopt", in relation to a spatial development framework, zoning scheme, policy or strategy, means the approval thereof by a competent authority;"agent" means a person authorised in terms of a power of attorney to make an application on behalf of the owner of land;"Appeal Authority" means the Appeal Authority contemplated in section 89(1); 29. "applicable period", referred to in sections 27(5) and (6), 28(2), (5) , 32(1) and 42(1), means the period that may be determined by the municipality in the conditions of approval subject to section 43(2)(b) of the Spatial Planning and Land Use Management Act or the period referred to in section 43(2)(a) of the Spatial Planning and Land Use Management Act;"applicant" means a person referred to in section 25(2) who makes an application to the municipality as contemplated in that section;"application" means an application to the municipality referred to in section 25(2);"authorised employee" means a municipal employee who is authorised in terms of delegated or sub-delegated authority by the municipality to exercise a power or perform a duty in terms of this by-law or to inspect land and buildings in order to enforce compliance with this by-law or the zoning scheme;"base zoning" means the zoning before the application of any overlay zone;"comments", in relation to comments submitted by the public, municipal departments and other organs of state and service providers on an application or appeal, includes objections, representations and petitions;"consolidation" in relation to land, means the merging of two or more adjacent land units into a single land unit, and includes the physical preparation of land for consolidation;"Council" means the municipal council of Swartland Municipality;"date of notification" means the date on which a notice is served as contemplated in section 45 or published in the media or Provincial Gazette;"development charge" means a development charge contemplated in section 93 as levied by the municipality;"emergency" includes a situation that arises from a flood, strong wind, severe rainstorm, fire, earthquake or industrial accident and that requires the relocation of human settlements;"external engineering service" means an engineering service outside the boundaries of a land area referred to in an application and that is necessary for the utilisation and development of the land;"Land Use Planning Act" means the Western Cape Land Use Planning Act, 2014 (Act 3 of 2014);"local spatial development framework" means a local spatial development framework contemplated in section 9;"Municipal Manager" means a person appointed in terms of section 54A of the Local Government: Municipal System Act, (Act 32 of 2000);"municipal spatial development framework" means a municipal spatial development framework adopted by the municipality in terms of Chapter 5 of the Municipal Systems Act;"municipality" means the municipality of Swartland established in terms of section 12 of the Local Government: Municipal Structures Act, 1998 (Act 117 of 1998), and includes—
(a)the Council;
(b)another political structure or a political office bearer of the municipality, authorised or delegated to perform a function or exercise a power in terms of this By-Law;
(c)the Tribunal authorised or delegated to perform a function or exercise a power in terms of this By-Law;
(d)the municipal manager; and
(e)an authorised employee.
"non-conforming use" means an existing land use that was lawful in terms of a previous zoning scheme but that does not comply with the zoning scheme in force;"occasional use", in relation to departure, means a right to utilise land for a purpose granted on a temporary basis for a specific occasion or event;"overlay zone" means a category of zoning that applies to land or a land unit in addition to the base zoning and that—
(a)stipulates additional development parameters or use rights that may be more or less restrictive than the base zoning; and
(b)may include provisions and development parameters relating to—
(i)primary or consent uses;
(ii)base zoning;
(iii)subdivision or sub divisional areas;
(iv)development incentives;
(v)density limitations;
(vi)urban form or urban renewal;
(vii)heritage or environmental protection;
(viii)management of the urban edge;
(ix)scenic drives or local areas;
(x)coastal setbacks (where coastlines are involved); or
(xi)any other purpose as set out in the zoning scheme;
"owners" association" means an owners’ association contemplated in section 39;"pre-application consultation" means a consultation contemplated in section 47;"restrictive condition" means any condition registered against the title deed of land restricting the use, development or subdivision of the land concerned:"service" means a service provided by the municipality, any other organ of state or a service provider, including services for the provision of water, sewerage, electricity, refuse removal, roads, storm-water drainage, and includes infrastructure, systems and processes related to the service;"site development plan" means a dimensioned plan drawn to scale that indicates details of the proposed land development, including the site layout, positioning of buildings and structures, property access, building designs and landscaping;"social infrastructure" means community facilities, services and networks that meet social needs and enhance community well-being;"Spatial Planning and Land Use Management Act" means the 2013. Spatial Planning and Land Use Management Act, 2013 (Act 16 of 2013);"Spatial Planning and Land Use Management Regulations" means the Spatial Planning and Land Use Management 2015 Regulations: Land Use Management and General Matters, made under the Spatial Planning and Land Use Management Act published under Notice R239/2015 in Government Gazette 38594. of 23 March 2015;"sub divisional area" means an overlay zone that permits subdivision for the purposes of a subdivision application involving a change of zoning;"Tribunal" means the Municipal Planning Tribunal established in terms of section 80;"zoning" includes base zoning and overlay zoning;"Zoning scheme" means the Zoning Scheme referred to in Schedule 2;

2. Application of by-law

This by-law applies to all land situated within the municipal area, including land owned by organs of state.

Chapter II
SPATIAL PLANNING

3. Compilation or amendment of municipal spatial development framework

(1)When the Council compiles or amends its municipal spatial development framework in accordance with the Municipal Systems Act, the Council must, as contemplated in section 11 of the Land Use Planning Act
(a)establish an intergovernmental steering committee to compile or amend its municipal spatial development framework; or
(b)refer its draft municipal spatial development framework or draft amendment of its municipal spatial development framework to the Provincial Minister for comment.
(2)The municipality must—
(a)publish a notice in two of the official languages of the Province most spoken in the area in two newspapers circulating in the area concerned of—
(i)the intention to compile or amend the municipal spatial development framework; and
(ii)the process to be followed, in accordance with section 28(3) and 29 of the Municipal Systems Act;
(b)inform the Provincial Minister in writing of—
(i)the intention to compile or amend the municipal spatial development framework;
(ii)its decision in terms of subsection (1)(a) or (b); and
(iii)the process to be followed to compile or amend the municipal spatial development framework, including the process contemplated in subsection (2)(a)(ii) ; and
(c)register relevant stakeholders, who must be invited to comment on the draft municipal spatial development framework or draft amendment of the municipal spatial development framework as part of the process contemplated in subsection (2)(a)(ii).

4. Establishment of project committee

(1)The municipality must establish a project committee to compile or amend its municipal spatial development framework.
(2)The project committee must consist of—
(a)the municipal manager or a municipal employee designated by the municipal manager; and
(b)municipal employees appointed by the municipal manager from at least the following municipal departments—
(i)the integrated development planning office;
(ii)the spatial planning department;
(iii)the engineering department;
(iv)the local economic development department; and
(v)the housing department.

5. Establishment of intergovernmental steering committee

If the Council establishes an intergovernmental steering committee, the municipality must, in writing, invite written nominations for representatives to serve on the intergovernmental steering committee from the following persons or organs of state—
(a)the head of the provincial department responsible for land use planning;
(b)the head of the provincial department responsible for environmental affairs; and
(c)other relevant organs of state.

6. Procedure with intergovernmental steering committee

(1)If the Council establishes an intergovernmental steering committee, the project committee must compile a draft status quo report setting out an assessment of the existing levels of development and development challenges in the municipal area and must submit it to the intergovernmental steering committee for comment.
(2)After consideration of the comments of the inter-governmental steering committee, the project committee must finalise the status quo report and submit it to the Council for adoption.
(3)After finalising the status quo report the project committee must compile a first draft of the municipal spatial development framework or first draft of the amendment thereof and submit it to the intergovernmental steering committee for comment.
(4)After consideration of the comments of the inter-governmental steering committee, the project committee must finalise the first draft of the municipal spatial development framework or first draft of the amendment thereof and submit it to the Council to approve the publication thereof for public comment in accordance with the process adopted in terms of sections 28 and 29 of the Municipal Systems Act.
(5)After consideration of the comments and representations received by virtue of the publication contemplated in subsection (4), the project committee must compile a final draft of the municipal spatial development framework or final draft of the amendment thereof and submit it to the intergovernmental steering committee for comment.
(6)After consideration of the comments of the inter-governmental steering committee contemplated in subsection
(5), the project committee must finalise the final draft of the municipal spatial development framework or final draft of the amendment thereof and submit it to the Council for adoption.
(7)If the final draft of the municipal spatial development framework or final draft of the amendment thereof contemplated in subsection (6) is materially different to what was published in terms of subsection (4), the municipality must in accordance with subsections (4), (5) and (6) read with the necessary changes, follow a further consultation and public participation process before the municipal spatial development framework or amendment thereto is adopted by the Council.
(8)The Council or the project committee may at any time in the process of compiling a municipal spatial development framework or drafting an amendment thereof request comments from the intergovernmental steering committee.
(9)The Council must adopt the final draft municipal spatial development framework or final draft amendment thereof, with or without amendments and must within 14 days of its decision give notice of its decision in the media and the Provincial Gazette.

7. Procedure without intergovernmental steering committee

(1)If the Council does not establish an intergovernmental steering committee to compile or amend its municipal spatial development framework, the project committee must—
(a)compile a draft status quo report setting out an assessment of the existing levels of development and development challenges in the municipal area and submit it to the Council for adoption;
(b)after adoption of the status quo report, compile a first draft of the municipal spatial development framework or first draft of the amendment of the municipal spatial development framework and submit it to the Council to approve the publication thereof for public comment;
(c)after approval of the first draft of the municipal spatial development framework or first draft of the amendment of the municipal spatial development framework for publication contemplated in paragraph (b), submit the first draft of the municipal spatial development framework or first draft of the amendment of the municipal spatial development framework to the Provincial Minister for comment in terms of section 13 of the Land Use Planning Act; and
(d)after consideration of the comments and representations received from the public and the Provincial Minister, submit the final draft of the municipal spatial development framework or final draft of the amendment of the municipal spatial development framework, with any further amendments, to the Council for adoption.
(2)If the final draft of the municipal spatial development framework or final draft of the amendment of the municipal spatial development framework contemplated in subsection (1) is materially different to what was published in terms of subsection (1)(b), the municipality must follow a further consultation and public participation process before the municipal spatial development framework or amendment of the municipal spatial development framework is adopted by the Council.
(3)The Council must adopt the final draft of the municipal spatial development framework or final draft of the amendment of the municipal spatial development framework, with or without amendments, and must within 14 days of its decision give notice of its decision in the media and the Provincial Gazette.

8. Functions and duties

(1)The members of the project committee must, in accordance with the directions of municipal manager—
(a)oversee the compilation of the municipal spatial development framework or drafting of an amendment of the municipal spatial development framework for adoption by the Council;
(b)provide technical knowledge and expertise to the Council;
(c)ensure that the compilation of the municipal spatial development framework or drafting of the amendment of the municipal spatial development framework is progressing according to the process contemplated in section 3(2)(a)(ii);
(d)guide the public participation process and ensure that the registered stakeholders remain informed;
(e)oversee the incorporation of amendments to the draft municipal spatial development framework or draft amendment of the municipal spatial development framework based on the consideration of the comments received during the process of drafting thereof;
(f)oversee the drafting of—
(i)a report in terms of section 14 of the Land Use Planning Act setting out the response of the municipality to the provincial comments issued in terms of section 12(4) or 13(2) of that Act; and
(ii)a statement setting out—
(aa)whether the municipality has implemented the policies and objectives issued by the national minister responsible for spatial planning and land use management and if so, how and to what extent the municipality has implemented it; or
(bb)if the municipality has not implemented the policies and objectives, the reasons for not implementing it.
(g)ensure alignment of the municipal spatial development framework with the development plans and strategies of other affected municipalities and other organs of state as contemplated in section 24(1) of the Municipal Systems Act;
(h)facilitate the integration of other sector plans into the municipal spatial development framework; and
(i)if the Council establishes an intergovernmental steering committee—
(i)assist the Council in establishing the intergovernmental steering committee and adhering to timeframes; and
(ii)ensure the flow of information between the project committee and the intergovernmental steering committee.
(2)The members of the intergovernmental steering committee must—
(a)provide the intergovernmental steering committee with the following—
(i)technical knowledge and expertise;
(ii)input on outstanding information that is required to compile the municipal spatial development framework or draft an amendment thereof;
(iii)information on budgetary allocations;
(iv)information on and the locality of any current or planned projects that have an impact on the municipal area; and
(v)written comments in terms of section 6; and
(b)provide the project committee with written comments in terms of section 6.

9. Local spatial development frameworks

(1)The municipality may adopt a local spatial development framework for a specific geographical area in a part of the municipal area.
(2)The purpose of a local spatial development framework is to, for a specific geographical area—
(a)provide detailed spatial planning guidelines;
(b)provide more detail in respect of a proposal provided for in the municipal spatial development framework;
(c)meet specific land use planning needs;
(d)provide detailed policy and development parameters for land use planning;
(e)provide detailed priorities in relation to land use planning and, in so far as they are linked to land use planning, biodiversity and environmental issues; and
(f)guide decision-making on land use applications.

10. Compilation, adoption, amendment or review of local spatial development frameworks

(1)If the municipality compiles, amends or reviews a local spatial development framework, it must adopt a process plan, including the public participation processes to be followed for the compilation, amendment, review or adoption of a local spatial development framework.
(2)The municipality must, within 21 days of adopting a local spatial development framework or an amendment of a local spatial development framework, publish a notice of the decision in the media and the Provincial Gazette.

11. Status of local spatial development frameworks

(1)A local spatial development framework or an amendment thereof comes into operation on the date of publication of the notice contemplated in section 10(2).
(2)A local spatial development framework guides and informs decisions made by the municipality relating to land development, but it does not confer or take away rights.

12. Structure plans

(1)If the municipality intends to convert a structure plan to a local spatial development framework, the municipality must comply with sections 9 to 11 and must—
(a)review that structure plan and make it consistent with the purpose of a local spatial development framework contemplated in section 9(2); and
(b)incorporate the provisions of the structure plan that are consistent with that purpose in the local spatial development framework.
(2)The municipality must, in terms of section 16(4) of the Land Use Planning Act, withdraw the relevant structure plan by notice in the Provincial Gazette when it adopts a local spatial development framework contemplated in subsection (1).

Chapter III
ZONING SCHEME, USE ZONES, USES AND ZONINGS

13. Application of zoning scheme

The zoning scheme applies to the entire Swartland municipal area and forms an integral part of this by-law.

14. Purpose of zoning scheme

The purpose of the zoning scheme includes—
(a)giving effect to the municipal spatial development framework;
(b)making provision for orderly development and the welfare of the community;
(c)the regulation of use rights and control of the use of land;
(d)the facilitation of the implementation of policies and principles set out in relevant spatial development frameworks and binding policies and principles set out in and in terms of national and provincial legislation;
(e)facilitation of efficient, economic and sustainable use of land;
(f)protection of areas with an environment which could be substantially adversely affected by development;
(g)other purposes prescribed by national or provincial legislation; and
(h)determination of use rights and development parameters, with due consideration of the principles referred to in Chapter VI - of the Land Use Planning Act.

15. Components of zoning scheme

The zoning scheme consists of the following components—
(a)this by-law;
(b)the zoning map; and
(c)the register.

16. Use zones

(1)The municipal area is divided in the use zones referred to in column 1 of Table A set out in Schedule 2.
(2)The purpose of each use zone is set out in column 1 of Table A.
(3)The description of the primary and consent uses applicable to each use zone is set out in Table B.
(4)The location, boundaries and extent of each use zone is depicted on the zoning map.
(5)The primary and consent uses applicable to each use zone are subject to the development parameters specified for that use zone as set out in Schedule 2.

17. Zoning map

(1)The zoning map depicts—
(a)the zoning of land in accordance with the use zone in which the land is located; and
(b)overlay zones, if applicable to the land.
(2)The municipality must update the zoning map within a reasonable time after use rights have been granted or have lapsed.
(3)The municipality may keep the zoning map in an electronic format.
(4)The municipality may provide an extract of the zoning map to members of the public on payment of a fee determined by the municipality in terms of the municipality’s tariff policy.

18. Preparation and approval of new zoning map

(1)The municipality must give notice of a draft zoning map.
(2)The notice must be published in newspapers with general circulation in the area concerned in at least two of the official languages of the Province most widely spoken in the municipal area and must—
(a)invite persons interested in, or affected by, the draft zoning map to submit written comments within a period of not less than 30 days from the date on which the notice was given;
(b)state the name and contact details of the person to whom the comments must be addressed and where the draft zoning map can be obtained; and
(c)state that any person who is unable to write may, during the municipality’s office hours, attend at any address stated in the notice where a named staff member of the municipality will assist that person to transcribe that person’s comments.
(3)A zoning map may be approved by the municipality with or without amendments.
(4)A zoning map takes effect when notice of its approval is published in the Provincial Gazette or on a future date as may be determined in the notice.
(5)Subsequent amendments to the map to reflect additional use rights granted or use rights that have lapsed are not published in the Provincial Gazette.

19. Rectification of errors on zoning map

(1)If the zoning of a land unit is incorrectly indicated on the zoning map or wrongly converted from a zoning map of a former zoning scheme, the owner of an affected land unit may submit an application to the municipality to correct the error.
(2)An owner contemplated in subsection (1) must apply to the municipality in the form determined by the municipality and must—
(a)submit written proof of the lawful land use rights; and
(b)indicate the suitable zoning which should be allocated.
(3)The onus of proving that the zoning is incorrectly indicated on the zoning map is on the owner.
(4)The owner is exempted from paying application fees and from liability for the costs of public participation.
(5)If the municipality approves the application, the municipality must amend the zoning map.
(6)The municipality may refuse an application to correct the zoning map if the owner fails to submit written proof of the lawful use rights.
(7)The municipality may correct a zoning map if it finds an error on the map after—
(a)notifying the owner in writing of its intention to correct the wrong conversion or error;
(b)inviting the owner to make representations within a specified period in respect of the proposed correction of the errors on the zoning map; and
(c)considering any representations received from the owner.
(8)If the municipality corrects the zoning map, it may only amend the map to show the correct zoning of the property.

20. Zoning scheme register

The municipality
(a)must record all departures, consent uses or other permissions granted and non-conforming uses in the register;
(b)may keep the register from the date of commencement of the zoning scheme in an electronic format; and
(c)must make the register available to members of the public for viewing.

21. Status of zoning map and exemption of the municipality from liability for an error

(1)The zoning map is the municipality’s record of the zoning of each land unit.
(2)A zoning recorded in the zoning map is presumed to be the correct zoning unless proved otherwise.
(3)A use right ceases to exist on the day it lapses in terms of this by-law or a previous zoning scheme even if the zoning map still records the use right as existing.
(4)The municipality is exempt from liability for any damage which may be caused by—
(a)an error in the zoning map; or
(b)an erroneous representation by the municipality about a use right or the zoning of a land unit.

22. Zoning versus ownership

(1)Notations on the zoning map are intended to indicate zonings and not land ownership.
(2)Land of which the ownership vests in a public authority may only be included in the authority zone if it is utilised for a purpose for which no other zone set out in Schedule 1 is appropriate.
(3)If any other zone in Schedule 1 is appropriate, the land must be zoned for that purpose, whether or not it is owned by a public authority.

Chapter IV
DEVELOPMENT MANAGEMENT

23. Determination of zoning

(1)The owner of land or his or her agent may apply in terms of section 25(2) to the municipality for the determination of a zoning for land referred to in section 34(1), (2) or (3) of the Land Use Planning Act.
(2)When the municipality considers an application in terms of subsection (1), it must have regard to the following—
(a)the lawful utilisation of the land, or the purpose for which it could be lawfully utilised immediately before the commencement of the Land Use Planning Act if it can be determined;
(b)the zoning, if any, that is most compatible with that utilisation or purpose and any applicable title deed condition;
(c)any departure or consent use that may be required in conjunction with that zoning;
(d)in the case of land that was vacant immediately before the commencement of the Land Use Planning Act, the utilisation that is permitted in terms of the title deed conditions or, where more than one land use is so permitted, one of such land uses determined by the municipality; and
(e)where the lawful utilisation of the land and the purpose for which it could be lawfully utilised immediately before the commencement of the Land Use Planning Act cannot be determined, the zoning that is the most desirable and compatible with any applicable title deed condition, together with any departure or consent use that may be required.
(3)If the lawful zoning of land contemplated in subsection (1) cannot be determined, the municipality must determine a zoning and serve notice of its intention in terms of section 56.
(4)A land use that commenced unlawfully, whether before or after the commencement of this by-law, may not be considered to be lawful.

24. Non-conforming uses

(1)A non-conforming use does not constitute an offence in terms of this by-law.
(2)A non-conforming use may continue as long as it remains otherwise lawful, subject to the following—
(a)if the non-conforming use is ceased for any reason for a period of more than twenty-four consecutive months, any subsequent utilisation of the property must comply with this by-law and the zoning scheme, with or without departures;
(b)an appropriate application contemplated in section 25(2) must be made for the alteration or extension of buildings or structures in respect of the non-conforming use;
(c)the owner bears the onus of proving that the non-conforming use right exists; and
(d)the use right is limited to the area of the building or land in respect of which the proven use right exists.
(3)Subject to subsection (2)(a) and (b), if an existing building that constitutes a non-conforming use is destroyed or damaged to the extent that it is necessary to demolish a substantial part of the building, the municipality may grant permission for the reconstruction of such building subject to conditions.

25. Land development requiring approval

(1)No person may commence, continue, or cause the commencement or continuation of, land development, other than the subdivision or consolidation of land referred to in section 34, without the approval of the municipality in terms of subsection (2).
(2)The owner of land or his or her agent must apply to the municipality in terms of this Chapter for the following in relation to the development of the land concerned—
(a)a rezoning of land;
(b)a permanent departure from the development parameters of the zoning scheme;
(c)a departure granted on a temporary basis to utilise land for a purpose not permitted in terms of the primary rights of the zoning applicable to the land;
(d)a subdivision of land that is not exempted in terms of section 34, including the registration of a servitude or lease agreement;
(e)a consolidation of land that is not exempted in terms of section 34;
(f)a removal, suspension or amendment of restrictive conditions in respect of a land unit;
(g)a permission required in terms of the zoning scheme;
(h)an amendment, deletion or imposition of conditions in respect of an existing approval;
(i)an extension of the validity period of an approval;
(j)an approval of an overlay zone as contemplated in the zoning scheme;
(k)an amendment or cancellation of an approved subdivision plan or part thereof, including a general plan or diagram;
(l)a permission required in terms of a condition of approval;
(m)a determination of a zoning;
(n)a closure of a public place or part thereof;
(o)a consent use contemplated in the zoning scheme;
(p)an occasional use of land;
(q)to disestablish a home owner’s association;
(r)to rectify a failure by a home owner’s association to meet its obligations in respect of the control over or maintenance of services;
(s)a permission required for the reconstruction of an existing building that constitutes a non-conforming use that is destroyed or damaged to the extent that it is necessary to demolish a substantial part of the building.
(3)If section 53 of the Land Use Planning Act is applicable to the land development, the owner or agent must also apply for approval of the land development in terms of that Act.
(4)If section 52 of the Spatial Planning and Land Use Management Act is applicable to the land development, the owner or agent must also apply for approval of the land development in terms of that Act.
(5)When an applicant or owner exercises a use right granted in terms of an approval, he or she must comply with the conditions of the approval and the applicable provisions of the zoning scheme.
(6)When the municipality on its own initiative intends to conduct land development or an activity contemplated in subsection (2), the decision on the application must be made by the Authorise Official and/or Tribunal in accordance with this Chapter and Chapter IV.

26. Continuation of application after change of ownership

If land that is the subject of an application is transferred to a new owner, the new owner may continue with the application as the successor in title to the previous owner and the new owner is regarded as the applicant for the purposes of this by-law.

27. Rezoning of land

(1)The municipality may, on its own initiative, rezone land of which it is not the owner to—
(a)provide a public service or to provide a public recreational space; or
(b)substitute a zoning scheme or part thereof for a zoning scheme in terms of which the land is not zoned in accordance with the utilisation thereof or existing use rights.
(2)An applicant, who wishes land to be rezoned, must submit an application to the municipality in terms of section 25(2).
(3)When the municipality creates an overlay zone for land it must comply with sections 12 and 13 of the Municipal Systems Act.
(4)Zoning may be made applicable to a land unit or part thereof and zoning need not follow cadastral boundaries.
(5)Subject to subsection (6), a rezoning approval contemplated in subsection (2) lapses after the applicable period from the date that the approval comes into operation if, within that period—
(a)the zoning is not utilised in accordance with the approval; or
(b)the following requirements have not been met—
(i)the approval by the municipality of a building plan envisaged for the utilisation of the approved use right; and
(ii)commencement of the construction of the building contemplated in subparagraph (i).
(6)An approval of a rezoning to sub divisional area contemplated in subsection 30(2) lapses after the applicable period from the date that the approval comes into operation if, within that period—
(a)a subdivision application is not submitted; and
(b)the conditions of approval are not complied with.
(7)If a subdivision application is submitted in respect of land that is zoned as sub divisional area, the zoning of sub divisional area lapses on the later date of the following dates—
(a)the date on which the subdivision is approved; or
(b)the date after the applicable period contemplated in subsection (6) including any extended period approved in terms of section 77.
(8)The approval of a rezoning to sub divisional area must include conditions that make provision for at least—
(a)density requirements;
(b)main land uses and the extent thereof; and
(c)a detailed phasing plan or a framework including—
(i)main transport routes;
(ii)main land uses;
(iii)bulk infrastructure;
(iv)requirements of organs of state;
(v)public open space requirements; and
(vi)physical development constraints.
(9)If a rezoning approval lapses, the zoning applicable to the land before the approval of the rezoning applies or, where no zoning existed before the approval of the rezoning, the municipality must determine a zoning in terms of section 23.

28. Departures

(1)An applicant may apply to the municipality in terms of section 25(2)—
(a)for a departure from the development parameters of a zoning or an overlay zone; or
(b)to utilise land on a temporary basis for a purpose not permitted in terms of the primary rights of the zoning applicable to the land for a period not exceeding five years.
(2)A departure contemplated in subsection (1)(a) lapses after the applicable period from the date that the approval comes into operation if, within that period—
(a)the departure is not utilised in accordance with the approval; or
(b)the following requirements have not been met—
(i)the approval by the municipality of a building plan envisaged for the utilisation of the approved departure; and
(ii)commencement of the construction of the building contemplated in subparagraph (i).
(3)The municipality may approve a departure contemplated in subsection (1)(b) for a period shorter than five years but, if a shorter period is approved, the period together with any extension approved in accordance with section 77 may not exceed five years;
(4)A temporary departure contemplated in subsection (1)(b) may not be approved more than once in respect of a particular use on a specific land unit.
(5)A temporary departure contemplated in subsection (1)(b) may include an improvement of land only if—
(a)the improvement is temporary in nature; and
(b)the land can, without further construction or demolition, revert to its previous lawful use upon the expiry of the use right.

29. Consent uses

(1)An applicant may apply to the municipality in terms of section 25(2) for a consent use contemplated in the zoning scheme.
(2)If the development parameters for the consent use that is being applied for are not defined in the zoning scheme, the municipality must determine the development parameters that apply to the consent use in terms of conditions of approval imposed in terms of section 76.
(3)A consent use may be approved permanently or for a period specified in the conditions of approval imposed in terms of section 76.
(4)A consent use approved for a specified period must not have the effect of preventing the property from being utilised in the future for the primary uses permitted in terms of the zoning of the land.
(5)A consent use contemplated in subsection (1) lapses after the applicable period from the date that the approval comes into operation if, within that period—
(a)the consent use is not utilised in accordance with the approval; or
(b)the following requirements have not been met—
(i)the approval by the municipality of a building plan envisaged for the utilisation of the approved consent use; and
(ii)commencement of the construction of the building contemplated in subparagraph (i).

30. Subdivision

(1)No person may subdivide land without the approval of the municipality in terms of section 25(2) unless the subdivision is exempted in terms of section 34.
(2)No application for subdivision involving a change of zoning may be considered by the municipality unless the land concerned is zoned as a sub divisional area.
(3)An applicant may submit a subdivision application simultaneously with an application for rezoning.
(4)The municipality must impose appropriate conditions in terms of section 76 relating to engineering services for an approval of a subdivision.
(5)If the municipality approves a subdivision, the applicant must submit a general plan or diagram to the Surveyor-General for approval, including proof to the satisfaction of the Surveyor-General of—
(a)the municipality’s decision to approve the subdivision;
(b)the conditions of approval imposed in terms of section 76; and
(c)the approved subdivision plan.
(6)The municipality must issue a certificate to the applicant or any other person on his or her written request to confirm that all the conditions of approval contemplated in section 31(1)(c) have been met, if the applicant has submitted the proof contemplated in that section.
(7)If the municipality issues a certificate referred to in subsection (6) in error, the owner is not absolved from complying with the obligations imposed in terms of the conditions.

31. Confirmation of subdivision

(1)A subdivision or part thereof is confirmed and cannot lapse when the following requirements are met within the period contemplated in section 32(1)—
(a)approval by the Surveyor-General of the general plan or diagram contemplated in section 30(5);
(b)completion of the installation of engineering services in accordance with the conditions contemplated in section 30(4) and other applicable legislation;
(c)proof to the satisfaction of the municipality that all the conditions of the approved subdivision that must be complied with before compliance with paragraph (d) have been met in respect of the area shown on the general plan or diagram; and
(d)registration of the transfer of ownership in terms of the Deeds Registries Act of the land unit shown on the diagram or of at least one new land unit shown on the general plan.
(2)Upon confirmation of a subdivision or part thereof in terms of subsection (1), zonings indicated on an approved subdivision plan are confirmed and cannot lapse.
(3)The municipality must in writing confirm to the applicant or any other person on his or her written request that a subdivision or part of a subdivision is confirmed if the applicant has to the satisfaction of the municipality submitted proof of compliance with the requirements referred to in subsection (1)(a) to (d) for the subdivision or part thereof.
(4)No building or structure may be constructed on a land unit forming part of an approved subdivision unless the subdivision is confirmed as contemplated in subsection (1) or the municipality approved the construction before the confirmation of the subdivision.

32. Lapsing of subdivision

(1)An approved subdivision lapses after the applicable period from the date that the approval comes into operation if the requirements contemplated in section 31(1)(a) to (d) have not been met within that period.
(2)If an applicant complies with section 31(1)(b) and (c) only in respect of a part of the land reflected on the general plan contemplated in section 31(1)(a), the applicant must withdraw the general plan and submit a new general plan to the Surveyor-General.
(3)If an approval of a subdivision or part thereof lapses in terms of subsection (1)—
(a)the municipality must—
(i)amend the zoning map and, where applicable, the register accordingly; and
(ii)notify the Surveyor-General accordingly; and
(b)the Surveyor-General must endorse the records of the Surveyor-General’s office to reflect the notification that the subdivision has lapsed.

33. Amendment or cancellation of subdivision plan

(1)The municipality may in terms of section 25(2) approve the amendment or cancellation of a subdivision plan, including conditions of approval, the general plan or diagram, in relation to land units shown on the general plan or diagram of which no transfer has been registered in terms of the Deeds Registries Act.
(2)When the municipality approves an application in terms of subsection (1), any public place that is no longer required by virtue of the approval must be closed in terms of section 36.
(3)The municipality must notify the Surveyor-General of an approval in terms of subsection (1) and the Surveyor-General must endorse the records of the Surveyor-General’s office to reflect the amendment or cancellation of the subdivision.
(4)An amended subdivision approval contemplated in subsection (1) is valid for the remainder of the period applicable to the initial approval of the subdivision before it was amended, reckoned from the date of approval of the amendment or cancellation in terms of subsection (1).

34. Exemption of certain subdivisions and consolidations

(1)The subdivision or consolidation of land does not require the approval of the municipality in the following cases—
(a)the implementation of a court ruling;
(b)an expropriation;
(c)a minor amendment to the common boundary between two or more land units if the resulting change in area of any of the land units does not exceed 10 per cent;
(d)the survey of closed streets or public open spaces in order to consolidate with an abutting land unit;
(e)the construction or alteration of a public or proclaimed street;
(f)the transfer land units to the municipality or an organ of state in terms of the Deeds Registries Act for municipal or government purposes;
(g)the registration of a servitude or lease agreement for—
(i)the provision or installation of water pipelines, electricity transmission lines, sewer pipelines, storm water pipes and canals, gas pipelines or oil and petroleum product pipelines by or on behalf of an organ of state or service provider;
(ii)the provision or installation of telecommunication lines by or on behalf of a licensed telecommunications operator;
(iii)the imposition of height restrictions;
(iv)the granting of a right of habitation, private right of way or usufruct; or
(v)an existing state- or municipality-owned housing scheme in order to make ownership of individual land units possible.
(h)the exclusive utilisation of land for agricultural purposes if the utilisation does not lead to urban expansion.
(2)Subject to subsection (5), the municipality may, by notice in the Provincial Gazette, exempt any other type of subdivision application from the need for approval in terms of this by-law if the exemption does not adversely affect the rights or legitimate expectations of any person.
(3)Subject to subsection (4), the municipality may, on application, exempt a subdivision from the need for approval in terms of this by-law if exceptional circumstances exist and if the exemption does not adversely affect the rights or legitimate expectations of any person.
(4)The municipality must endorse on the plan of subdivision that a subdivision is exempt from the need for approval in terms of this by-law.
(5)The exemptions in subsection (1) and the power to exempt in subsection (2) do not apply—
(a)if a rezoning or any other land use approval in terms of this by-law is required;
(b)when engineering services must be moved or provided; or
(c)if the subdivision is required to create individual land units for new housing.
(6)An owner of land or his or her agent must obtain a certificate from the municipality that certifies in writing that the subdivision or consolidation is exempted from the application of section 25, and sections 30 to 33 in the case of a subdivision, or sections 25, 41 and 42 in the case of a consolidation.
(7)The municipality must indicate on the subdivision plan, or on the diagram in respect of the consolidation, that the subdivision or consolidation is exempted from the application of the sections referred to in subsection (2).

35. Ownership of public places and land for engineering services and social facilities

(1)The ownership of land that is earmarked for a public place as shown on an approved subdivision plan vest in the municipality upon confirmation of the subdivision or a part thereof.
(2)The municipality may in terms of conditions imposed in terms of section 76 determine that land designated for the provision of municipal service infrastructure and amenities on an approved subdivision plan be transferred to the municipality upon confirmation of the subdivision or a part thereof.

36. Closure of public places

(1)The municipality may, on own initiative or on application, permanently close a public place or any part thereof in accordance with Chapter IV.
(2)An applicant who requires the closure of a public place, whether permanently or temporarily, must apply in terms of section 25(2) to the municipality.
(3)If any person lodges a claim against the municipality for loss or damage that he or she has allegedly suffered due to wrongdoing on the part of the municipality when it permanently closed a public place, the authorised employee must—
(a)require proof of negligence or any other wrongdoing on the part of the municipality which resulted in the loss or damage; and
(b)before any claim is paid or settled, obtain a full technical investigation report in respect of the circumstances that led to the closure of the public place to determine whether or not there has been negligence on the part of the municipality.
(4)The municipality may pay a claim if—
(a)the circumstances of the loss or damage reveal that the municipality acted wrongfully;
(b)the claimant has proved his or her loss or damage;
(c)the claimant has provided proof of a fair and reasonable quantum;
(d)no claim has been paid by personal insurance covering the same loss; and
(e)any relevant information as requested by the authorised employee has been received.
(5)The ownership of the land comprising any public place, or a part thereof, that is permanently closed in terms of this section continues to vest in the municipality unless the municipality determines otherwise.
(6)The municipal manager may, without complying with Chapter IV , temporarily close a public place
(a)for the purpose of, or pending, the construction,reconstruction or maintenance of the public place;
(b)for the purpose of, or pending, the construction, extension, maintenance or demolition of any building, structure, works or service alongside, on, across, through, over or under the public place;
(c)if the public place is in a state that is dangerous to the public;
(d)by reason of an emergency or public event that requires special measures for the control of traffic or crowds; or
(e)for any other reason that renders the temporary closing of the public place necessary or desirable.
(7)The municipality must notify the Surveyor-General of an approval in terms of subsection (1) and the Surveyor-General must endorse the records of the Surveyor-General’s office to reflect the closure of the public place.

37. Services arising from subdivision

Subsequent to the approval of an application for subdivision in terms of this by-law, the owner of any land unit originating from the subdivision must—
(a)allow without compensation that the following be conveyed across his or her land unit in respect of other land units originating from the subdivision—
(i)gas mains;
(ii)electricity cables;
(iii)telephone cables;
(iv)television cables;
(v)other electronic infrastructure;
(vi)main and other water pipes;
(vii)foul sewers;
(viii)storm-water pipes; and
(ix)ditches and channels;
(b)allow the following on his or her land unit if considered necessary and in the manner and position as may be reasonably required by the municipality
(i)surface installations such as mini-substations;
(ii)meter kiosks; and
(iii)service pillars;
(c)allow access to the land unit at any reasonable time for the purpose of constructing, altering, removing or inspecting any works referred to in paragraph (a) or (b); and
(d)receive material or permit excavation on the land unit as may be required to allow use of the full width of an abutting street and to provide a safe and proper slope to its bank where necessitated by differences between the level of the street as finally constructed and the level of the land unit unless he or she elects to build retaining walls to the satisfaction of and within a period to be determined by the municipality.

38. Certification by municipality

(1)A person may apply to the Registrar of Deeds to register the transfer of a land unit in the instances referred to in subsection (3)(a) to (c), only if the municipality has issued a certificate in terms of this section.
(2)The Registrar of Deeds may register the transfer of a land unit in the instances referred to in subsection (3)(a) to (c) only if the municipality has issued a certificate in terms of this section.
(3)The municipality must issue a certificate to transfer a land unit contemplated in subsections (1) and (2) if the owner provides the municipality with the following—
(a)where an owners’ association has been established in respect of that land unit, a conveyancer’s certificate confirming that money due by the transferor of the land unit to that owners’ association has been paid, or that provision has been made to the satisfaction of the owners’ association for the payment thereof;
(b)proof of payment of any existing contravention penalty due by the transferor of the land unit or proof of compliance with an instruction in a compliance notice issued to the transferor in terms of Chapter IX;
(c)in the case of the first transfer of a land unit arising from a subdivision, proof that—
(i)all common property arising from the subdivision has been transferred to the owners’ association as contemplated in section 39(3)(e) or will be transferred to the owners’ association simultaneously with the registration of the transfer of that land unit;
(ii)land needed for public purposes or other municipal infrastructure as contemplated in terms of a condition imposed under section 76 has been transferred to the municipality or will be transferred to the municipality simultaneously with the registration of the transfer of that land unit;
(iii)the engineering services and amenities that must be provided in connection with the subdivision are available; and
(iv)a certificate contemplated in section 30(6) has been issued by the municipality.

39. Owners’ associations

(1)The municipality may, when approving an application for a subdivision of land, impose conditions relating to the compulsory establishment of an owners’ association by the applicant for an area determined in the conditions.
(2)An owners’ association that comes into being by virtue of subsection (1) is a juristic person and must have a constitution.
(3)The constitution of an owners’ association must be approved by the municipality before the transfer of the first land unit and must make provision for—
(a)the owners’ association to formally represent the collective mutual interests of the area, suburb or neighbourhood set out in the constitution in accordance with the conditions of approval;
(b)control over and maintenance of buildings, services or amenities arising from the subdivision;
(c)the regulation of at least one annual meeting with its members;
(d)control over the design guidelines of the buildings and erven arising from the subdivision;
(e)the ownership by the owners’ association of all common property arising from the subdivision, including—
(i)private open spaces;
(ii)private roads; and
(iii)land required for services provided by the owners’ association;
(f)enforcement of conditions of approval or management plans;
(g)procedures to obtain the consent of the members of the owners’ association to transfer an erf in the event that the owners’ association ceases to function; and
(h)the implementation and enforcement by the owners’ association of the provisions of the constitution.
(4)The constitution of an owners’ association may have other objectives as set by the association but may not contain provisions that are in conflict with any law.
(5)The constitution of the owners’ association takes effect on the registration of the first land unit.
(6)An owners’ association may amend its constitution when necessary, but if an amendment affects the municipality or a provision referred to in subsection (3), the amendment must also be approved by the municipality.
(7)An owners’ association that comes into being by virtue of subsection (1)—
(a)has as its members all the owners of the land units arising from the subdivision and their successors in title, who are jointly liable for expenditure incurred in connection with the association; and
(b)is upon registration of the first land unit automatically established.
(8)The design guidelines contemplated in subsection (3)(d) may introduce more restrictive development rules than the rules provided for in the zoning scheme.

40. Owners’ associations that cease to function

(1)If an owners’ association ceases to function or carry out its obligations, the municipality or any affected person, including a member of the association, may apply—
(a)in terms of section 25(2)(q) to disestablish the owners’ association subject to—
(i)the amendment of the conditions of approval to remove the obligation to establish an owners’ association; and
(ii)the amendment of title conditions pertaining to the owners’ association, to remove any obligation in respect of an owners’ association;
(b)in terms of section 25(2)(r) for appropriate action by the municipality to rectify a failure of the owners’ association to meet any of its obligations in respect of the control over or maintenance of services contemplated in subsection 39(3)(b); or
(c)to the High Court to appoint an administrator who must exercise the powers of the owners’ association to the exclusion of the owners’ association.
(2)In considering an application contemplated in subsection (1)(a)(i) , the municipality must have regard to—
(a)the purpose of the owners’ association;
(b)who will take over the control over and maintenance of services for which the owners’ association is responsible; and
(c)the impact of the disestablishment of the owners’ association on the members of the owners’ association and the community concerned.
(3)The municipality or the affected person may recover from the members of the owners’ association the amount of any expenditure incurred by the municipality or that affected person, as the case may be, in respect of any action taken in terms of subsection (1).
(4)The amount of any expenditure so recovered is, for the purposes of section 39(7)(a), considered to be expenditure incurred in connection with the owners’ association.

41. Consolidation of land units

(1)No person may consolidate land without the approval of the municipality in terms of section 25(2) unless the consolidation is exempted in terms of section 34.
(2)If the municipality approves a consolidation, the applicant must submit a diagram to the Surveyor-General for approval, including proof to the satisfaction of the Surveyor-General of—
(a)the municipality’s decision to approve the consolidation;
(b)the conditions of approval imposed in terms of section 76; and
(c)the approved consolidation plan.
(3)If the municipality approves a consolidation, the municipality must—
(a)amend the zoning map and where applicable the register, accordingly; and
(b)issue a certificate to the effect that all conditions of consolidation have been complied with.

42. Lapsing of consolidation

(1)An approved consolidation of land units lapses if the consolidation is not registered in terms of the Deeds Registries Act within the applicable period from the date that the approval comes into operation.
(2)If an approval of a consolidation lapses in terms of subsection (1)—
(a)the municipality must—
(i)amend the zoning map, and where applicable the register, accordingly; and
(ii)notify the Surveyor-General accordingly; and
(b)the Surveyor-General must endorse the records of the Surveyor-General’s office to reflect the notification that the consolidation has lapsed.

43. Removal, suspension or amendment of restrictive conditions

(1)The municipality may, on its own initiative or on application in terms of section 25(2), remove, suspend or amend a restrictive condition.
(2)The municipality may remove, suspend or amend a restrictive condition
(a)permanently;
(b)for a period specified in the approval; or
(c)subject to conditions of approval.
(3)In addition to the procedures set out in Chapter IV, the owner must—
(a)submit a certified copy of the relevant title deed to the municipality; and
(b)where applicable, submit the bondholder’s consent to the application.
(4)The municipality must cause a notice of an application in terms of subsection (1) to be served on—
(a)all organs of state that may have an interest in the restrictive condition;
(b)a person whose rights or legitimate expectations will be affected by the approval of the application; and
(c)all persons mentioned in the title deed for whose benefit the restrictive condition applies.
(5)When the municipality considers the removal, suspension or amendment of a restrictive condition, the municipality must have regard to the following—
(a)the financial or other value of the rights in terms of the restrictive condition enjoyed by a person or entity, irrespective of whether these rights are personal or vest in the person as the owner of a dominant tenement;
(b)the personal benefits which accrue to the holder of rights in terms of the restrictive condition;
(c)the personal benefits which will accrue to the person seeking the removal, suspension or amendment of the restrictive condition if it is amended, suspended or removed;
(d)the social benefit of the restrictive condition remaining in place in its existing form;
(e)the social benefit of the removal, suspension or amendment of the restrictive condition; and
(f)whether the removal, suspension or amendment of the restrictive condition will completely remove all rights enjoyed by the beneficiary or only some of those rights.
(6)An approval to remove, suspend or amend a restrictive condition comes into operation—
(a)if no appeal has been lodged, after the expiry of the period contemplated in section 89(2) within which an appeal must be lodged; or
(b)if an appeal has been lodged, when the Appeal Authority has decided on the appeal.
(7)The municipality must cause a notice of the decision to amend, suspend or remove a restrictive condition to be published in the Provincial Gazette after the decision comes into operation as contemplated in subsection (6) and notify the Registrar of the decision.

44. Endorsements in connection with removal, suspension or amendment of restrictive conditions

(1)An applicant at whose instance a restrictive condition is removed, suspended or amended must, after the publication of a notice contemplated in section 43(7) in the Provincial Gazette, apply to the Registrar of Deeds to make the appropriate entries in, and endorsements on, any relevant register or title deed to reflect the removal suspension or amendment of the restrictive condition.
(2)The Registrar of Deeds may require proof of the removal, suspension or amendment of a restrictive condition from the applicant including the submission of the following to the Registrar of Deeds—
(a)a copy of the approval;
(b)the original title deed; and
(c)a copy of the notice contemplated in section 43(7) as published in the Provincial Gazette.

Chapter V
APPLICATION PROCEDURES

45. Manner and date of notification

(1)Any serving of a notice or notification or acknowledgement given in terms of this by-law must be in writing and may be issued to a person—
(a)by delivering it by hand to the person;
(b)by sending it by registered mail—
(i)to that person’s business or residential address; or
(ii)in the case of a juristic person, to its registered address or principal place of business;
(c)by means of data messages contemplated in the Electronic Communications and Transactions Act, 2002 (Act 25 of 2002), by sending a copy of the notice to the person, if the person has an email address or other electronic address; or
(d)where an address is unknown despite reasonable enquiry, by publishing it once in the Provincial Gazette and once in a local newspaper circulating in the area of that person’s last known residential or business address.
(2)The date of notification in respect of a notice served or given to a person in terms of this by-law—
(a)when it was served by certified or registered post, is the date of registration of the notice; and
(b)when it was delivered to that person personally, is the date of delivery to that person;
(c)when it was left at that person’s place of residence, work or business in the Republic with a person apparently over the age of sixteen years, is the date on which it was left with that person;
(d)when it was displayed in a conspicuous place on the property or premises to which it pertains, is the date that it is posted on that place; or
(e)when it was e-mailed or sent to an electronic address, is the date that it was received by that person as contemplated in the Electronic Communications and Transactions Act, 2002.
(3)The municipality may determine specific methods of service and notification in respect of applications and appeals including—
(a)conformation specifications relating to matters such as size, scale, colour, hard copy, number of copies, electronic format and file format;
(b)the manner of submission and communication with the municipality;
(c)the method by which a person may be notified;
(d)other information requirements; and
(e)other procedural requirements.

46. Procedures for applications

(1)An applicant must comply with the procedures in this Chapter and, where applicable, the specific procedures provided for in Chapter IV of this by-law.
(2)An applicant may apply simultaneously for different types of applications for land development in terms of section 25(2).

47. Pre-application consultation

(1)The municipality may require an owner of land who intends to submit an application or his or her agent to meet with the authorised employee and, where applicable, with employees of other relevant organs of state for a pre-application consultation before he or she submits an application to the municipality in order to determine the information and documents that must be submitted with the application.
(2)The municipality may issue guidelines regarding—
(a)applications that require a pre-application consultation;
(b)the nature of the information and documents that must be submitted with an application;
(c)the attendance of employees from the municipality or other organs of state at a pre-application consultation; and
(d)the procedures at a pre-application consultation.
(3)The municipality must keep minutes of the proceedings of a pre-application consultation.

48. Information required

(1)Subject to subsection (2), an application must be accompanied by the following information and documents—
(a)an application form provided by the municipality, completed and signed by the applicant;
(b)if the applicant is an agent, a power of attorney authorising the applicant to make the application on behalf of the owner;
(c)if the owner of the land is a company, closed corporation, trust, body corporate or owners’ association, proof that the person is authorised to act on behalf of the company, closed corporation, trust, body corporate or owners’ association;
(d)proof of registered ownership or any other relevant right held in the land concerned;
(e)the relevant bondholder’s consent if any;
(f)a written motivation for the application based on the criteria referred to in section 75;
(g)a copy of the Surveyor-General’s diagram of the property concerned or, if it does not exist, an extract from the relevant general plan;
(h)a locality plan and site development plan, if required, or a plan showing the proposed land development in its cadastral context;
(i)in the case of an application for the subdivision of land, copies of the subdivision plan showing the following—
(i)the location of the proposed land units;
(ii)the proposed zonings in respect of the proposed land units;
(iii)all existing structures on the property and abutting properties;
(iv)the proposed public places and the land needed for public purposes;
(v)the existing access points;
(vi)all servitudes;
(vii)contours with at least a one-meter interval or such other interval as may be approved by the municipality;
(viii)the street furniture;
(ix)the lamp, electricity and telephone posts;
(x)the electricity transformers and mini-substations;
(xi)the storm-water channels and catch pits;
(xii)the sewerage lines and connection points;
(xiii)any significant natural features; and
(xiv)all distances and areas to scale;
(j)proof of an agreement or permission if the proposed land development requires a servitude over land or access to a provincial or national road;
(k)any other documents or information that the municipality may require;
(l)proof of payment of application fees;
(m)a copy of the title deed of the land concerned;
(n)a conveyancer’s certificate indicating that the application is not restricted by any condition contained in the title deed pertaining to the application property or a copy of all historical title deeds; and
(o)where applicable, the minutes of a pre-application consultation in respect of the application.
(2)The municipality may at a pre-application consultation add or remove any information or documents contemplated in subsection (1) for a particular application.
(3)The municipality may issue guidelines regarding the submission of information, documents or procedural requirements.

49. Application fees

(1)An applicant must pay the application fees determined by the municipality before submitting an application in terms of this by-law.
(2)Application fees paid to the municipality are non-refundable and proof of payment of the application fees must accompany an application.

50. Grounds for refusing to accept application

The municipality may refuse to accept an application if—
(a)there is no proof of payment of the applicable fees; or
(b)the application is not in the form or does not contain the information or documents referred to in section 48.

51. Receipt of application and commencement of application process

(1)The municipality must—
(a)record the receipt of an application, in writing or by affixing a stamp on the application, on the day of receipt;
(b)verify whether the application complies with section 48; and
(c)notify the applicant in writing within fourteen days of receipt of the application
(i)that the application is complete and complies with section 48 and that the application process commences; or
(ii)of any information, documents or fees referred to in section 48 that are outstanding and that the applicant must provide to the municipality within 14 days of the date of notification.
(2)The municipality must within fourteen days of receipt of the outstanding information, documents or fees referred to in subsection (1)(c)(ii) notify the applicant in writing that the application is complete and that the application process commences.
(3)The municipality may refuse to consider the application if the applicant fails to provide the information or documents or pay the fees within the period contemplated in subsection (1)(c)(ii) .
(4)The municipality must notify the applicant in writing of a refusal to consider an application under subsection (3) and must close the application.
(5)An applicant has no right of appeal to the Appeal Authority in respect of a decision contemplated in subsection (3) to refuse to consider an application.
(6)If an applicant wishes to continue with an application that the municipality refused to consider under subsection (3), the applicant must apply again and pay the applicable application fees.
(7)The municipality must cause notice of the application to be given within 21 days from date on which the application process commences as contemplated in subsection (1)(c)(i) or (2).

52. Provision of additional information or documents

(1)The municipality must, within 30 days of receipt of an application that complies with section 48, notify the applicant in writing of any information or documents it requires in addition to the requirements contemplated in section 48.
(2)The applicant must provide the municipality with the additional information or documents contemplated in subsection (1) within 30 days of the date of notification or within the further period agreed to between the applicant and the municipality.
(3)If the applicant fails to provide the additional information or documents within the period contemplated in subsection (2), the municipality must consider the application without the information or documents and notify the applicant accordingly.
(4)The municipality must, within 21 days of receipt of the additional information or documents, if the applicant provided all the required information or documents, acknowledge receipt thereof and notify the applicant in writing that the application process proceeds or that further information, documents or fees are required as a result of the information or documents received.
(5)If the municipality notified the applicant that further information or documents are required as contemplated in subsection (4), subsections (2) and (3) apply to the further submission of information or documents.

53. Withdrawal of application or power of attorney

(1)An applicant may, at any time before the municipality makes a decision on an application submitted by the applicant, withdraw the application by giving written notice of the withdrawal to the municipality.
(2)The owner of land must in writing inform the municipality if he or she has withdrawn the power of attorney given to his or her former agent and confirm whether he or she will personally proceed with the application.

54. Public notice in accordance with other laws and integrated procedures

(1)The municipality may, on written request and motivation by an applicant, before notice is given of an application in terms of section 55 or 56, determine that—
(a)a public notice procedure carried out in terms of another law in respect of the application constitutes public notice for the purpose of an application made in terms of this by-law; or
(b)public notice of the application given in terms of this by-law may be published in accordance with the requirements for public notice applicable to a related application in terms of another law.
(2)If the municipality determines that an application may be published as contemplated in subsection (1)(b), an agreement must be entered into between the municipality and the relevant organs of state to facilitate the simultaneous publication of notices.

55. Publication of notices

(1)Subject to section 54, the municipality must, in accordance with subsection (2), cause public notice to be given of the following applications—
(a)an application for a rezoning or a rezoning on the initiative of the municipality;
(b)the subdivision of land larger than five hectares inside the outer limit of urban expansion as reflected in the municipal spatial development framework;
(c)the subdivision of land larger than one hectare outside the outer limit of urban expansion as reflected in the municipal spatial development framework;
(d)if the municipality has no approved municipal spatial development framework, the subdivision of land larger than five hectares inside the physical edge, including existing urban land use approvals, of the existing urban area;
(e)if the municipality has no approved municipal spatial development framework, the subdivision of land larger than one hectare outside the physical edge, including existing urban land use approvals, of the existing urban area;
(f)the closure of a public place;
(g)an application in respect of a restrictive condition;
(h)other applications that will materially affect the public interest or the interests of the community if approved.
(2)Public notice of an application referred to in subsection (1) must be given by—
(a)publishing a notice with the contents contemplated in section 57 in newspapers with a general circulation in the area concerned in at least two of the official languages of the Province most spoken in the area concerned;
(b)if there is no newspaper with a general circulation in the area, posting a notice with the contents contemplated in section 57, for at least the duration of the notice period, on the land concerned and on any other notice board, as may be determined by the municipality; and
(c)publishing a notice with the contents contemplated in section 57 on the municipality’s website.
(3)The municipality may require the applicant to attend to the publication as contemplated in subsection (2) of the public notice of an application.
(4)An applicant who publishes a notice in terms of this section must within the period determined by the municipality of publication of the notice provide the municipality with proof, as determined by the municipality that the notice was published in accordance with this section.
(5)When the municipality intends to conduct development or an activity contemplated in subsection (1)(a) to (h) it must cause a notice contemplated in subsection (2) to be published.

56. Serving of notices

(1)The municipality must cause a notice with the contents contemplated in section 57 to be served of at least the following applications—
(a)an application referred to in section 55(1);
(b)a determination of a zoning contemplated in section 23;
(c)an application for subdivision, amendment or cancellation of a subdivision contemplated in section 25(2)(d) and (k) respectively;
(d)an application for consolidation contemplated in section 25(2)(e);
(e)the amendment, deletion or imposition of a condition contemplated in section 25(2)(h).
(2)A notice contemplated in subsection (1) must be served—
(a)in accordance with section 45;
(b)in at least two of the official languages of the Province most spoken in the area concerned;
(c)on each person whose rights or legitimate expectations will be affected by the approval of the application; and
(d)on every owner of land adjoining the land concerned.
(3)The municipality may require the serving of a notice as contemplated in this section for any other application made in terms of this by-law and that is not listed in subsection (1).
(4)The municipality may require the applicant to attend to the serving of a notice as contemplated in subsection (2).
(5)An applicant who serves a notice in terms of this section must within the period determined by the municipality of the service of that notice provide the municipality with proof, as determined by the municipality, of the service of the notice in accordance with subsection (2).
(6)The municipality may require the applicant to make the application available for inspection by members of the public at a public place determined by the municipality.
(7)When the municipality intends to conduct development or an activity contemplated in subsection (1)(a) to (e) it must cause a notice to be served as contemplated in subsection (2).

57. Contents of notice

When notice of an application must be published or served in terms of this by-law, the notice must—
(a)provide the name and contact details of the applicant and the owner;
(b)identify the land or land unit to which the application relates by giving the property description and the physical address;
(c)state the intent and purpose of the application;
(d)state that a copy of the application and supporting documentation will be available for viewing during the hours and at the place mentioned in the notice;
(e)state the name and contact details of the person to whom comments must be addressed;
(f)invite members of the public to submit written comments, together with the reasons therefor, in respect of the application;
(g)state in which manner comments may be submitted;
(h)state the date by which the comments must be submitted, which date may not be less than 30 days from the date on which the notice was given; and
(i)state that any person who cannot write may during office hours come to an address stated in the notice where a named staff member of the municipality will assist those persons by transcribing their comments.

58. Other methods of public notice

(1)The municipality may, cause public notice to be given by one or more of the methods referred to in subsection (2)—
(a)to ensure additional public notice of applications listed in sections 55(1) if the municipality considers notice in accordance with sections 55 or 56 to be ineffective or expects that the notice would be ineffective; or
(b)to give public notice of any other application in terms of this by-law.
(2)Public notice contemplated in subsection (1) may be given by—
(a)displaying a notice contemplated in section 57 of a size of at least 60 centimetres by 42 centimetres on the frontage of the erf concerned or at any other conspicuous and easily accessible place on the erf, provided that—
(i)the notice is displayed for a minimum of 30 days during any period that the public may comment on the application; and
(ii)the applicant, within 30 days from the last day of display of the notice, submits to the municipality
(aa)a sworn affidavit confirming the maintenance of the notice for the prescribed period; and
(bb)at least two photos of the notice, one from close up and one from across the street;
(b)convening a meeting for the purpose of informing affected members of the public of the application;
(c)broadcasting information regarding the application on a local radio station in a specified language;
(d)holding an open day or public meeting to notify and inform affected members of the public of the application;
(e)publishing the application on the municipality’s website for the duration of the period within which the public may comment on the application; or
(f)obtaining letters of consent or objection to the application, provided that the letters are accompanied by acceptable evidence that the person signing the letter has been provided with correct and adequate information about the application.
(3)Additional public notice can be given simultaneously with notice given in accordance with sections 55 or 56 or thereafter.
(4)The municipality may require the applicant to attend to the publication of a notice as contemplated in subsection (2).
(5)An applicant who gives notice in terms of this section must within the period determined by the municipality of giving notice provide the municipality with proof, as determined by the municipality that notice has been given in accordance with subsection (2).

59. Requirements for petitions

(1)Comments in respect of an application submitted by the public in the form of a petition must clearly state—
(a)the contact details of the authorised representative of the signatories of the petition;
(b)the full name and physical address of each signatory; and
(c)the comments and reasons therefor.
(2)Notice to the person contemplated in subsection (1)(a) constitutes notice to all the signatories to the petition.

60. Requirements for the submission of comments

(1)A person may respond to a notice contemplated in sections 54, 55, 56 or 58 by commenting in writing in accordance with this section.
(2)Any comment made as a result of a notice process must be in writing and addressed to the person mentioned in the notice and must be submitted within the period stated in the notice and in the manner set out in this section.
(3)The comments must state the following—
(a)the name of the person concerned;
(b)the address or contact details at which the person or body concerned will receive notice or service of documents;
(c)the interest of the person in the application; and
(d)the reason for the comments.
(4)The reasons for any comment must be set out in sufficient detail in order to—
(a)indicate the facts and circumstances that explain the comments;
(b)where relevant demonstrate the undesirable effect the application will have if approved;
(c)where relevant demonstrate any aspect of the application that is not considered consistent with applicable policy; and
(d)enable the applicant to respond to the comments.
(5)The municipality may refuse to accept comments submitted after the closing date.

61. Intergovernmental participation process

(1)Subject to section 54, the municipality must, simultaneously with the notification to the applicant that an application is complete as contemplated in section 51(1)(c)(i) or (2) cause notice of the application together with a copy of the application concerned to be given to every municipal department and organ of state that has an interest in the application and request their comment on the application.
(2)An organ of state must submit written comment on an application to the municipal manager within 60 days of receiving a request therefor.

62. Amendments before approval

(1)An applicant may amend his or her application at any time before the approval of the application
(a)at the applicant’s own initiative;
(b)as a result of an objection, comment or representation submitted during the notice process; or
(c)at the request of the municipality.
(2)If an amendment to an application is material, the municipality must give notice of the amendment of an application to all municipal departments and other organs of state and service providers who commented on the application and request them to submit comments on the amended application within 21 days of the date of notification.
(3)If an amendment to an application is material, the municipality may require that further notice of the application be published or served in terms of section 54, 55, 56 or 58.

63. Further public notice

(1)The municipality may require that notice of an application be given again if more than 18 months have elapsed since the first public notice of the application and if the municipality has not considered the application.
(2)The municipality may, at any stage during the processing of the application if new information comes to its attention that is material to the consideration of the application, require—
(a)notice of an application to be given or served again in terms of section 54, 55, 56 or 58; and
(b)an application to be re-sent to municipal departments, other organs of state or service providers for comment.

64. Liability for cost of notice

The applicant is liable for the costs of publishing and serving notice of an application in terms of sections 54, 55, 56, 58, 62 or 63.

65. Right of applicant to reply

(1)Copies of all comments and other information submitted to the municipality must be given to the applicant within 14 days after the closing date for public comment together with a notice informing the applicant of his or her rights in terms of this section.
(2)The applicant may, within 30 days from the date on which he or she received the comments, submit a written reply thereto to the municipality.
(3)The applicant may, before the expiry of the period of 30 days referred to in subsection (2), apply to the municipality for an extension of the period to submit a written reply, to an additional period not exceeding 14 days.
(4)If the applicant does not submit a reply within the period of 30 days or within an additional period contemplated in subsection (3) if granted, the applicant is considered to have no comment.
(5)If the municipality requires additional information from the applicant as a result of the comments received, the information must be supplied within the further period as may be agreed upon between the applicant and the municipality.
(6)If the applicant does not provide the additional information within the period contemplated in subsection (5), section 52(3), read with the necessary changes, applies.

66. Written assessment of application

(1)An authorised employee must in writing assess an application in accordance with section 75 and make a recommendation to the decision-maker regarding the approval or refusal of the application.
(2)An assessment of an application must include a motivation for the recommendation and, where applicable, the proposed conditions of approval.

67. Decision-making period

(1)If the power to make a decision in respect of an application is delegated to an authorised employee and no integrated process in terms of another law is being followed, the authorised employee must decide on the application within 60 days, reckoned from—
(a)the last day for the submission of comments as contemplated in section 60(2) if no comments were submitted;
(b)the last day for the submission of the applicant’s reply to comments submitted as contemplated in section 65(2) or (3); or
(c)the last day for the submission of additional information as contemplated in section 65(5).
(2)If the power to make a decision is not delegated to an authorised employee and no integrated process in terms of another law is being followed, the Tribunal must decide on the application within 120 days, reckoned from the applicable date contemplated in subsection (1)(a) to (c).
(3)The authorised employee or Tribunal, as the case may be, may extend the period contemplated in subsection (1) or (2) in exceptional circumstances including the following—
(a)if an interested person has submitted a petition for intervener status;
(b)in the case of the Tribunal, if an oral hearing is to be held.

68. Failure to act within period

Subject to sections 51(5), an applicant may lodge an appeal with the Appeal Authority if the authorised employee or the Tribunal fails to decide on an application within the period referred to in section 67(1) or (2).

69. Powers to conduct routine inspections

(1)An authorised employee or the Tribunal may, in accordance with the requirements of this section, enter land or a building to conduct an inspection for the purpose of obtaining information to assess an application in terms of this by-law and to prepare a written assessment contemplated in section 66.
(2)When conducting an inspection, the authorised employee may—
(a)request that any record, document or item be produced to assist in the inspection;
(b)make copies of or take extracts from any document produced by virtue of paragraph (a) that is related to the inspection;
(c)on providing a receipt, remove a record, document or other item that is related to the inspection; or
(d)inspect any building or structure and make enquiries regarding that building or structure.
(3)No person may interfere with a person referred to in subsection (1) who is conducting an inspection as contemplated in subsection (1).
(4)The authorised employee or member of the Tribunal must, on request, produce identification showing that he or she is authorised to conduct the inspection.
(5)An inspection under subsection (1) must take place at a reasonable time and after reasonable notice has been given to the owner or occupier of the land or building.

70. Decisions on applications

An employee authorised by virtue of section 79, or the Tribunal, as the case may be, may in respect of an application contemplated in section 25(2)—
(a)approve, in whole or in part, or refuse that application;
(b)upon the approval of that application, impose conditions in terms of section 76;
(c)conduct any necessary inspection to assess an application in terms of section 69;
(d)in the case of the Tribunal, appoint a technical adviser to advise or assist in the performance of the Tribunal’s functions in terms of this by-law.

71. Notification and coming into operation of decision

(1)The municipality must, within 21 days of its decision, in writing notify the applicant and any person whose rights are affected by the decision of the decision, the reasons for the decision and their right to appeal, if applicable.
(2)A notice contemplated in subsection (1) must inform an applicant when an approval comes into operation.
(3)If the owner has appointed an agent, the owner must take steps to ensure that the agent notifies him or her of the decision of the municipality.
(4)An approval comes into operation only after the expiry of the period contemplated in section 89(2) within which an appeal must be lodged if no appeal has been lodged.
(5)Subject to subsection (6), the operation of the approval of an application that is the subject of an appeal is suspended pending the decision of the Appeal Authority on the appeal.
(6)If an appeal is lodged only against conditions imposed in terms of section 76, the Tribunal or the authorised employee who imposed the conditions may determine that the approval of the application is not suspended.

72. Duties of agent

(1)An agent must ensure that he or she has the contact details of the owner on whose behalf he or she is authorised to act.
(2)An agent may not provide information or make a statement in support of an application which information or statement he or she knows or believes to be misleading, false or inaccurate.

73. Errors and omissions

(1)The municipality may at any time correct an error in the wording of its decision if the correction does not change the decision or result in an alteration, insertion, suspension or deletion of a condition of approval.
(2)The municipality may, on its own initiative or on application by the applicant or interested party, upon good cause shown, condone an error in a procedure, if the condonation does not have a material adverse effect on, or unreasonably prejudice, any party.

74. Exemptions to facilitate expedited procedures

(1)The municipality may in writing and subject to section 60 of the Land Use Planning Act
(a)exempt a development from compliance with a provision of this by-law to reduce the financial or administrative burden of—
(i)integrated application processes contemplated in section 54;
(ii)the provision of housing with the assistance of a state subsidy; or
(iii)incremental upgrading of existing settlements;
(b)in an emergency situation authorise that a development may depart from any of the provisions of this by-law.
(2)If the Provincial Minister grants an exemption or authorisation to deviate from a provision of the Land Use Planning Act to the municipality in terms of section 60 of the Land Use Planning Act, the municipality is exempted from or authorised to deviate from any provision in this by-law that corresponds to the provision of the Land Use Planning Act in respect of which an exemption was granted or deviation was authorised.

Chapter VI
CRITERIA FOR DECISION-MAKING

75. General criteria for consideration of applications

(1)When the municipality considers an application, it must have regard to the following—
(a)the application submitted in terms of this by-law;
(b)the procedure followed in processing the application;
(c)the desirability of the proposed utilisation of land and any guidelines issued by the Provincial Minister regarding the desirability of proposed land uses;
(d)the comments in response to the notice of the application, including comments received from organs of state, municipal departments and the Provincial Minister in terms of section 45 of the Land Use Planning Act;
(e)the response by the applicant, if any, to the comments referred to in paragraph (d);
(f)investigations carried out in terms of other laws that are relevant to the consideration of the application;
(g)a registered planner’s written assessment in respect of an application for—
(i)a rezoning;
(ii)a subdivision of more than 20 cadastral units;
(iii)a removal, suspension or amendment of a restrictive condition if it relates to a change of land use;
(iv)an amendment, deletion or imposition of additional conditions in respect of an existing use right;
(v)an approval of an overlay zone contemplated in the zoning scheme;
(vi)a phasing, amendment or cancellation of a subdivision plan or part thereof;
(vii)a determination of a zoning;
(viii)a closure of a public place or part thereof;
(h)the impact of the proposed land development on municipal engineering services;
(i)the integrated development plan, including the municipal spatial development framework;
(j)the integrated development plan and spatial development framework of the district municipality, where applicable;
(k)the applicable local spatial development frameworks adopted by the municipality;
(l)the applicable structure plans;
(m)the applicable policies of the municipality that guide decision-making;
(n)the provincial spatial development framework;
(o)where applicable, a regional spatial development framework contemplated in section 18 of the Spatial Planning and Land Use Management Act or provincial regional spatial development framework;
(p)the policies, principles and the planning and development norms and criteria set by the national and provincial government;
(q)the matters referred to in section 42 of the Spatial Planning and Land Use Management Act;
(r)the principles referred to in Chapter Vl of the Land Use Planning Act; and
(s)the applicable provisions of the zoning scheme.
(2)Where required in terms of applicable development parameters or conditions of approval, the municipality must approve a site development plan if the site development plan
(a)is consistent with the development rules of the zoning;
(b)is consistent with the development rules of an overlay zone, if applicable;
(c)complies with the conditions of approval; and
(d)complies with this by-law.

76. Conditions of approval

(1)The municipality may approve an application subject to reasonable conditions that arise from the approval of the proposed utilisation of land.
(2)Conditions imposed in accordance with subsection (1) may include conditions relating to—
(a)the provision of engineering services and infrastructure;
(b)requirements relating to engineering services as contemplated in section 92 and 93;
(c)the cession of land or the payment of money;
(d)settlement restructuring;
(e)agricultural or heritage resource conservation;
(f)biodiversity conservation and management;
(g)the provision of housing with the assistance of a state subsidy, social facilities or social infrastructure;
(h)energy efficiency;
(i)requirements aimed at addressing climate change;
(j)the establishment of an owners’ association in respect of the approval of a subdivision;
(k)the provision of land needed by other organs of state;
(l)the endorsement in terms of section 31 of the Deeds Registries Act in respect of public places where the ownership thereof vests in the municipality;
(m)the provision of land needed for public places or the payment of money in lieu of the provision of land for that purpose;
(n)the extent of land to be ceded to the municipality for the purpose of a public open space or road as determined in accordance with a policy adopted by the municipality;
(o)the registration of public places in the name of the municipality;
(p)the transfer of ownership to the municipality of land needed for other public purposes;
(q)the implementation of a subdivision in phases;
(r)requirements of other organs of state;
(s)the submission of a construction management plan to manage the impact of the construction of a new building on the surrounding properties or on the environment;
(t)agreements to be entered into in respect of certain conditions;
(u)the phasing of a development, including lapsing clauses relating to such phasing;
(v)the delimitation of development parameters or land uses that are set for a particular zoning;
(w)the setting of a validity period and any extensions thereto;
(x)the setting of a period within which a particular condition must be met;
(y)requirements for an occasional use, which must include—
(i)parking and the number of ablution facilities required;
(ii)the maximum duration or occurrence of the occasional use; and
(iii)parameters relating to a consent use in terms of the zoning scheme;
(z)the payment of a contravention levy in respect of the unlawful utilisation of land.
(3)If the municipality imposes a condition contemplated in subsection (2)(a) or (b), an engineering services agreement must be concluded between the municipality and the owner of the land concerned before the construction of infrastructure commences on the land.
(4)A condition contemplated in subsection (2)(c) may require only a proportional contribution to municipal public expenditure according to the normal need therefor arising from the approval, as determined by the municipality in accordance with section 93(7) and any other applicable provincial norms and standards.
(5)Municipal public expenditure contemplated in subsection (4) includes but is not limited to municipal public expenditure for municipal service infrastructure and amenities relating to—
(a)community facilities, including play equipment, street furniture, crèches, clinics, sports fields, indoor sports facilities or community halls;
(b)nature conservation;
(c)energy conservation;
(d)climate change; or
(e)engineering services.
(6)Except for land needed for public places or internal engineering services, any additional land required by the municipality or other organs of state arising from an approved subdivision must be acquired subject to the applicable laws that provide for the acquisition or expropriation of land.
(7)An owners’ association or home owners’ association that came into being by virtue of a condition imposed under the Land Use Planning Ordinance, 1985 (Ordinance 15 of 1985) and that exists immediately before the commencement of this by-law is regarded as an owners’ association that came into being by virtue of a condition imposed by the municipality in accordance with this by-law.
(8)The municipality may not approve a land use application subject to a condition that approval in terms of other legislation is required.
(9)Conditions requiring a standard to be met must specifically refer to an approved or published standard.
(10)No conditions may be imposed that rely on a third party for fulfilment.
(11)If the municipality approves a land use application subject to conditions, it must specify which conditions must be complied with before the sale, development or transfer of the land.
(12)The municipality may, on its own initiative in terms of section 25(6) or on application in terms of section 25(2), amend, delete or impose additional conditions after having given due notice to the owner and any persons whose rights may be affected.

Chapter VII
EXTENSION OF VALIDITY PERIOD OF APPROVALS

77. Applications for extension of validity period

(1)Subject to section 43(2) of the Spatial Planning and Land Use Management Act, the municipality may approve an application for the extension of a validity period imposed in terms of a condition of approval, on a date before or after the expiry of the validity period of an approval, if the application for the extension of the period was submitted before the expiry of the validity period.
(2)When the municipality considers an application in terms of subsection (1), it must have regard to the following—
(a)whether the circumstances prevailing at the time of the original approval have materially changed;
(b)whether the legislative or policy requirements applicable to the approval that prevailed at the time of the original approval have materially changed; and
(c)whether there is a pending review application in court which may have an effect on the date of implementation of the approval.
(3)If there are material changes in circumstances or in legislative or policy requirements that will necessitate new conditions of approval if an extension of a validity period is approved, an application contemplated in section 25(2)(h) must be submitted for consideration before or simultaneously with the application for the extension of a validity period.
(4)The extended validity period takes effect on and is reckoned from the expiry date of the validity period applicable to the original approval or from the expiry date of the previously extended validity period approved in terms of this by-law.

Chapter VIII
MUNICIPAL PLANNING DECISION-MAKING STRUCTURES

78. Municipal planning decision-making structures

Applications are decided by—
(a)an authorised employee who has been authorised by the municipality to consider and determine the applications contemplated in subsection 79(1);
(b)the Tribunal, where the powers and duties to consider and determine an application have not been delegated to an authorised employee contemplated in section 79(2); or
(c)the Appeal Authority where an appeal has been lodged against a decision of the authorised employee or the Tribunal.

79. Consideration of applications

(1)The municipality may categorise applications for consideration and determination by an authorised employee and must delegate the powers and duties to decide on those applications to that authorised employee.
(2)The Tribunal considers and determines all applications, other than those in respect of which the powers and duties to consider and determine them have been assigned and delegated to an authorised employee in terms of subsection (1) .

80. Establishment of tribunal

(1)The municipality must—
(a)establish a Municipal Planning Tribunal for its municipal area;
(b)by agreement with one or more municipalities establish a joint Municipal Planning Tribunal; or
(c)agree to the establishment of a district Municipal Planning Tribunal by the district municipality.
(2)An agreement referred to in subsection (1)(b) or (c) must provide for—
(a)the composition of the Tribunal;
(b)the terms and conditions of appointment of members of the Tribunal;
(c)the determination of rules and procedures at meetings of the Tribunal; and
(d)other matters as may be prescribed in terms of the Spatial Planning and Land Use Management Act.

81. Composition of tribunal for municipal area

(1)A Tribunal established in terms of subsection 80(1)(a) must consist of at least the following members appointed by the Council
(a)three employees in the full-time service of the municipality; and
(b)two persons who are not employees of the municipality or councillors.
(2)The members of the Tribunal must have knowledge and experience of land use planning or the law related thereto and be representative of a broad range of appropriate experience and expertise.
(3)A member of the Tribunal appointed in terms of subsection (1)(b) may be—
(a)an official or employee of—
(i)any department of state or administration in the national or provincial sphere of government;
(ii)a government business enterprise;
(iii)a public entity;
(iv)organised local government as envisaged in the Constitution;
(v)an organisation created by government to provide municipal support;
(vi)a non-governmental organisation; and
(vii)any other organ of state not provided for in subparagraph (i) to (iv); or
(b)an individual in his or her own capacity.

82. Process for appointment of members for tribunal for municipal area

(1)The members of the Tribunal referred to in subsection 81(1)(b) may be appointed by the Council only after the municipality has—
(a)in the case of an official or employee contemplated in section 81(3)(a), extended a written invitation to nominate an official or employee to serve on the Tribunal to the departments in the national and provincial sphere of government, other organs of state and organisations referred to in section 81(3)(a); and
(b)in the case of member contemplated in 81(3)(b), by notice in a newspaper in circulation in the municipal area, invited interested parties to submit, within the period stated in the notice, names of persons who meet the requirements to be so appointed.
(2)An invitation for nominations must—
(a)request sufficient information to enable the municipality to evaluate the knowledge and experience of the nominee;
(b)request a written nomination in the form that the municipality determines that complies with subsection (3).
(3)A nomination in response to an invitation must—
(a)permit self-nomination or provide for acceptance of the nomination by the nominee;
(b)include confirmation by the nominee that he or she is not disqualified from serving as a member in terms of section 84;
(c)include agreement by the nominee that the municipality may verify all the information provided by the nominee;
(d)include a statement that the nominee will be obliged to commit to and uphold a code of conduct if her or she is appointed; and
(e)provide for a closing date for nominations which date may be no less than 14 days from the date of publication of the invitation in terms of subsection(1)(b) or the written invitation in terms of subsection (1)(a) and no nominations submitted after that date may be evaluated by the municipality.
(4)If no or insufficient nominations are received or if the nominees do not possess the requisite knowledge and skills or comply with any additional criteria which may have been determined by the municipality, the municipality must invite nominations for a second time and follow the process required for the invitation for nominations referred to in this section.
(5)If after the second invitation for nominations, no or insufficient nominations are received or if the nominees do not possess the requisite knowledge and skills or comply with any additional criteria which may have been determined by the municipality, the executive authority of the municipality must designate persons who possess the requisite knowledge and skills and comply with any additional criteria which may have been determined by the municipality and appoint the person.
(6)Nominations submitted to the municipality by virtue of subsection (1) must be submitted in writing in the form determined by the municipality and must contain the contents referred to in subsection (3).
(7)The municipality must convene an evaluation panel consisting of officials in the employ of the municipality to evaluate nominations that comply with this section as received by the municipality and determine the terms of reference of that evaluation panel.
(8)The Council must appoint the members of the Tribunal after having regard to—
(a)the recommendations of the evaluation panel;
(b)the knowledge and experience of candidates in respect of land use planning or the law related thereto;
(c)the requirement that the members of the Tribunal must be representative of a broad range of appropriate experience and expertise;
(d)the powers and duties of the Tribunal; and
(e)the policy of the municipality in respect of the promotion of persons previously disadvantaged by unfair discrimination.
(9)The Council may not appoint any person to the Tribunal if that person—
(a)was not nominated in accordance with the provisions of this section;
(b)is disqualified from appointment as contemplated in section 84; or
(c)if he or she does not possess the knowledge or experience required in terms of section 81(2).
(10)The Council must designate from among the members of the Tribunal
(a)the chairperson of the Tribunal; and
(b)another member as deputy chairperson, to act as chairperson of the Tribunal when the chairperson is absent or unable to perform his or her duties.
(11)The municipal manager must—
(a)inform the members in writing of their appointment;
(b)obtain written confirmation from the Council that the Council is satisfied that the Tribunal is in a position to commence its operations; and
(c)after receipt of the confirmation referred to in paragraph (a), publish a notice in the Provincial Gazette of the following—
(i)the name of each member of the Tribunal;
(ii)the date on which the appointment of each member takes effect;
(iii)the term of office of each member; and
(iv)the date that the Tribunal will commence its operation.
(12)The Tribunal may commence its operations only after publication of the notice contemplated in subsection (11)(c).

83. Term of office and conditions of service of members of tribunal for municipal area

(1)A member of a Tribunal contemplated in section 80(1)(a)—
(a)is appointed for five years or a shorter period as the municipality may determine; and
(b)may be appointed for further terms, subject to section 37(1) of the Spatial Planning and Land Use Management Act.
(2)The office of a member becomes vacant if—
(a)the member is absent from two consecutive meetings of the Tribunal without the leave of the chairperson of the Tribunal;
(b)the member tenders his or her resignation in writing to the chairperson of the Tribunal;
(c)the member is removed from the Tribunal under subsection (3); or
(d)the member dies.
(3)The Council may, after having given the member an opportunity to be heard, remove a member of the Tribunal if—
(a)sufficient grounds exist for his or her removal;
(b)the member contravenes the code of conduct referred to in section 86;
(c)the member becomes subject to a disqualification from membership of the Tribunal as referred to in section 84.
(4)A vacancy on the Tribunal must be filled by the Council in terms of section 81 and 82.
(5)A member who is appointed by virtue of subsection (4) holds office for the unexpired part of the period for which the member he or she replaces was appointed.
(6)Members of the Tribunal referred to in section 81(1)(b) must be appointed on the terms and conditions and must be paid the remuneration and allowances and be reimbursed for expenses, as determined by the Council.
(7)An official of the municipality appointed in terms of section 81(1)(a) as a member of the Tribunal
(a)may only serve as member of the Tribunal for as long as he or she is in the full-time employ of the municipality;
(b)is bound by the conditions of service determined in his or her contract of employment and is not entitled to additional remuneration, allowances, leave or sick leave or any other employee benefit as a result of his or her membership on the Tribunal.
(8)A person appointed in terms of section 81(1)(b) as a member of the Tribunal
(a)is not an employee on the staff establishment of the municipality;
(b)in the case of a person referred to in section 81(3)(a), is bound by the conditions of service determined in his or her contract of employment and is not entitled to additional remuneration, allowances, leave or sick leave or any other employee benefit as a result of his or her membership of the Tribunal;
(c)performs the specific tasks in respect of the consideration of an application allocated to him or her by the chairperson of the Tribunal;
(d)sits at such meetings of the Tribunal that requires his or her relevant knowledge and experience as determined by the chairperson of the Tribunal;
(e)in the case of a person referred to in section 81(3)(b), is entitled to a seating and travel allowance as determined by the municipality for each meeting of the Tribunal that he or she is required to attend; and
(f)in the case of a person referred to in section 81(3)(b), is not entitled to overtime, annual leave, sick leave, maternity leave, family responsibility leave, study leave, special leave, a performance bonus, medical scheme contribution, pension, motor vehicle or any other benefit to which a municipal employee is entitled to.
(9)The allowances referred to in subsection (8)(e) are subject to taxation in accordance with the normal tax rules that are issued by the South African Revenue Service.

84. Disqualification from membership of tribunal

(1)A person may not be appointed or continue to serve as a member of the Tribunal if that person—
(a)is not a citizen or permanent resident of the Republic of South Africa;
(b)is a member of Parliament, a provincial legislature, a Municipal Council or a House of Traditional Leaders;
(c)is an unrehabilitated insolvent;
(d)has been declared by a court of law to be mentally incompetent or has been detained under the Mental Health Care Act, 2002 (Act 17 of 2002);
(e)has at any time been convicted of an offence involving dishonesty;
(f)has at any time been removed from an office of trust on account of misconduct;
(g)has previously been removed from a tribunal for a breach of the Spatial Planning and Land Use Management Act or this by-law;
(h)has been found guilty of misconduct, incapacity or incompetence; or
(i)fails to comply with the Spatial Planning and Land Use Management Act or this by-law.
(2)A member must vacate office if that member becomes subject to a disqualification as contemplated in subsection (1).
(3)A member of a Tribunal
(a)must make full disclosure of any conflict of interest, including any potential conflict; and
(b)may not attend, participate or vote in any proceedings of the Tribunal in relation to any matter in respect of which the member has a conflict of interest.
(4)For the purposes of this section, a member has a conflict of interest if—
(a)the member, a family member, partner or business associate of the member is the applicant or has a pecuniary or other interest in the matter before the Tribunal;
(b)the member has any other interest that may preclude or may reasonably be perceived as precluding the member from performing the functions of the member in a fair, unbiased and proper manner;
(c)the member is an official in the employ of national, provincial or local government, if the department by which such an official is employed, has a direct or substantial interest in the outcome of the matter.
(5)The Council may at any time remove any member of the Tribunal from office—
(a)if there are reasonable grounds justifying the removal; or
(b)where a member has been disqualified in terms of subsection (1), after giving such a member an opportunity to be heard.
(6)If a member’s appointment is terminated or the member resigns, the Council may appoint a person to fill the vacancy for the unexpired portion of the vacating member’s term of office, in accordance with sections 81 and 82.

85. Meetings of tribunal for municipal area

(1)Subject to section 88, the Tribunal contemplated in section 80(1)(a) must determine its own internal arrangements, proceedings and procedures and those of its committees by drafting rules for—
(a)the convening of meetings;
(b)the procedure at meetings; and
(c)the frequency of meetings.
(2)The Tribunal may constitute itself to comprise one or more panels to determine—
(a)applications in specific geographical areas;
(b)applications in specific areas within the municipality; or
(c)a particular application or type or category of application.
(3)In this section, unless the context indicates otherwise, ‘the Tribunal’ includes a panel of the Tribunal contemplated in subsection (2).
(4)The Tribunal must meet at the time and place determined by the chairperson or in the case of a panel, the presiding officer provided that it must meet at least once per month if there is an application to consider.
(5)If the Tribunal constitutes itself to comprise a panel, the Tribunal must designate at least three members of the Tribunal to be members of that panel, of whom one must at least be a member contemplated in section 81(1)(b).
(6)A quorum for a meeting of the Tribunal is the simple majority of its appointed members.
(7)A quorum for a meeting of a panel of the Tribunal is—
(a)the greater of a simple majority of its designated members or
(b)three, if the panel consist of only three members.
(8)Meetings of the Tribunal or a panel of the Tribunal must be held as contemplated in this section and section 88 in accordance with the rules of the Tribunal.

86. Code of conduct for members of tribunal for municipal area

(1)The code of conduct in Schedule 1 applies to every member of a Tribunal contemplated in section 81(1).
(2)If a member contravenes the code of conduct, the Council may—
(a)in the case of member contemplated in section 81(1)(a), institute disciplinary proceedings against the member;
(b)remove the member from office.

87. Administrator for tribunal for municipal area

(1)The municipal manager must appoint or designate an employee as the Administrator and other staff for the Tribunal contemplated in section 70(1)(a) in terms of the Municipal Systems Act.
(2)The Administrator must—
(a)liaise with the relevant Tribunal members and the parties concerned regarding any application filed with, or other proceedings of, the Tribunal;
(b)maintain a diary of meetings of the Tribunal;
(c)allocate a meeting date for, and application number to, an application;
(d)arrange the attendance of members of the Tribunal at meetings;
(e)arrange venues for Tribunal meetings;
(f)perform the administrative functions in connection with the proceedings of the Tribunal;
(g)ensure that the proceedings of the Tribunal are conducted efficiently and in accordance with the directions of the chairperson of the Tribunal;
(h)arrange the affairs of the Tribunal so as to ensure that time is available to liaise with other organs of state regarding the alignment of integrated applications and authorisations;
(i)notify the parties concerned of decisions and procedural directives given by the Tribunal;
(j)keep a record of all applications submitted to the Tribunal as well as the outcome of each, including—
(i)decisions of the Tribunal;
(ii)on-site inspections and any matter recorded as a result thereof;
(iii)reasons for decisions; and
(iv)proceedings of the Tribunal; and
(k)keep records by any means as the Tribunal may deem expedient.

88. Functioning of tribunal for municipal area

(1)The meetings of the Tribunal contemplated in section 85(1)(a) must be held at the times and places as the chairperson may determine.
(2)If an applicant or a person whose rights or legitimate expectations will be affected by the approval of an application, requests to make a verbal representation at a meeting of the Tribunal, he or she must submit a written request to the Administrator at least 14 days before that meeting.
(3)The Chairperson may approve a request contemplated in subsection (2), subject to reasonable conditions.
(4)An application may be considered by the Tribunal by means of—
(a)the consideration of the written application and comments; or
(b)an oral hearing.
(5)The application may be considered in terms of subsection(4)(a) if it appears to the Tribunal that the issues for determination of the application can be adequately determined in the absence of the parties by considering the documents or other material lodged with or provided to it.
(6)An oral hearing may be held—
(a)if it appears to the Tribunal that the issues for determination of the application cannot be adequately determined in the absence of the parties by considering the documents or other material lodged with or provided to it; or
(b)if such hearing would assist in the expeditious and fair disposal of the application.
(7)If appropriate in the circumstances, the oral hearing may be held by electronic means.

89. Appeals

(1)The executive mayoral committee is the Appeal Authority in respect of decisions of the Tribunal or an authorised employee contemplated in sections 78(a) or (b) and a failure to decide on an application as contemplated in section 68.
(2)A person whose rights are affected by a decision contemplated in subsection (1) may appeal in writing to the Appeal Authority within 21 days of notification of the decision.
(3)An applicant may appeal in writing to the Appeal Authority in respect of the failure of the Tribunal or an authorised employee to make a decision within the period contemplated in section 67(1) or (2), any time after the expiry of the period contemplated in those sections.
(4)An appeal is lodged by serving the appeal on the municipal manager in the form determined by the municipality and, in the case of an appeal contemplated in subsection (2), within the period contemplated in subsection (2).
(5)When the Appeal Authority considers an appeal, it must have regard to—
(a)the provisions of section 75(1), read with the necessary changes; and
(b)the comments of the Provincial Minister contemplated in section 52 of the Land Use Planning Act.

90. Procedure for appeal

(1)An appeal is invalid if—
(a)in the case of an appeal contemplated in in section 89(2), it is not lodged within the period referred to in that section; and
(b)it does not comply with this section.
(2)An appeal must set out the following—
(a)the grounds for the appeal which may include the following grounds—
(i)that the administrative action was not procedurally fair as contemplated in the Promotion of Administrative Justice Act, 2000 (Act 3 of 2000);
(ii)grounds relating to the merits of the land development or land use application on which the appellant believes the Tribunal or authorised employee erred in coming to the conclusion that the Tribunal or authorised employee did, as the case may be;
(b)whether the appeal is lodged against the whole decision or a part of the decision;
(c)if the appeal is lodged against a part of the decision, a description of the part;
(d)if the appeal is lodged against a condition of approval, a description of the condition;
(e)the factual or legal findings that the appellant relies on;
(f)the relief sought by the appellant; and
(g)any issue that the appellant wishes the Appeal Authority to consider in making its decision; or
(h)in the case of an appeal in respect of the failure of a decision-maker to make a decision, the facts that prove the failure;
(3)An applicant who lodges an appeal must submit proof of payment of appeal fees as may be determined by the municipality to the municipal manager.
(4)An applicant who lodges an appeal must simultaneously serve notice of the appeal on any person who commented on the application concerned and any other person as the municipality may determine.
(5)The notice must be served in accordance with section 45.
(6)The notice contemplated in subsection (5) must invite persons to comment on the appeal within 21 days of being notified of the appeal.
(7)The appellant must submit proof of service of the notice as contemplated in subsection (5) to the municipal manager within 14 days of the date of notification.
(8)If a person other than the applicant lodges an appeal, he or she must submit proof of payment of appeal fees as determined by the municipality to the municipal manager, and the municipal manager must give written notice of the appeal to the applicant within 14 days of receipt thereof.
(9)An applicant who has received notice of an appeal in terms of subsection (8) may submit comment on the appeal to the municipality within 21 days of being notified.
(10)The municipality may refuse to accept any comments on an appeal after the closing date for those comments.
(11)The municipal manager—
(a)may request the Provincial Minister within 14 days of the receipt of an appeal to comment in writing on the appeal within 60 days of receipt of the request;
(b)must notify and request the Provincial Minister within 14 days of the receipt of an appeal to comment on the appeal within 60 days of receipt of the request in respect of appeals relating to the following applications—
(i)a development outside the municipality’s planned outer limit of urban expansion as reflected in its municipal spatial development framework;
(ii)if the municipality has no approved municipal spatial development framework, a development outside the physical edge, including existing urban land use approvals, of the existing urban area;
(iii)a rezoning of land zoned for agricultural or conservation purposes;
(iv)any category of land use applications as may be prescribed by the Provincial Minister; and
(c)must on receipt of an appeal in terms of this section notify the applicant in writing whether or not the operation of the approval of the application is suspended.
(12)An authorised employee must draft a report assessing an appeal and must submit it to the municipal manager within—
(a)30 days of the closing date for comment requested in terms of subsection (6) and (9), if no comment was requested in terms of subsection (11); or
(b)30 days of the closing date for comments requested in terms of subsection (11).
(13)The municipal manager must within 14 days of receiving the report contemplated in subsection (12) submit the appeal to the Appeal Authority.
(14)The municipal manager or an employee designated by him or her must—
(a)liaise with the Appeal Authority and the parties concerned regarding any appeal lodged with the Appeal Authority;
(b)maintain a diary of meetings of the Appeal Authority;
(c)allocate a meeting date for, and appeal number to, an appeal;
(d)arrange the attendance of members of the Appeal Authority at meetings;
(e)arrange venues for the Appeal Authority;
(f)perform the administrative functions in connection with the proceedings of the Appeal Authority;
(g)ensure that the proceedings of the Appeal Authority are conducted efficiently and in accordance with the directions of the Appeal Authority;
(h)arrange the affairs of the Appeal Authority so as to ensure that time is available to liaise with other organs of state regarding the alignment of integrated appeal procedures;
(i)notify the parties concerned of decisions and procedural directives given by the Appeal Authority;
(j)keep a record of all appeals lodged as well as the outcome of each, including—
(i)decisions of the Appeal Authority;
(ii)on-site inspections and any matter recorded as a result thereof;
(iii)reasons for decisions; and
(iv)proceedings of the Appeal Authority; and
(v)keep records by any means as the Appeal Authority may deem expedient.
(15)An appellant may, at any time before the Appeal Authority makes a decision on an appeal submitted by the appellant, withdraw the appeal by giving written notice of the withdrawal to the municipal manager.
(16)The owner of land must in writing inform the municipality if he or she has withdrawn the power of attorney given to his or her former agent and confirm whether he or she will personally proceed with the appeal.

91. Consideration by appeal authority

(1)An appeal may be considered by the Appeal Authority by means of—
(a)the consideration of the written appeal and comments; or
(b)an oral hearing.
(2)The appeal may be considered in terms of subsection (1)(a) if it appears to the Appeal Authority that the issues for determination of the appeal can be adequately determined in the absence of the parties by considering the documents or other material lodged with or provided to it.
(3)An oral hearing may be held—
(a)if it appears to the Appeal Authority that the issues for determination of the appeal cannot be adequately determined in the absence of the parties by considering the documents or other material lodged with or provided to it; or
(b)if such hearing would assist in the expeditious and fair disposal of the appeal.
(4)If appropriate in the circumstances, the oral hearing may be held by electronic means.
(5)If the Appeal Authority decides to hold an oral hearing, any party to the appeal proceedings may appear in person or may be represented by another person.
(6)The Appeal Authority must ensure that every party to a proceeding before the Appeal Authority is given an opportunity to present his or her case, whether in writing or orally as contemplated in subsections (2) and (3) and, in particular, to inspect any documents to which the appeal authority proposes to have regard in reaching a decision in the proceeding and to make submissions in relation to those documents.
(7)The Appeal Authority must—
(a)consider and determine all appeals lawfully submitted to it;
(b)confirm, vary or revoke the decision of the Tribunal or authorised employee;
(c)provide reasons for any decision made by it;
(d)give directions relevant to its functions to the municipality;
(e)keep a record of all its proceedings; and
(f)determine whether the appeal falls within its jurisdiction.
(8)Subject to subsection (12), the Appeal Authority must decide on an appeal within 60 days of receipt of the assessment report contemplated in section 90(13)
(9)If the Appeal Authority revokes a decision of the Tribunal or authorised employee it may—
(a)remit the matter to the Tribunal or authorised employee
(i)if there was an error in the process which is unfair and which cannot be corrected by the Appeal Authority; and
(ii)with instructions regarding the correction of the error; or
(b)replace the decision with any decision it regards necessary.
(10)The Appeal Authority may appoint a technical adviser to advise or assist it with regard to a matter forming part of the appeal.
(11)The Appeal Authority must within 21 days from the date of its decision notify the parties to an appeal in writing of—
(a)the decision and the reasons therefor; and
(b)if the decision on an appeal upholds an approval, notify the applicant in writing that he or she may act on the approval.
(12)The Appeal Authority may extend the period contemplated in subsection (8) in exceptional circumstances including the following—
(a)if an interested person has submitted a petition for intervener status;
(b)if an oral hearing is to be held.

Chapter IX
PROVISION OF ENGINEERING SERVICES

92. Responsibility for provision of engineering services

(1)An applicant is responsible for the provision, installation and costs of internal engineering services required for a development once an application is approved.
(2)The municipality is responsible for the provision and installation of external engineering services.
(3)If the municipality is not the provider of an engineering service, the applicant must satisfy the municipality that adequate arrangements have been made with the relevant service provider for the provision of that service.
(4)The municipality may enter into a written agreement with an applicant to provide that—
(a)the applicant is responsible for the provision, installation and costs of external engineering service instead of paying the applicable development charges; or
(b)the applicant is responsible for the provision, installation and costs of external engineering service and that the fair and reasonable costs of the external engineering service may be set off against the development charges payable by the applicant.

93. Development charges

(1)The applicant must pay development charges to the municipality in respect of the provision and installation of external engineering services and parking.
(2)These external engineering services for which development charges are payable must be set out in a policy adopted and annually reviewed by the municipality.
(3)The amount of the development charges payable by an applicant must be calculated in accordance with the policy adopted by the municipality.
(4)The date by which development charges must be paid and the means of payment must be specified in the conditions of approval.
(5)The development charges imposed are subject to escalation at the rate calculated in accordance with the policy on development charges.
(6)The municipal manager must annually submit a report to the Council on the development charges paid to the municipality, together with a statement of the expenditure of the amount and the purpose of the expenditure.
(7)When determining the contribution contemplated in section 76(4) and (5), the municipality must have regard to provincial norms and standards as well as—
(a)the municipal service infrastructure and amenities for the land concerned that are needed for the approved land use;
(b)the public expenditure on that infrastructure and those amenities incurred in the past and that facilitates the approved land use;
(c)the public expenditure on that infrastructure and those amenities that may arise from the approved land use;
(d)money in respect of contributions contemplated in section 76(4) paid in the past by the owner of the land concerned; and
(e)money in respect of contributions contemplated in section 76(4) to be paid in the future by the owner of the land concerned.

94. Land for parks, open spaces, parking and other uses

(1)When the municipality approves an application for the use of land for business or residential purposes, the municipality may require the applicant to provide land for parks, public open spaces or parking.
(2)The extent of land required for parks, public open spaces or parking is determined by the municipality in accordance with a policy adopted by the municipality.
(3)The land required for parks, public open spaces or parking must be provided within the land area of the application or may, with the consent of the municipality, be provided elsewhere within the municipal area.
(4)When an application is approved without the required provision of land for parks, open spaces or parking within the land area of the development, the applicant may be required to pay money to the municipality in lieu of the provision of land.

Chapter X
ENFORCEMENT

95. Enforcement

(1)The municipality must comply and enforce compliance with—
(a)the provisions of this by-law;
(b)the provisions of a zoning scheme;
(c)conditions imposed in terms of this by-law or previous planning legislation; and
(d)title deed conditions.
(2)The municipality may not do anything that is in conflict with subsection (1).

96. Offences and penalties

(1)A person is guilty of an offence and is liable on conviction to a fine or imprisonment not exceeding 20 years or to both a fine and such imprisonment if he or she—
(a)contravenes or fails to comply with sections 25(1) and (5) , 30(1), 31(4), 41(1), 69(3), 72(2) or 98(2);
(b)utilises land in a manner other than prescribed by a zoning scheme without the approval of the municipality;
(c)upon registration of the first land unit arising from a subdivision, fails to transfer all common property arising from the subdivision to the owners’ association;
(d)supplies particulars, information or answers in an application, or in an appeal against a decision on an application, or in any documentation or representation related to an application or an appeal, knowing it to be false, incorrect or misleading or not believing them to be correct;
(e)falsely professes to be an authorised employee or the interpreter or assistant of an authorised employee; or
(f)hinders or interferes with an authorised employee in the exercise of any power or the performance of any duty of that employee.
(2)An owner who permits his or her land to be used in a manner set out in subsection (1)(b) and who does not cease that use or take reasonable steps to ensure that the use ceases, or whopermits a person to contravene the zoning scheme, is guilty of an offence and liable upon conviction to a fine or imprisonment or to both a fine and such imprisonment.
(3)A person convicted of an offence in terms of this by-law who, after conviction, continues with the action in respect of which he or she was so convicted, is guilty of a continuing offence and liable upon conviction to imprisonment for a period not exceeding three months or to an equivalent fine or to both such fine and imprisonment, in respect of each day on which he or she so continues or has continued with that act or omission.
(4)The municipality must adopt fines and contravention levies to be imposed in the enforcement of this by-law.

97. Serving of compliance notices

(1)The municipality must serve a compliance notice on a person if it has reasonable grounds to suspect that the person or owner is guilty of an offence in terms of section 96.
(2)A compliance notice must instruct the occupier and owner to cease the unlawful utilisation of land or construction activity or both, without delay or within the period determined by the municipality, and may include an instruction to—
(a)demolish, remove or alter any building, structure or work unlawfully erected or constructed or to rehabilitate the land or restore the building concerned to its original form or to cease the activity, as the case may be, within the period determined by the municipal manager;
(b)submit an application for the approval of the utilisation of the land or construction activity in terms of this by-law within 30 days of the service of the compliance notice and to pay the contravention penalty within 30 days after approval of the utilisation; or
(c)rectify the contravention of or non-compliance with a condition of approval within a specified period.
(3)A person who has received a compliance notice with an instruction contemplated in subsection (2)(a) may not submit an application in terms of subsection (2)(b).
(4)An instruction to submit an application in terms of subsection (2)(b) must not be construed as an indication that the application will be approved.
(5)In the event that the application submitted in terms of subsection (2)(b) is refused, the owner must demolish, remove or alter the building, structure or work unlawfully erected or constructed and rehabilitate the land or restore the building.
(6)A person who received a compliance notice in terms of this section may object to the notice by submitting written representations to the municipality within 30 days of receipt of the notice.

98. Contents of compliance notice

(1)A compliance notice must—
(a)identify the person to whom it is addressed;
(b)describe the alleged unlawful utilisation of land or construction activity concerned and the land on which it is occurring or has occurred;
(c)state that the utilisation of land or construction activity is unlawful and inform the person of the particular offence contemplated in section 96 which that person allegedly has committed or is committing by the continuation of that activity on the land;
(d)state the steps that the person must take and the period within which those steps must be taken;
(e)state anything which the person may not do and the period during which the person may not do it;
(f)make provision for the person to submit representations in terms of section 99 with the contact person stated in the notice; and
(g)issue a warning to the effect that—
(i)the person may be prosecuted for and convicted of an offence contemplated in section 96;
(ii)on conviction of an offence, the person will be liable for the penalty as provided for;
(iii)the person may be required by an order of court to demolish, remove or alter any building, structure or work unlawfully erected or constructed or to rehabilitate the land or restore the building concerned or to cease the activity;
(iv)in the case of a contravention relating to a consent use or temporary departure, the approval may be withdrawn;
(v)in the case of an application for authorisation of the activity or development parameter, the contravention penalty in the amount as stated in the notice, including any costs incurred by the municipality, may be imposed.
(2)Any person on whom a compliance notice is served must comply with that notice within the period stated in the notice unless the person has objected to the notice in terms of section 89 and the municipality has not decided on the matter in terms of that section or the municipality has agreed to suspend the operation of the compliance notice in terms of section 99(2).

99. Objections to compliance notice

(1)Any person or owner who receives a compliance notice in terms of section 97 may object to the notice by making written representations to the municipality within 30 days of the date of notification.
(2)After consideration of any objections or representations made in terms of subsection (1) and any other relevant information, the municipality
(a)may suspend, confirm, vary or withdraw a compliance notice or any part of the compliance notice; and
(b)must specify the period within which the person to whom the compliance notice is addressed must comply with any part of the compliance notice that is confirmed or varied.

100. Failure to comply with compliance notice

If a person fails to comply with a compliance notice, the municipality may—
(a)lay a criminal charge against the person;
(b)apply to the High Court for an order—
(i)restraining that person from continuing the unlawful utilisation of the land;
(ii)directing that person to, without the payment of compensation—
(aa)demolish, remove or alter any building, structure or work unlawfully erected or constructed; or
(bb)rehabilitate the land concerned;
(c)in the case of consent use or a temporary departure, withdraw the approval granted and act in terms of section 97.

101. Compliance certificates

(1)An authorised employee who is satisfied that the owner or occupier of any land or premises has complied with a compliance notice may issue a certificate, in the manner and form determined by the municipality, to confirm the compliance.
(2)The authorised employee must submit a report to the municipality regarding his or her findings contemplated in subsection (1) and the issuing of a compliance certificate.

102. Urgent matters

(1)The municipality does not have to comply with sections 97(6), 98(1)(f) and 99 in a case where an unlawful utilisation of land must be stopped urgently and may issue a compliance notice calling upon the person or owner to cease the unlawful utilisation of land immediately.
(2)If the person or owner fails to cease the unlawful utilisation of land immediately, the municipality may apply to the High Court for an urgent interdict or any other relief necessary.

103. General powers and functions of authorised employees

(1)An authorised employee may, with the permission of the occupier or owner of land without a warrant and without previous notice, enter upon land or premises or enter a building at any reasonable time for the purpose of ensuring compliance with this by-law.
(2)An authorised employee must be in possession of proof that he or she has been designated as an authorised employee for the purposes of subsection (1).
(3)An authorised employee may be accompanied by an interpreter, a police official or any other person who may be able to assist with the inspection.

104. Powers of entry, search and seizure

(1)In ensuring compliance with this by-law in terms of section 97, an authorised employee may—
(a)question any person on land or premises entered upon or in a building entered, who, in the opinion of the authorised employee, may be able to provide information on a matter that relates to the enforcement of this by-law;
(b)question any person on that land or those premises or in that building about any act or omission in respect of which there is a reasonable suspicion that it constitutes—
(i)an offence in terms of this by-law;
(ii)a contravention of this by-law; or
(iii)a contravention of an approval or a term or condition of that approval;
(c)question that person about any structure, object, document, book, record, written or electronic information or inspect any structure, object, document, book or record which may be relevant for the purpose of this subsection;
(d)copy or make extracts from any document, book, record, written or electronic information referred to in paragraph (c), or remove that document, book, record or written or electronic information in order to make copies thereof or extracts therefrom;
(e)require that person to produce or deliver to a place specified by the authorised employee any document, book, record, written or electronic information referred to in paragraph (c) for inspection;
(f)examine that document, book, record, written or electronic information or make a copy thereof or an extract therefrom;
(g)require from that person an explanation of any entry in that document, book, record, written or electronic information;
(h)inspect any article, substance, plant or machinery which is or was on the land, or any work performed on the land or any condition prevalent on the land, or remove for examination or analysis any article, substance, plant or machinery or a part or sample thereof;
(i)take photographs or make audio-visual recordings of anything or any person on that land or those premises or in that building relevant to the purposes of the investigation; or
(j)seize a book, record, written or electronic information referred to in paragraph (c) or article, substance, plant or machinery referred to in paragraph (h) or a part or sample thereof that in his or her opinion may serve as evidence at the trial of the person to be charged with an offence under this by-law or the common law, provided that the user of the article, substance, plant or machinery on the land or premises or in the building concerned may make copies of that book, record or document before the seizure.
(2)When an authorised employee removes or seizes any article, substance, plant or machinery, book, record or other document as contemplated in this section, he or she must issue a receipt to the owner or person in control thereof.
(3)An authorised employee may not have a direct or indirect personal or private interest in the matter to be investigated.

105. Warrant of entry for enforcement purposes

(1)A judge of a High Court or a magistrate for the district in which the land is situated may, at the request of the municipality, issue a warrant to enter upon the land or premises or building if—
(a)the prior permission of the occupier or owner of land cannot be obtained after reasonable attempts; or
(b)the purpose of the inspection would be frustrated by the occupier or owner’s prior knowledge thereof.
(2)A warrant may be issued only if it appears to the Judge or Magistrate from information on oath that there are reasonable grounds for believing that—
(a)an authorised employee has been refused entry to land or a building that he or she is entitled to inspect;
(b)an authorised employee will be refused entry to land or a building that he or she is entitled to inspect;
(c)an offence contemplated in section 96 is occurring or has occurred and an inspection of the premises is likely to yield information pertaining to that offence; or
(d)the inspection is reasonably necessary for the purposes of this by-law.
(3)A warrant must authorise the municipality to enter upon the land or premises or to enter the building to take any of the measures referred to in section 104 as specified in the warrant, on one occasion only, and that entry must occur—
(a)within one month of the date on which the warrant was issued; and
(b)at a reasonable time, except where the warrant was issued on grounds of urgency.

106. Regard to decency and order

The entry upon land or premises or in a building under this Chapter must be conducted with strict regard to decency and order, which must include regard to—
(a)a person’s right to respect for and protection of his or her dignity;
(b)the right to freedom and security of the person; and
(c)a person’s right to personal privacy.

107. Enforcement litigation

Whether or not the municipality lays criminal charges against a person for an offence contemplated in section 96, and despite section 97, the municipality may apply to a competent court for an interdict or any other appropriate order, including an order compelling that person to—
(a)demolish, remove or alter any building, structure or work unlawfully erected or constructed;
(b)rehabilitate the land concerned; or
(c)cease the unlawful utilisation of land.

Chapter XI
GENERAL PROVISIONS

108. Naming and numbering of streets

(1)If as a result of the approval of a development application streets or roads are created, whether public or private, the municipality must approve the naming of streets and must allocate a street number to each of the erven or land units located in such street or road.
(2)The proposed names of the streets and numbers must be submitted as part of an application for subdivision.
(3)In considering the naming of streets, the municipality must take into account the relevant policies regarding street naming and numbering.
(4)The municipality must notify the Surveyor-General of the approval of new streets as a result of the approval of an amendment or cancellation of a subdivision in terms of section 33 and the Surveyor-General must endorse the records of the Surveyor-General’s Office to reflect the amendment or cancellation of the street names on an approved general plan.

109. Repeal and replacement

(1)The Swartland Municipality by-law on Municipal Land Use Planning published in Provincial Gazette No 7420 dated 3 July 2015 is hereby repealed.
(2)The Swartland Municipality: Town Planning Scheme Regulations published in Provincial Gazette No 37 dated 20 March 2014 are hereby repealed and replaced with the Scheme Regulations set out in Schedule 2.

110. Short title and commencement

This by-law is called the Swartland Municipality: Municipal Land Use Planning By-law and comes into operation on the date of publication thereof in the Provincial Gazette.

Schedule 1

CODE OF CONDUCT FOR MEMBERS OF TRIBUNAL

1. General conduct

A member of the Tribunal must at all times—
(a)act in accordance with the principles of accountability and transparency;
(b)disclose his or her personal interests in any decision to be made in the planning process in which he or she serves or has been requested to serve;
(c)abstain completely from direct or indirect participation as an advisor or decision-maker in any matter in which he or she has a personal interest and leave any chamber in which such matter is under deliberation unless the personal interest has been made a matter of public record and the Council has given written approval and has expressly authorised his or her participation.

2. A member of the Tribunal may not—

(a)use his or her position or privileges as Tribunal member or confidential information obtained as a Tribunal member, for private gain or to improperly benefit another person; and
(b)participate in a decision concerning a matter in which that Tribunal member or that member’s spouse, partner or business associate, has a direct or indirect personal interest or private business interest.

3. Gifts

A member of the Tribunal may not receive or seek gifts, favours or any other offer under circumstances in which it might reasonably be inferred that the gifts, favours or offers are intended or expected to influence that member’s objectivity as an advisor or decision-maker in the planning process.

4. Undue influence

A member of the Tribunal may not—
(a)use the power of his or her office to seek or obtain special advantage for private gain or to improperly benefit another person that is not in the public interest;
(b)use confidential information acquired in the course of his or her duties to further a personal interest;
(c)disclose confidential information acquired in the course of his or her duties unless required by law to do so or by circumstances to prevent substantial prejudice or damage to another person;
(d)and commit a deliberately wrongful act that reflects adversely on the Tribunal, the municipality, the government or the planning profession by seeking business by stating or implying that he or she is prepared, willing or able to influence decisions of the Tribunal by improper means.

Schedule 2

SWARTLAND MUNICIPALITY ZONING SCHEME

1. Definitions

In this Zoning Scheme, unless the context indicates otherwise:

A

"abattoir", means a place where animals including poultry or sea animals, are slaughtered and prepared for distribution to butcheries and food markets;"access gate ", means a prominent access to or exit from an urban area or a specific part of an urban area which features man- made or natural characteristics and creates a strong feeling of arrival or departure;"access steps and porches", means access steps and porches for a building, including low walls and railings, if such steps and porches are not located within the retaining walls of the building;"activity corridor", means an area of generally higher intensity urban use or land suitable for intensification, parallel to and on both sides of an activity spine, and includes any higher order transport routes such as railway lines and through roads;"activity spine", means a public street, incorporating an existing or planned public transport route, and adjacent land used or intended for mixed use development;"additional dwelling unit", means a dwelling unit that may be erected on an agricultural land unit where a permitted dwelling house has first been erected, in a zone where ’additional dwelling unit’ is a consent use, provided that:
(i)the additional dwelling unit shall be erected on the same cadastral unit as the dwelling house that has first been erected;
(ii)the additional dwelling unit shall comply with the other relevant requirements specified in this Zoning Scheme;
(iii)the additional dwelling unit must have a lesser floor area than the dwelling house that has first been erected;
(iv)in the Agricultural Zone 1, a maximum of one additional dwelling unit can be permitted if the extent of the cadastral unit does not exceed 10 ha, or if it does exceed 10 ha, then a maximum of 2, 3, 4 or 5 additional dwelling units will be permitted if the extent of the cadastral unit exceeds 10, 20, 30 or 40 ha respectively;
"adult entertainment enterprise", means an establishment where films, photographs, books or magazines are hired or sold for payment, or where pornographic live performances occur for payment with the focus on the display or description of pornographic or erotic sexual activities or human genitals and includes an escort agency and a massage parlour, except a massage enterprise where massaging for medical or sport purposes is practised by a registered medical practitioner or similar professional person;"advertise", with regard to a matter in terms of this Zoning Scheme, means to serve a notice to each owner of land having an interest in the matter in the opinion of the municipal manager and whose address he knows or is able to obtain and, if the said municipal manager so decides, to publish a notice in the Provincial Gazette and in the press wherein:
(i)the location where and the hours during which particulars of the matter will be available for inspection, are indicated, and
(ii)it is mentioned that objections may be lodged with a person as indicated before a date which is also indicated, at a time which is at least 21 days after the date on which the notice is so served or published,
and "advertisement" unless otherwise indicated has a corresponding meaning;"advertisement", when used in the context of outdoor advertising, means any visible representation of a word, name, letter, figure or object or an abbreviation of a word or name of any sign or symbol, or light which is not intended solely for illumination or warning against danger;"advertisement structure", means any physical structure constructed to display an advertisement;"Advertising on Roads and Ribbon Development Act", means the Advertising on Roads and Ribbon Development Act, 1940 (Act 21 of 1940);"agriculture", means the cultivation of land for crops and other plants, or the keeping and breeding of animals, including sea animals, including oysters and abalone, or the operation of a game farm, including use on an intensive basis of the natural veld or land, and includes only such activities and buildings (including those for accommodation), as are reasonably connected with the main farming activities, but excludes an agricultural industry;"agricultural industry", means a business or an enterprise for the treatment and processing of agricultural products on or separate from the farm unit where those agricultural products are grown, due to the nature, perishability or fragility of such agricultural products, and includes, inter alia, wineries and farm packing stores, but does not include service trades;"agri-village", means a private settlement of restricted size, established and managed as a lawful enterprise in a rural area and where tenure is restricted to bona fide rural workers from the farms and forestry or conservation areas in the vicinity and their dependants, and which represents a partnership between land owners, labour and the state;"air rights" or "underground rights", means rights to development, of a defined space above or below a public street, railway line or land area utilised by another mode of transport usage, for specific purposes;"animal hospital", means a place where animals are treated and cared for, and ‘animal clinic’ has the same meaning;"antenna", means any system of wires, poles, rods, reflective surfaces, satellite dish, TV antenna or similar devices, used to transmit or receive electronic communication signals or electro-magnetic waves;"appeal", means an application to the competent authority for review of a decision made;"aquaculture", means the cultivation of water fauna and flora in artificially constructed dams including nets and containers in natural ponds and streams;"area of control", when used in the context of outdoor advertisement, means an area where advertising control must be applied, such as maximum, partial or minimum control, in accordance with the visual sensitivity of the area and the traffic safety conditions;"associated", when used in the context of an associated use or purpose, means a use, purpose, building or activity which is ancillary and subservient to the lawful dominant use of the land, and "associate" has the same meaning;"atrium", means a covered courtyard comprising a void within a building that extends for one storey or more in height, but does not contain floors that penetrate into the void; an atrium contains a floor and a roof or ceiling;"authority usage", means a use which is practised by or on behalf of a public authority and the characteristics of which are such that it cannot be classified or defined under the other uses of this Zoning Scheme, and includes a use practised by:
(i)the State, such as military training centres and installations, police stations, correctional institutions or jails;
(ii)the Provincial Government, such as road stations or road camps;
(iii)the municipality, such as fire services, waste water treatment works, waste control sites, reservoirs, composting installations or water purification works or a municipal office with related uses such as accommodation for staff who are required to be on standby for emergencies, or
(iv)a public utility, such as a telecommunication facility;
"average depth", in relation to a land unit, means:
(i)the average perpendicular distance between a public street or road and the points at which the side boundaries meet the rear boundary, or
(ii)in the case of a corner site, the average perpendicular distance between the public street or road and the point at which the side boundaries meet, or
(iii)in the case of a panhandle site or a very irregular shaped land unit, the average depth as determined by the municipality;
"average width", in relation to a land, unit means:
(i)the average of the length of the street boundary and the rear boundary, or
(ii)in the case of a corner site, the average of the length of the shortest street boundary or the opposite side boundary, or
(iii)in the case of a panhandle site or a very irregular shaped land unit, the average width as determined by the municipality;

B

"balcony", means a floor projecting outside a building at a level higher than that of the ground floor, enclosed only by low walls, railings or by main containing walls of rooms abutting such projecting floor, and includes a roof, if any, over such a floor and pillars supporting the roof;"basement", means part of a building of where the finished floor level is at least 2m below natural ground level, or the ceiling not more than 1m above, a height halfway between the highest and lowest natural ground level immediately contiguous to the building;"base zone", means that zone which determines the basic land use and land use provisions for land in terms of this Zoning Scheme, before the application of any overlay zone;"bed and breakfast establishment", means a dwelling house or second dwelling unit in which the occupant of the dwelling unit provides lodging and meals for compensation to transient guests who have permanent residence elsewhere, provided that:
(i)the dominant use of the dwelling unit concerned shall remain for the living accommodation of a single family, and
(ii)the land unit complies with the provisions pertaining to a bed and breakfast establishment;
"billboard", means any screen or board bigger than 4,5m2 supported by a freestanding structure, which is to be used or is intended to be used for the purpose of posting, displaying or exhibiting an advertisement, which is also commonly known as an advertising board, whose main function is to advertise non-locality bound products, activities or services;"bioregion", means a geographical area that contains an entire ecosystem or several established ecosystems characterised by particular land-forms, vegetative cover, human culture and history;"biosphere reserve", means areas of land, coastal or marine ecosystems or a combination thereof, which are internationally recognised within the framework of the Man and Biosphere Programme of the United Nations Educational, Scientific and Cultural Organisation (UNESCO);"boarding house", means a building, where lodging is provided with or without meals, together with the outbuildings as are normally used therewith, and includes an old age home, a building in which rooms are rented for residential purposes and a residential club, but does not include a dwelling house, group housing, a double dwelling house, an institution, a place of instruction, a hotel, a bed and breakfast establishment or flats;"boat launching facility", means land used to launch boats into the water and to retrieve boats from the water and includes a boat ramp and slip-way;"bottle store", means premises where alcoholic drinks are sold primarily in the retail trade on an off-sales basis, and includes an off-sales facility which is under the same management as a licensed hotel;"boundary", in relation to a land unit, means one of the cadastral lines separating such unit from another land unit or from a public street or road;"builder’s yard", means premises used for the storage of material and equipment which:
(i)is required or is normally used for construction work;
(ii)was obtained from demolition of structures or from excavations of land, or
(iii)is necessary for or is normally used in land improvements, such as storage of material used for building roads, for the installation of essential services, or for any other construction work (e.g. of sand or bricks), whether for public or private purposes;
"building", without in any way limiting its ordinary meaning, includes:
(i)any roofed structure;
(ii)any external stairs, steps or landings of a building and any gallery, canopy, balcony, stoep, veranda, porch or similar feature of a building;
(iii)any walls or railings enclosing any feature referred to in (ii),
and
(iv)any other portion of a building;
"building line", means an imaginary line on a land unit, which defines a distance from a specified boundary, within which the erection of buildings or structures (excluding a boundary fence) are completely or partially prohibited;"business premises", means a building or land from which business is conducted, and includes a shop, supermarket, restaurant, office, financial institution and buildings for similar uses, but does not include a place of assembly, place of entertainment, institution, service station, motor repair garage, industry, industrial hive, noxious trade, risk activity, adult entertainment enterprise or bottle store;

C

"cadastral line", means a line representing the official boundary of a land unit as registered in the Deeds Office or as a record on a diagram or general plan approved by the Surveyor General;"camping site", means land on which tents and caravans are utilised as accommodation for visitors, and includes ablution, cooking area, barbeque and other facilities for the use of such visitors;"caravan", means a vehicle which has been well equipped for use by persons for living or sleeping purposes, regardless of whether such vehicle is a trailer or not and which can be readily moved;"caravan park", means a land unit or part thereof where tents or caravans for short-term holiday accommodation have been planned for and can be accommodated, and includes ablution, cooking and other facilities for the occupants of the caravans;"carriageway crossing", means a motor vehicle entrance or exit way, or a combined entrance and exit way, from a land unit to a public road;"carport", means a roofed structure, for the housing of motor vehicles, which is open at the entrance and on at least one other side;"car wash", means a building or structure equipped for the purpose of washing motor vehicles;"cellular telecommunication infrastructure", means, but is not limited to, one of the following:
(i)an antenna support structure including any solid or lattice structure, mast pole, monopole, anchor tower, lattice tower, freestanding tower or any structure designed and primarily used to support the antenna;
(ii)antenna structures including any system for wires, poles, rods or similar devices used for the transmission or reception of electromagnetic waves, attached to a building or mast, and includes cabling between the equipment room and the antenna;
(iii)a base station site including the land, antenna support structures, and all associated infrastructure such as the antenna, microwave dish, equipment room and access road;
(iv)an equipment room including a structure to house cellular telecommunication equipment associated with an antenna support structure and/or antenna, which may be a separate building used exclusively for the equipment or may be a container, room or multiple rooms within a building with another specific use, or
(v)microwave dishes including any device incorporating a reflective surface that is solid, open mesh, or bar configured in the shape of a shallow dish, cone, horn or something similar, and is used to transmit and/or receive electromagnetic waves;
"cemetery", means a place where the dead are buried and may include buildings that are necessary for the religious, administrative and clerical uses associated therewith, but does not include a crematorium;"clinic", means an institution where patients are given medical treatment or medical-related advice, and may include a medical centre, an outpatients’ centre or a wellness centre with associated uses, provided that a clinic does not contain live-in facilities for more than twenty persons, including staff and patients;"commencement date", means the date of commencement of this Zoning Scheme;"commercial antenna", means a facility, incorporating a high mast, for the transmission and/or receiving of electromagnetic waves, and includes a television station, a radio station and a cellular communication tower;"commercial pet kennel", means kennel services for dogs, cats and similar animals, and includes commercial breeding or boarding kennels, pet motels and training centres;"common boundary", in relation to a land unit, means a common boundary with an adjoining land unit and does not include a street boundary;"composting", the creation and sale of fertiliser that is allowed to form out of the storing and special treatment of organic residue;"conference facility", means a place of gathering, which also supplies meals, and which normally is an additional activity to a primary function such as a hotel, guest house or restaurant, and where the building restrictions will be those of the primary function, except that additional parking may be required;"consent", means special permission granted by the municipality, after due consideration of the relevant facts and after a reasonable and lawful process has been followed, in terms of which a specific type of land use or activity is permitted, in addition to the primary use rights applicable to the land concerned;"consent use", means an additional use right or a variation of a development management provision that is permitted in terms of the provisions in a particular zone, only with the consent of the municipality;"conservational usage", means the use and/or maintenance of land in its natural state with the purpose of conserving the biophysical properties of the land, including the flora and fauna occurring on the land;"conservation worthy", means a protected tree listed under section 12 of the National Forest Act, 1998 (Act 84 of 1998), i.e. a tree taller than 6m, and a tree with a trunk circumference of more than 1,5m measured 1m from the ground, and that was not declared an invader plant within the Western Cape under section 2(3) of the Conservation of Agricultural Resources Act, 1983 (Act 43 of 1983);"correctional institution", means a building where children are housed and trained on instruction by a court of law, and includes a reformatory, place of detention or industrial school, but does not include a jail;"coverage ", means the total area of a land unit that may be covered by buildings, expressed as a percentage of the net area of such land unit, and shall include:
(a)walls and buildings;
(b)solid roofs;
(c)stairs, steps, landings (except entrance landings and steps), galleries, passages and similar features, whether internal or external, and
(d)canopies, verandas, porches, balconies, terraces and similar features, provided that the following portions of buildings shall be disregarded in the calculation of coverage:
(i)stoeps, entrance steps and landings;
(ii)cornices, chimney breasts, pergolas, flower boxes, water pipes, drain pipes and minor decorative features not projecting more than 500mm from the wall of the building;
(iii)eaves not projecting more than 1m from the wall of a building, and
(iv)a basement, provided that the basement ceiling does not project above the finished ground level;
"crèche", means a facility for the day care of young children in the absence of their parents, and may provide care for more children than are permitted at a day care centre;"crematorium", means a building where the dead are reduced to ash through a process known as ‘cremation’, and includes facilities for associated religious and administrative functions;"current use", means the use as determined by the municipality in terms of applicable legislation or that which is practised actually and lawfully on land or in a structure or building or part thereof in the opinion of the municipality, and ‘existing building’ has the same meaning;

D

"day care centre", means the use of a portion of a dwelling house or outbuildings by the occupant to provide day care, pre-school, play group or after school care services for children provided that:
(i)no more than 20 children shall be registered at a time, or be present on the land unit concerned at any time;
(ii)the service must primarily be of a day care and educational nature and may not be medical;
(iii)the service may not operate outside the hours of 06h00 to 18h00, and
(iv)the dominant use of the dwelling house shall remain for the living accommodation purposes of a single family; provided that a child care service for 5 or less children may be regarded as an occupational practice, and a child care service for more than 20 children shall be regarded as a crèche or place of instruction;
"dBA", means the physical unit used to describe noise level, that is, the A-weighted sound pressure level measured in decibels. The term ‘dBA’ is therefor an abbreviation of the term ‘decibel. ‘A’ frequency weighting is an adjustment made to sound- level measurement to accommodate the response of the human ear. This shall be measured in accordance with accepted scientific principles, as prescribed in the Noise Control Regulations in the Provincial Government of the Western Cape P.N. 627/1998 Noise Control Regulations, as amended, promulgated in terms of ECA;"department head", means the head of the department, or the person, that is charged with the administration of this Zoning Scheme Regulations;"departure use", means the use of land that was considered legal before the date of commencement, but does not comply to the utilisation of land use provisions put forward in this Zoning Scheme and remains a legal use as long as changes requiring building plan approval are not made;"develop", in relation to land, means to prepare or develop land for occupation or use, whether by filling, drainage or levelling of areas; the removal of vegetation, the installation of engineering services, the subdivision of land or the erection, alteration or extension of buildings or structures on land, and "development" has a corresponding meaning in relation to land;"development framework" means a plan or written strategy approved by the municipality and, if applicable, the Provincial Government;"development management provisions", means measures, limitations, provisions or requirements that determine to which degree use or development of land will be permitted;"display", in relation to a sign, includes, without in any way limiting its ordinary meaning, the erection of any structure for support of such sign;"district distributor road", means a public road or street declared by the municipality to be a district distributor road on the basis that it functions as an important distributor of traffic in an area or district;"disturbing noise", means the ambient noise level which exceeds the sound level of a zone concerned or, if no zone level has been determined, a noise level which exceeds the sound level of the environment at the same point of measurement by 7 dBA or more, provided that the determination of the sound level of the environment shall be done in accordance with Noise Control Regulations promulgated in terms of NEMA;"dominant use", means the predominant or major use of land, and may consist of the primary or consent uses permitted on the land;"double storey", means a storey above the ground floor. ‘First storey’ has a similar meaning;"double dwelling house", means a building erected for residential purposes that is designed as a single architectural entity containing two dwelling units on one land unit;"dwelling house", means a building containing only one dwelling unit;"dwelling unit ", means a self-contained inter-leading group of rooms with not more than one kitchen, used for the living accommodation and housing of a single family, together with such outbuildings as are ordinarily used therewith;

E

"eave", means a part of a roof projecting from the facade of a building and includes gutters;"ECA", means the Environment Conservation Act, 1989 (Act 73 of 1989);"ecosystem", means a self-sustaining and self-regulating community of organisms and the interaction between such organisms with one another and their environment;"encroachment agreement", means an agreement between an owner and the municipality relating to the projection of portions of a building or structure from the owner’s land unit onto or over the municipality’s property;"engineering services", means infrastructure for the provision of water and electricity, sewerage infrastructure, storm water disposal infrastructure, streets, roads and pedestrian walkways, including all related services and equipment;"entrance steps and landings", means steps and landings of a building, including any low walls and railings, if such steps and landings are not within the main containing walls of the building;"environment", means the objects, conditions and influences in the direct environment put together, which affect the life and habits of persons or of any other organisms or collection of organisms;"environmental impact assessment", means a report concerning the impact on the environment of specified activities, and which shall comply with requirements laid down by NEMA;"environmental management plan", a business plan that establishes and coordinates mitigation, rehabilitation and monitoring measures for the monitoring of the implementation of a proposal and for the monitoring of maintenance after implementation;"erection", in relation to a building or structure includes:
(i)the building of a new building or structure;
(ii)the alteration or conversion, or addition to, a building or structure, and
(iii)the re-erection of a building or structure which has completely or partially been demolished, and ‘erect’ has a corresponding meaning;
"equipment room", means a building to accommodate communication equipment associated with telecommunication infrastructure which can be a separate building used exclusively for the equipment or it can be a container, or a room within a building;"erf", means the same as ‘land unit’;"exhibition centre", means a premises where displays, social functions, markets as well as training can take place and includes associated facilities and amenities as well as infrastructure including parking;

F

"family", means:
(i)a single person maintaining an independent household, or
(ii)two or more persons directly related by blood or marriage maintaining a common household, or
(iii)no more than five unrelated persons maintaining a common household;
"farm shop", means a building, located on a farm, which does not exceed 500m² in floor space, including storage facilities, where the farmer sells goods, whether to his employees or to the general public and can include a restaurant;"first storey", means the storey above the ground floor and has the same meaning as ‘double storey’;"farm stall", means a building, located on a farm, which does not exceed 100m² in floor space, including storage facilities, where a farmer sells products produced and processed on his farm, whether to his employees or to the general public;"flats", means a building of more than one storey containing three or more dwelling units as living accommodation for persons, where one or more dwelling units do not have a ground floor, together with such outbuildings as are ordinarily associated therewith. This excludes double dwelling houses or group houses, provided that in those zones where flats are permissible, one dwelling unit shall be permissible without the consent of the municipality, in a building approved for other purposes than for flats;"flood", means a general and temporary condition of partial or complete inundation of land areas from the overflow of a body of water;"flood level", means the level of floodwater that on average occurs every 100 years (also called a 1 in 100 years flood), and means the same as ‘base flood’;"floodway", means the channel, river or other watercourse and adjacent land areas that must be kept free of structures and other obstructions, for the base flood to be discharged without the water surface elevation being increased;"floor", means the inner, lower surface of a room, garage or basement and includes a terrace or atrium to which the occupants of a building have access;"floor factor", means the factor (expressed as a proportion of 1) which is prescribed for the calculation of the maximum floor space of a building or buildings permissible on a land unit, and which is the floor space divided by the nett erf area of the land unit, so that the maximum permissible floor space can be calculated by multiplication of the floor factor with the net erf area;"floor space ", in relation to a building, means the area of a floor which is covered by a concrete slab, roof or projection, provided that:
(i)any area, including a basement, which is reserved solely for parking or loading of vehicles, shall be excluded;
(ii)external entrance steps and landings, any stoep and any area required for external fire escapes, shall be excluded;
(iii)a projection including a projection of eaves, and a projection which acts as a sunscreen or an architectural feature, whose projection does not exceed 1m beyond the exterior wall or similar support, shall be excluded;
(iv)any uncovered internal courtyard, lightwell or other uncovered shaft which has an area in excess of 10m², shall be excluded;
(v)any arcade, with a minimum width of 2m, which provides access through the building concerned from public parking, a public street or open space, to a separate public parking area, public street or open space, and which at all times is open to the public, as well as any covered walkway, the roof of which allows light to pass through, shall be excluded;
(vi)any covered paved area outside and immediately adjoining a building at or below the ground floor level, where such paved area is part of a forecourt, yard, external courtyard, pedestrian walkway, parking area or vehicular access, shall be excluded;
(vii)subject to (viii) below, any balconies, terraces, stairs, stairwells, verandas, common entrances and common passages covered by a roof shall be excluded, and
(viii)any stairwells, liftwells or other entrance areas or atriums, in the case of multi-storey buildings, shall only be counted once, provided further that floor space shall be measured from the outer face of the exterior walls or similar supports of such buildings. Where the buildings consist of more than one storey, the total floor space shall be the sum of the floor space of all the storey’s, including that of basements;
"floor space ratio", means the same as ‘floor factor’;"food processing", means the manufacturing of food products through the processing of agronomic and stock farming products as well as of already-existing food;"four-by-four track (4x4 track)", means a series of roads, tracks and routes, designed for use by off-road vehicles as a recreation or adventure facility, and includes buildings normally required for the administration and maintenance thereof, but does not include holiday accommodation or tourist facilities;"frail care facility", means a facility that provides short and long term care for people with chronic illnesses and disabilities with the aim of improving the quality of life of patients and their families facing problems associated with life threatening illness, through the prevention and relief of suffering and includes treatment of elderly people, people suffering from diabetes, cardiovascular disease, stroke, accident victims, HIV/AIDS and other;"freestanding base telecommunication station", means a freestanding support structure on land or anchored to land and used to accommodate telecommunication infrastructure for the transmitting or receiving of electronic communication signals and may include an access road to such facility, and bears the same meaning as ‘transmission tower’;"funeral parlour", means a premises where the dead are prepared to be buried or cremated and includes facilities for associated activities, administration and religious functions;

G

"gambling facility", means a premises for gambling by gaming or wagering, and where there is the opportunity to receive a monetary reward;"garage", means a building used for the storage of motor vehicles, but does not include a motor repair garage or service station;"grade line", means an imaginary line connecting the highest and the lowest natural levels of ground immediately contiguous to a building;"greenhouse", means a structure with the sides primarily made of a transparent material such as glass, Perspex or plastic, for the purpose of growing delicate plants or hastening growing of plants under controlled environmental conditions;"gross density", means a measure of the number of dwelling units in a specified area, and is calculated, for the purposes of this Zoning Scheme, as follows:"gross leasable area", means the total floor space designed for, or capable of, occupation and control by tenants, measured from the centre line of the joint partitions to the inside finished surface of the outside walls, but shall exclude toilets, lift shafts, service ducts, vertical penetrations of floors, interior parking and loading bays;"gross parking space", means an area which incorporates one parking bay plus circulation and landscaping space for one parking bay;"ground floor", means the lowest floor of a building which is not a basement."ground level", means the same as "natural ground level";"ground storey", means the lowest storey of a building, the base of which is the ground floor, but which is not a basement;"group house", means a dwelling unit which forms part of a group housing scheme;"group housing", and "group housing scheme", means a group of separate and/or linked dwelling units planned, designed and built as a harmonious architectural entity and arranged around or inside a communal open space in a varied and ordered way and where every dwelling unit has a ground floor, and of which the dwelling units may be cadastral subdivided;"group housing site", means one or more land units with a minimum size of 1 000m2 on which a group housing scheme or retirement village may be erected;"guest house", means a dwelling house that is used for the purpose of letting individual rooms for residential accommodation, with or without meals, and which exceeds the restrictions of a bed and breakfast establishment, provided that:
(i)the dwelling house is retained in a form which can easily be re-used by a family as a single dwelling house, and
(ii)all amenities and provision of meals shall be for the sole benefit of bona fide lodgers;

H

"health care facility", means a building used for the care of people in a medical, social or social welfare facility, or for the administration thereof, and includes a hospital, clinic or home for the aged, indigent or physically handicapped, but does not include a correctional institution or jail;"height, of a building", means a vertical dimension of the building from the grade-line to the highest point of the building measured in metres or in number of storey’s, provided that:
(i)the height restriction which refers to storey’s does not apply to roofs, domes, chimneys, flues, masts and antennae, and
(ii)elevator or escalator motor rooms, satellite dishes, ventilation shafts, water tanks, air conditioning plant and equipment on the roof of a building, shall be deemed to constitute a storey, unless it is enclosed within the roof or hidden behind parapet walls not exceeding 2m in height, in which case they shall be deemed to form part of the top storey;
"heritage conservation area", means an area designated for this purpose by the municipality, in terms of this Zoning Scheme;"Heritage Resources Act", means the National Heritage Resources Act,1999 (Act 25 of 1999);"high water mark", means the high water mark as defined in the National Environmental Management: Integrated Coastal Management Act, 2008 (Act 24 of 2008);"hillside area", means an area which has a slope of 1 in 5 or greater;"holiday accommodation", means a harmoniously designed and built holiday development, used for holiday and recreational purposes, whether in private or public ownership, which:
(i)consists of a single enterprise in which accommodation is supplied by means of short term rental or time sharing only;
(ii)may include ancillary staff accommodation and the provision of camping sites;
(iii)may include a restaurant and indoor and outdoor recreation facilities, and
(iv)does not include a hotel or motel;
"holiday housing", means a harmoniously designed and built holiday or recreational development with an informally grouped layout which may include the provision of a camping site and land for mobile homes or dwelling units and which may be separately alienated by means of timeshare, sectional title division, the selling of block shares or cadastral subdivision;"horticulture", means the cultivation of plants and fungi on an intensive scale, including the cultivation of plants and fungi under one roof or in a greenhouse, and also refers to the sale of self-cultivated plants and fungi on a land unit;"home occupation", means the practicing of an occupation or trade, or the conducting of an enterprise from a dwelling unit by one or more occupants of the dwelling unit and his or their assistants, provided that the dominant use of the dwelling unit concerned shall remain for the living accommodation of a single family, and the provisions pertaining to home occupation in this Zoning Scheme are adhered to;"hospital", means a facility designed as an integrated complex for the diagnosis, care and treatment of human illness, and includes live-in facilities for patients, nurses and staff;"hotel", means premises used as a temporary residence for transient guests, where lodging and meals are provided, and may include associated conference and entertainment facilities that are subservient and ancillary to the dominant use which is for hotel purposes, as well as premises which are licensed to sell liquor for consumption on the premises, but does not include an off-sales facility;"house tavern", means premises for the conducting of an enterprise from a dwelling house or outbuilding, by the occupant of the dwelling house concerned, for the sale of alcoholic beverages, and may include consumption of alcoholic beverages by customers on the land unit, provided that the dominant use of the dwelling house concerned shall remain for the living accommodation of a single family;"house shop", means premises for the conducting of retail trade from a dwelling house or outbuilding by one or more occupants of the dwelling house concerned, provided that the dominant use of the dwelling house concerned shall remain for the living accommodation of a single family;

I

"ICNIRP", means International Commission on Non-Ionizing Radiation Protection;"industrial hive", means a building or a complex of uniformly designed buildings, containing a mix of retail and manufacturing activities, and arranged in an orderly manner around common spaces, which may include common parking and access;"industry", means premises which in the municipality’s opinion, are used as a factory and in which:
(i)an article or part of such article is made, manufactured, produced, built, assembled, compiled, printed, ornamented, processed, treated, adapted, repaired, renovated, rebuilt, altered, painted (including spray painting), polished, finished, cleaned, dyed, washed, broken up, disassembled, sorted, packed, chilled, frozen or stored in cold storage, or
(ii)livestock (including poultry) is slaughtered, or
(iii)electricity is generated for use in processes referred to in (i) and (ii) above, provided that industry includes an office, caretaker’s quarters or other uses which are subservient and ancillary to the use of the land as a factory, but does not include a noxious trade or risk activity;
"informal trading", means the lawful sale of products in areas specifically demarcated for this purpose by the municipality, such as markets and demarcated areas in the business district;"institution", means premises used as or intended to be used as a social, health or welfare facility, or for the administration thereof, and includes a hospital, clinic, pharmacy, home for the aged, indigent or handicapped, rehabilitation centre, reformatory or place of detention, whether of a commercial or charitable nature, but does not include a jail;"integrated development framework", means a development framework which deals with integration of different strategies and sectoral plans relating to development, such As spatial, economic, social, infrastructure, housing, institutional, fiscal, land reform, transportation, environmental or water plans, to attain the optimal allocation of limited resources in a particular geographic area, and may include an integrated development plan as defined in the Municipal Systems Act;"integrated development plan", means a plan envisaged in section 25 of the Municipal Systems Act;"intensive stock farming", means the keeping, feeding and breeding of animals on an intensive scale. These animals include poultry and sea animals including oysters and abalone, on an intensive basis;

K

"keeping of animals", means the accommodation of animals;

L

"land", means land with or without improvements in terms of land development and, includes land covered with water such as marsh or wetlands;"landscape plan", means a plan indicating detailed landscape proposals including walkways, paving, plants, water features, recreation areas, engineering services and any other such land uses;"landscaping", means the planting or placement of plants for the purpose of protecting and promoting aesthetic appeal, scenic beauty, character and value of land, as well as promotion of public health and safety through the reduction of noise pollution, storm water runoff, air pollution, visual pollution or light glare;"land survey certificate", means a certificate issued by a professional land surveyor;"land unit", means a portion of land registered or viable to be registered in a deeds registry;"level of the pavement", means
(i)in the case of a pavement/footway which has been constructed within a road reserve reserves to the back of the pavement/ footway, or
(ii)the height determined by the municipality, referring to a foot-way that was not been constructed or is yet to be constructed and ‘level of the footway’ has the same meaning;
"licensed hotel", means a building designed to comply with the requirements of a hotel;"linked", in relation to the definitions of town housing and group housing, means to be connected by means of a boundary wall or garage;"loading zone", means an area measuring not less than 4,5m x 7,5m, which is clearly demarcated for loading and off-loading of goods from commercial vehicles, which also provides vehicular access to a public street at the satisfaction of the municipality;"local sign", means the same as ‘permanent sign’;"lodge", means premises, not exceeding 450m² floor space, single storey, or 350m² footprint, double storey, used as a temporary residence for transient guests, where lodging and meals are provided, and may include associated conference and entertainment facilities that are subservient and ancillary to the dominant use of the premises as a lodge. ‘Lodge’ also implies that there are premises on site which are licensed to sell liquor to be consumed on that same land unit, however does not include an off-sales facility;"lodger", means a person who pays rent for bedroom accommodation within another person’s dwelling unit;"lodging", means bedroom accommodation which is made available in exchange for payment, and includes the services ordinarily related to such accommodation;

M

"maximum floor space", means the greatest total floor space which is allowed for a building or buildings including all the storey’s on a land unit, such maximum floor space being calculated by multiplication of the floor factor by the net erf area of the land unit or that portion of the land unit which is situated within a particular zone. This is applicable provided that where the land unit is situated within two or more zones in which different floor factors apply, the maximum floor space for the whole land unit shall be the total of the maximum floor space for each portion of the land unit;"medical consulting rooms", means premises, excluding a hospital or clinic, which are used for human medical or medically related consultation, examination or treatment, but does not include live-in facilities;"mezzanine", means an intermediate floor in a building between the ground floor and the first floor, which for the purposes of measuring height shall be counted as a storey;"Mineral and Petroleum Development Act, 200 (Act 28 of 2002)", means the Act that controls the issuing of permits and licenses;"mining", means an enterprise which practices the extraction of raw material from the earth, whether by means of surface or underground methods, and includes, but is not limited to, the removal of stone, limestone, sand, clay, kaolin, ores, minerals, gas and precious stones as well as referring to the process of stone crushing;"mobile home", means a transportable factory-constructed structure with the necessary service connections, which is designed so that it can be used as a permanent dwelling;"mortuary", a place, specifically referring to a funeral home, where dead bodies are kept before burial or cremation;"motor vehicle", means a vehicle designed or used for propulsion by means of an internal combustion or electrical engine, and includes a motor cycle, trailer or caravan, but does not include a vehicle moving exclusively on rails;

N

"National Building Act", means the National Building Regulations and Building Standards Act, 1977 (Act 103 of 1977);"National Constitution", means the Constitution of the Republic of South Africa, 1996; natural ground level, means the level of the land surface on a land unit:
(a)in its unmodified state, or
(b)in a state where the land has been graded, with a grading machine that levels out the surface land area, with the municipality’s permission, for the purposes of development, provided that:
(i)any grading of land for the purpose of development shall connect evenly with the existing levels of abutting land units;
(ii)where land is excavated, the excavated level is deemed to be the natural level of the ground;
(iii)where it is not possible to determine the natural level of the land owing to irregularities or disturbances of the land, the municipality shall determine a level for the purpose of administrating this Zoning Scheme, and
(iv)where land is excavated and the excavated material is used to elongate a building site (cut to fill) the municipality shall define a level for the purposes of administering this zoning scheme;
"nature reserve", means a national park, or some other nature park which is in the ownership of a public authority or has been declared as such in terms of legislation and remains in private ownership. It consists of an area which is utilised as a game park or reserve for fauna and flora in its natural habitat and includes contextual size and impact related accommodation facilities for tourists or holidaymakers;"NEMA", means the National Environmental Management Act, 1998 (Act 107 of 1998);"nett density", means the density of a specified area, calculated through land set aside for ancillary uses, such as open spaces, streets, schools and business use, being subtracted from the total area, at the satisfaction of the municipality, and the number of residential units being divided by the remaining area that exist or for which planning is being done;"nett erf area", means the total area of a land unit, excluding all land reserved for public purposes, such as streets, roads or road widening;"noise level ", means a reading on an integrated impulse sound level meter taken in accordance with accepted scientific principles, as described in the noise control regulations promulgated in terms of NEMA;"noise pollution", means any sound which, in the opinion of the municipality, causes or may cause unreasonable nuisance, or which may disturb the comfort or peace and quiet of a person or persons in the vicinity;"non-conforming use", means use of land which was lawful before the commencement date, but which does not conform to the use or land use provisions stipulated in this Zoning Scheme and stays a lawful use as long as no changes requiring building plan approval are made;"noxious trade", means an offensive, poisonous or potentially harmful trade, use or activity which due to fumes, emissions, smell, vibration, noise, waste products, the nature of material used, the processes employed, or other causes, is deemed by the municipality to be a potential source of danger, nuisance or offence to the general public or persons in the surrounding area;"nursery", means an enterprise for the sale of plants, horticultural products and horticultural equipment;

O

"occupant", means any person who physically inhabits a building, a structure or land area, or a person having the charge or management thereof, and includes the representative of any person absent from the area or whose whereabouts is unknown;"occupational practice", means the same as ‘home occupation’;"offices", means a room or a suite of rooms or a building used for an administrative function or for the conducting of an enterprise primarily concerned with administrative, clerical, financial or professional services, and includes a post office or magistrate’s offices or professional use;"office park", means a group of office buildings which are designed and built as a harmonious architectural entity, arranged in an orderly manner within a landscaped environment, and involving shared use and management of amenities such as roads, services, access control or common land;"Ordinance", the Land Use Planning Ordinance, Ordinance 15 of 1985;"Organ of state", means an organ of the state as defined in Section 239 of the National Constitution;"outbuilding", means a structure, whether attached to or separate from the main building, which is designed to be normally used for the housing of domestic workers, for storing motor vehicles or for general storage purposes, provided that these uses are usually necessary in connection with the main building, however this does not include additional dwelling units;"outdoor advertisement", means the action or process of notifying, warning, informing, announcing or any other mode of communicating of information in a visual manner and which takes place outdoors;"outdoor recreation facility", means an area where leisure and recreational opportunities are available, primarily outdoor facilities such as, but not limited to, open-air concerts, miniature golf and roller-skating rinks. These are available usually in the interest of commercial gain;"overlay zone", means a category of zoning applicable to particular land, which stipulates additional land use provisions for such land in addition to the underlying zoning requirements, and may include parameters relating to consent use restrictions, subdivision, urban renewal, environmental protection or any other purpose as set out in this Zoning Scheme. This is given that overlay zoning may add further land use provisions in a particular area or zone which may be more restrictive or less restrictive than that of the land units which are not covered by the overlay zoning implying that ‘overlay zoning’ has a corresponding meaning;"owner", in relation to land, means the person or entity in whose name that land is registered in a deeds registry, and may include the holder of a registered servitude right, or long term lease, or any successor in title;

P

"package of plans", means the hierarchy of plans specified in terms of this Zoning Scheme;"panhandle", means a narrowed section of a land unit that provides access to a street;"parking bay", means an area measuring no less than 5m x 2,5m for perpendicular parking and 6m x 2,8m for parallel parking, which is clearly outlined and demarcated for the parking of one motor vehicle and which is accessible at the satisfaction of the municipality;"parsonage", means a dwelling for the living accommodation of a spiritual leader who is in the full-time service of an organisation which conducts religion in a place of worship, and can include the living accommodation of the spiritual leader’s family as well as a monastery;"patio", means a paved roofless area adjacent to and belonging to a building or an open-air courtyard;"pergola", means any roofless, horizontal or almost horizontal grid or framework and is applicable if the area seen in the horizontal projection of the solid portions of this grid does not exceed 25% of the total area thereof;"permanent sign", means a sign on a specific site, premises or building which is permanently displayed and which refers to an activity, product, service or attraction offered or provided on those premises on that site or inside the building, and has the same meaning as ‘local sign’;"Petroport", means a facility with direct access from a highway, through-way or main transport route, which provides rest, service and fuel facilities for long-distance trucks and other long-distance vehicular traffic, and includes facilities for emergency vehicle towing services;"petrol filling station", means the same as ‘service station’;"place of assembly", means a public hall, a hall for public or social functions, a music hall, a concert hall or a hall for display purposes which is not directly related to a commercial enterprise, town hall or civic centre;"place of entertainment", means a theatre, cinema, dance hall, amusement park, sports centre, billiards room, games arcade, skating rink, or similar place and may include a gambling facility;"place of instruction", means a crèche, pre-primary school, school,college, technical institute, university, research institution, convent, public library, public art gallery, museum or other centre of education, and includes an associated hostel, but excludes a building or land unit which is predominantly used as a certified correctional institution or industrial school or as an institution;"place of worship", means a church, synagogue, mosque, temple, chapel or other place for practicing a faith or religion, and includes any building, including a residence, associated therewith, but does not include a funeral parlour, cemetery or crematorium with related chapel;"porch", means a roof (not being the roof or balcony) projecting from the outside of a building above a doorway, and forming a covered entrance to such building, and includes any paved area hereunder, any low walls or railings enclosing such paved area and any pillars supporting such roof;"Premier", means the Premier of the Western Cape Province;"primary distributor road", means a public street declared by the municipality to be a primary distributor road;"primary use", in relation to land or buildings, means any use specified in this Zoning Scheme as a primary use, being a use that is permitted without the need to obtain the municipality’s consent except for building plan approval;"private open space", means land which is or will be under private ownership, or municipal land on a long term lease, with or without access control, used primarily as a site for outdoor sports, play, rest or recreation, or as a park, garden, or play area or for nature conservation;"private parking", means land, a building or part of a building which is managed by a private individual or institution and which is used exclusively for parking purposes and is not normally accessible to the general public except when payment is involved;"private road", means land reserved for the passage or parking of motor vehicles, which is privately owned and does not vest in the municipality or another public authority;"professional use", means that kind of use which is normally and reasonably associated with professionals such as doctors, dentists, attorneys, architects, engineers and town planners, where services rendered, are separate from trading are one of the distinguishing factors;"property", means land together with all buildings and structures on the land;"public authority", means a state department, a municipality or a department of the Provincial Government;"public garage", means a business where motor vehicles are provided with fuel in exchange for payment, and includes trading in motor vehicles, oil, tyres or motor spares, the repair or overhauling of motor vehicles, a restaurant or café together with bathroom facilities, spray painting, panel beating, blacksmith or body work;"public housing", means dwelling units which are built with funds granted by a public authority;"public nuisance", means any act, omission or condition which in the municipality’s opinion is offensive, induces injury or is dangerous to health, or materially interferes with the ordinary comfort, convenience, peace and quiet of the public, or which adversely affects the safety of the public, taking into account:
(i)the reasonableness of the activities in question in the area concerned, and the impacts which result from these activities, and
(ii)any noise levels stipulated in an overlay zone applying to the land concerned;
"public open space", means land which is under or will be under the ownership of the municipality, which is not, or is not to be, leased on a long term basis, and which is set aside for the public as an open space, park, garden, picnic area, playground, square or conservation area;"public parking", means land that is accessible to the general public for parking purposes with or without a fee;"public place", means land indicated on an approved plan, diagram or map, of which ownership vests in the municipality or in another public authority;"public road or public street", means any land indicated on an approved plan, diagram or map, of which the ownership vests in the municipality or another public authority in terms of applicable law, and which has been set aside for vehicular and pedestrian use;"publish in the press", means to publish a notice in such newspaper or newspapers as the municipal manager may determine from time to time, or in the Provincial Gazette or in both a newspaper or newspapers as intended herein and the Provincial Gazette, and "publication in the press" has a corresponding meaning;

R

"racing track", means land used to race, rally and scramble, including go-karts, quad bikes, motorcycles, motorboats as well as racing animals (e.g. horses and dogs), and includes the testing of vehicles and boats;"rear boundary", with regard to a land unit, means every boundary situated thereon (other than a street or side boundary) which is parallel to, or is within 45° of being parallel to, every side boundary of such land unit and which does not intersect a street boundary, provided that, in the case of a panhandle land unit, the municipality shall determine which boundary, if any, is the rear boundary;"recycling plant" , a facility where waste is separated for reprocessing for further use as a product or raw material;"register", means the document held by the municipality in connection with all departures, consent uses, site development plans, conditions relating to use rights or special zone land use provisions;"rehabilitation centre", means premises or part thereof used or intended to be used to rehabilitate people or animals through physical or mental stimulation;"religious leader’s residence", means a building designed as a joint architectural unit on the same land unit as a place of worship;"renewable energy structure", means any wind, water or organic matter turbine or solar voltaic apparatus, or grouping thereof that captures and converts wind, water, organic matter or solar radiation into energy for commercial gain irrespective of whether it feeds onto an electricity grid or not, and includes any appurtenant structure or any test facility or structure that may lead to the generation of energy on a commercial basis;"residential building", means a building (excluding a dwelling house, a group house, a town house or flats) for occupation by persons, together with such outbuildings as are ordinarily used therewith, and includes a boarding house, lodging rooms, a licensed hotel (excluding an off-sales facility), an old-age home, a children’s home and a hostel, but does not include buildings which, either by means of inclusion or exclusion, are mentioned in the definition of "place of instruction" or "institution";"resort shop", means a shop, within a holiday resort, which does not exceed 500m2 in floor space, including storage facilities;"resource industry", means the process of extracting, mining, winning or quarrying raw materials from the ground including gravel, sand and stone, and includes buildings and activities connected with such operations as well as a crushing plant.;"restaurant", means a commercial establishment where meals and liquid refreshments are prepared and served to paying customers for consumption on the site, and includes licensed provision of alcoholic beverages for consumption on the site;"rezoning", means amendment of the zoning scheme in order to effect a change of zoning in relation to a particular land unit or part thereof or to land units;"riding school", means a place or undertaking for the leasing of horses and riding instructions being provided in exchange for payment, and includes the care and stabling of such horses;"right of use", in relation to land, means the right to use land in accordance with the zoning thereof, including any lawful departure;"risk activity", means an undertaking where the material handled or the processes carried out are liable to cause rapid combustion or give rise to poisonous fumes, or cause explosions, and includes activities involving dangerous and hazardous substances that are controlled in terms of national legislation;"road", means a public or private street or road;"rooftop base station", means a cell phone base station where antennae are attached to the roof or side of an existing building; provided that any antenna support structure or equipment room that is not part of the building, does not extend more than 2,5m in height above the top of the building;

S

"SANS", means South African National Standards;"satellite dish antenna", means an apparatus capable of receiving or transmitting communications from a satellite;"scenic drive", means a public road or street which has been declared as a scenic drive by the municipality in recognition of the high visual amenity alongside that public road or street, including background vistas of mountains, open country, coastline or urban landscape;"scenic drive corridor", means all land within 200m on either side of a scenic drive as measured perpendicularly from the centre line of the road reserve;"scrap yard", means a building or land which is utilised for one or more of the following purposes:
(i)storing, depositing or collecting of junk or scrap material or articles of which the value depends mainly or entirely on the material used in the manufacture thereof;
(ii)the dismantling of second hand vehicles or machines to recover components or materials, and
(iii)the storing or sale of second-hand parts, pipes, poles, steel, wire, lumber, tyres, bricks, containers or other articles which are suitable to be left in the open without any serious damage being incurred;
"second dwelling", means a dwelling unit which may be erected with the consent of the municipality on a land unit where a dwelling house, permitted as a primary use, has already been erected, provided that:
(i)this regulation authorises the municipality to grant its consent for a second dwelling unit in the zone concerned;
(ii)the second dwelling unit shall remain on the same cadastral unit as the dwelling house;
(iii)the second dwelling unit shall have a lesser floor area than the dwelling house;
(iv)the second dwelling unit shall comply with other requirements specified in this regulation;
(v)sectional title ownership for the main and second dwelling shall be permitted, provided that both dwellings shall have direct access to public roadway and both dwellings shall have direct connections to Municipal infrastructure.
"secondary use", means a consent use which is stipulated by the municipality, in terms of this Zoning Scheme, as a secondary use in order to indicate that it will probably be supported and approved relatively quickly, provided that it complies with an approved planning policy which has passed through an acceptable public process;"Sectional Titles Act", means the Sectional Titles Act, 1986 (Act 95 of 1986);"sectoral plan", means any written strategy or plan which deals mainly with one of the sectors or elements or particular subjects that form part of an integrated development plan and which may, for example, be an economic, land reform, environmental, housing, water, service or transport plan;"service station", means premises for the retail supply of fuel, and includes trading in motor vehicles, oil, tyres or motor spares, or the repair, overhauling or washing of motor vehicles, but does not include spray-painting, panel beating, blacksmith or body work, provided that any part of a shop or business premises which incorporates facilities for retail supply for the use of motor vehicles, shall be deemed to be a service station;"service trade", means an enterprise which:
(i)is primarily involved in the rendering of a service to the local community such as the repair of household appliances or the supply of household services, and
(ii)is not likely to be a source of disturbance to surrounding land units, and
(iii)employs at most ten people, and
(iv)is not liable, in the event of fire, to cause excessive combustion, give rise to poisonous fumes or cause explosions, and
(v)includes a builder’s yard and allied trades and a laundry, bakery, dairy depot and similar types of uses, but
(vi)does not include an abattoir, a brick-making site, sewage works, a service station or a motor repair garage;
"services agreement", means a written agreement which is concluded between a developer of land and the municipality, in terms of which the respective responsibilities of the two parties for the planning, design, provision, installation, financing and maintenance of internal and external engineering services and the standard of such services are determined;"setback", means the line delimiting an area, measured from the centre line of a particular public street, within which no building or other structure including a boundary fence, may be erected;"shelter", means a unit of accommodation intended for human occupation, constructed of material which need not comply with the standards of durability intended by the National Building Act;"shop", means premises used for the retail sale of goods and services individually or in relatively small quantities to the public, and includes a retail concern where goods which are sold in such a concern are manufactured or repaired, provided that the floor space relating to such manufacturing or repairs shall not comprise more than one third of the floor space of the shop, and provided further that "shop" does not include an industry, a service trade, a motor repair garage, a service station, a restaurant, an adult entertainment enterprise, a bottle store or an industrial hive, and if such uses occur on the same land unit as a shop, they shall be regarded as separate uses subject to the relevant separate land use provisions;"side boundary", means a boundary of a land unit other than the street boundary or the rear boundary;"sidewalk", means a path (or pavement) along the side of a road that may accommodate moderate changes in height and is normally separated from the vehicular section by a curb. There may also be a strip of vegetation, grass, bushes or trees or a combination of these between the pedestrian section and the vehicular section;"site development plan", means a plan which shows detail of proposed development at the level of a particular site, including:
(i)existing biophysical characteristics of the site;
(ii)the layout of the site, indicating the use of different portions thereof;
(iii)the position, use and extent of buildings;
(iv)sketch plans and elevations in regard to proposed structures, including information about their external appearance or outside elevation;
(v)the alignment and general specifications of vehicle access, roads, parking areas and pedestrian footpaths;
(vi)the position and extent of private, public and communal space;
(vii)typical details of fencing or boundary walls around the perimeter of the site as well as within the site;
(viii)electricity supply and external lighting proposals;
(ix)provision for the disposal of storm water, sewage and refuse;
(x)water supply;
(xi)external signage details;
(xii)general landscaping proposals including vegetation to be preserved, vegetation to be removed, vegetation to be planted, external paving, and measures for stabilising outdoor areas where applicable;
(xiii)the phasing of the development;
(xiv)(xiv) the proposed development in relation to existing and finished ground levels, including excavations and cut and fill;
(xv)statistical information about the extent of the proposed development, floor space allocations and sizes as well as the provision of parking, and
(xv)any other details as may reasonably be required by the municipality;
"slope", means the degree of deviation of a surface from the horizontal, usually expressed as a ratio and calculated for the purpose of this Zoning Scheme Regulations as follows:"special area", means an area of historical, cultural or ecological significance, or a biosphere zone, to which, over and above the zoning restrictions, additional guidelines regarding management and development must be applied;"special usage", means a use which is such, or in respect of which the land use provisions are such, that it is not otherwise provided for in this Zoning Scheme, which is defined fully and in respect whereof the land use parameters are defined fully by means of conditions of approval or by means of provisions applying to the special zone, and includes conservation usage;"stoep", means an uncovered paved area or projecting floor outside and immediately adjoining a building, at or below the level of the ground floor thereof, and includes any low walls or railings enclosing such paved areas or floors;"storey", means that portion of a building included between the surface of any floor and the surface of the next floor above, or if there is no floor above, then the ceiling, provided that:
(i)a basement does not constitute a storey;
(ii)a roof, or dome which forms part of the roof, shall not constitute a separate storey unless the space within the roof or dome is designed for, or used for, human occupation, in which case it is deemed to be a storey, and
(iii)any storey which is higher than 3m but equal to or less than 6m in height, shall, for the purpose of height measurement, be deemed to be 2 storey’s, and every additional 3m in height or portion thereof, shall be deemed to be an additional storey;
"street", in the context of provisions pertaining to street building lines, setbacks, street boundaries, street corners, off-street parking, site access or loading requirements, includes a public street and a private road;"street boundary", means the common boundary of a land unit with a street, provided that where a part of a land unit is reserved in terms of the Zoning Scheme Regulations or any other law for the purpose of a new street or street widening, the street boundary of the land unit is the boundary of such proposed new street or proposed street widening;"structure", without in any way limiting its ordinary meaning, includes any building, shelter, wall, fence, pillar, pergola, steps, landing, terrace, sign, ornamental architectural features, swimming pool, fuel pump and underground tank, as well as any portion of a structure;"structure plan", means a plan referred to in section 16 of the Western Cape Land Use Planning Act, 2014;"subdivide and subdivision", in relation to land, means to subdivide land whether by means of:
(i)survey;
(ii)the allocation, with a view to a separate registration of land units, of undivided portions thereof in any manner, or
(iii)the preparation thereof for such subdivision;
"sub divisional area", means land zoned as sub divisional area or alternatively land zoned in a manner which shall allow subdivision as contemplated in section 25 of the by-law;"sub divisional plan", means a plan which reflects the prescribed information in relation to intended subdivision, including but without being limited to, the relative location of the proposed subdivided land units, public places and public streets on a land unit that is to be subdivided;"substitution scheme", means a zoning scheme regulations which replaces any other zoning scheme regulations or a part thereof;"supermarket", means a retail concern with a net retail floor space of not less than 350m², which is utilised for sales on a basis of self-service and where the goods for sale fall in one or more of the following categories:
(i)foodstuffs;
(ii)toiletries;
(iii)household cleaning agents;
(iv)clothing;
(v)wine sales, or
(vi)home and garden equipment;
"Systems Act", means the Local Government: Municipal Systems Act, (Act 32 of 2000);

T

"Telecommunication infrastructure", means:
(i)any part of the infrastructure of a telecommunication network for radio/ wireless communication including voice, data and video telecommunications, which may include antennae;
(ii)any support structure, equipment room, radio equipment and optical communications equipment (laser or infra-red) provided by cellular network operators or any other telecommunication providers;
(iii)all ancillary structures needed for the operation of telecommunication infrastructure, provided that fibre optic installations and point to point copper (cable) installations are excluded from this definition;
"terrace", means an area to which the occupants of a building have access, created on a flat roof over a portion of a storey, resulting from the setback of a part of the building above such a storey;"title", in relation to tenure, means land ownership, and includes all forms of ownership that can be taken up in a title deed;"token zone", means the zoning of a relatively small part of a land unit which differs from the zoning of the larger part of the land unit;"total floor space", in relation to a building, means the sum of the floor space of all the storey’s of such a building, including basements;"tourist facilities", means amenities for tourists or visitors such as lecture rooms, restaurants, gift shops, restrooms or recreational facilities, but does not include a hotel or overnight accommodation;"town house", means a dwelling unit forming part of a town housing scheme;"town housing and town housing scheme", means a housing development which is a row or group of linked and/or attached dwelling units, designed and built as a harmonious architectural entity, of which every dwelling unit has a ground floor and which can be cadastrally subdivided;"town housing site", means a land unit or more than one land unit with a total minimum size of 2 000m², on which a town housing scheme has been erected or is to be erected;"traffic impact assessment", means a study of demand for travel generated by a proposed development in relation to the existing and planned road system, where the development generates more than 275 trips or increases daily trips by more than 20% above existing levels;"traffic impact statement", means a statement of demand for travel generated by a proposed development in relation to the existing and planned road system, where the development generates less than 275 trips or increases daily trips by less than 20% above existing levels;"transmission tower", means any support structure and associated infrastructure of more than 3m in height, that is used for the transmission and/ or reception of electromagnetic waves; and includes telecommunication, cellular telecommunication, radio, television and satellite transmission;"transport usage", means an undertaking based on the provision of a transport service, and includes both public and private transport facilities, such as airports, airfields, railway stations, bus depots, taxi ranks, public transport interchanges and associated uses;

U

"urban conservation", means the development or maintenance of the built environment in a prescribed manner, aimed at maximisation of its historic, aesthetic or social attributes and the enhancement of the value of the area, both for present and future use;"urban edge", means a demarcated line which may or may not follow cadastral boundaries, together with an interrelated policy which serves to determine, manage, direct and control the outer limit of urban expansion;"use", in addition to its ordinary meaning, includes earmarked use or intention to use;"use zone", means the part of this Zoning Scheme which is shown on the zoning map by means of a specific notation or bordering or any other distinguishing manner, in order to identify permitted use of the land;"utility usage", means a use or an element of infrastructure that is required to provide engineering or associated services for the proper functioning of urban development, and includes water reservoirs and purification works, electricity substations and transmission lines, waste water pump stations and treatment works (sewage), but does not include roads, parking or other transport usage;

V

"veranda", means a covered area, not being an area which is part of a yard or parking area, or a projecting floor outside and immediately adjoining a building at or below the level of the ground floor thereof, and includes both such areas of the floor and roof or other feature covering it, as well as any low walls or railings enclosing such paved area or floor;

W

"wall of remembrance", means a place where human ashes and corresponding plaques are placed, or only plaques for the dead are placed, and where space for remembering the dead is created;"warehouse", means premises used primarily for the storage of goods, except those that are offensive or dangerous, and includes premises used for business of a predominantly wholesale nature, as well as for rendering of services, but does not include premises used for business of a predominantly retail nature;"waste disposal site", means a place where household, commercial or industrial products are stored, salvaged, treated or disposed of in a lawful manner, and includes sanitary infill;"winery", means a place where wine is made and may include a selling area for the general public and a wine-tasting area;"wine shop", means a place to sell packaged wine for consumption off the premises;

Z

"zone", when used as a noun, means land which has been designated for a particular zoning, irrespective of whether it comprises one or more land units or parts of land units;"zone", when used as a verb in relation to land, means to designate land for a particular zoning;"zoning", when used as a noun, means a category of directions regulating the development of land and setting out the purposes for which the land may be used and the land use or land use provisions applicable in respect of the said category of directions, as determined by the Zoning Scheme Regulations;"zoning map", means an approved map or approved maps showing the zones and land units in respect of land situated within the area of jurisdiction of the municipality;Zoning of land as specified use zonesThe land indicated on the zoning map, as indicated in column 2 or 3 of Table A, is zoned for the various purposes mentioned in column 1 of Table A and may, subject to relevant provisions of the by-law and this zoning scheme, not be used for any other purpose.Erection of buildings and use of land in specified use zones:The purposes, called primary uses, for which land may be used in the various zones indicated in column 1 of Table B, are mentioned in column 2 of Table B. The purposes, called consent uses, for which land may be used in the various zones indicated in column 1 of Table B with the approval of the municipality, are mentioned in column 3 of Table B. Any use that does not occur in column 2 or 3, may, subject to overriding provisions of the by-law and this zoning scheme, not be permitted in the relevant zone.TABLE AIn the case of land which had not been zoned prior to 1 July 1986 and of which the land use is subject to title conditions, the use thereof for the purpose of zoning as intended by Section 14(1) of the Ordinance, is deemed to be the use imposed or permitted by the Premier in terms of title conditions, or, if more than one use is thus permitted, one of such uses as determined by the Council.It is important to note that the buildings and uses permitted in terms of Table B or which can be approved by the consent of the Council, may be subject to departures, which can render the use right relating to a land unit effectively more or less limited than appears from the notation on the map. In such cases the relevant information relating to the land unit must be noted in the register held for this purpose.
TABLE B  
ZONING  
RESIDINGPrimary usesContent uses
Residential Zone 1:Low densityDwelling house.Second dwelling,Double dwellinghouse, Bed &Breakfastestablishment, Daycare centre, Place ofinstruction, Place ofworship, Homeoccupation
Residential Zone 2:Medium densityDwelling house.Second dwelling, Bed& Breakfastestablishment, Daycare centre, Guesthouse, House shop,House tavern, Homeoccupation.
Residential Zone 3:High density EstatehousingDwelling house,Private open space.Group housing, Townhousing, Flats, Hotel,Restaurant, Place ofassembly, Homeoccupation.
Residential Zone 4:Incremental housingDwelling house,Second dwelling, Bed& Breakfastestablishment, Shelter.Double dwellinghouse, Day carecentre, Place ofInstruction, Housetavern, House shop,Home occupation.
GENERALRESIDENTIALPrimary usesConsent uses
General ResidentialZone 1: GrouphousingGroup housing,Dwelling house.Home occupation.
General ResidentialZone 2: TownhousingTown housing,Dwelling house.Flats, Homeoccupation.
General ResidentialZone 3: FlatsFlats, Guest house,Boarding house,Dwelling house,Group housing, Townhousing.Shop, Lodge,Institution, Place ofinstruction, Place ofassembly, Homeoccupation,Transmission tower,Rooftop base station.
BUSINESSPrimary usesConsent uses
Business Zone 1:General businessBusiness premises,Flats, Offices, Officepark, Restaurant,Service trade, Publicparking, Animalhospital, Nursery,Transmission tower,Rooftop base station,Wine shop.Service station, Hotel,Funeral parlour, Carwash, Residentialbuilding, Place ofassembly, Place ofentertainment, Adultentertainmententerprise, Institution,Bottle store.
Business Zone 2:NeighbourhoodbusinessBusiness premises,Flats, Public parking,Transmission tower,Rooftop base station,Wine shop.Offices, Place ofassembly, Place ofentertainment,Restaurant, Bottlestore, Service trade,Car wash, Nursery,Lodge
Business Zone 3:Service stationService station, Carwash, Transmissiontower, Rooftop basestation.Shop, Businesspremises, Restaurant,Wine shop.
TABLE B
ZONING
Business Zone 4:PetroportPetroport, Shop,Restaurant,Transmission tower,Rooftop base station.Public garage, Touristfacility, Holidayaccommodation,Lodge, Wine shop.
INDUSTRIALPrimary usesConsent uses
Industrial Zone 1:Light industryService trade,Industrial hive, Warehouse, Car wash,Restaurant, Servicestation, Public parking,Transmission tower,Rooftop base station.Industry, Publicgarage, Shop, Bottlestore, Offices, Officepark, Adultentertainmententerprise.
Industrial Zone 2:General industryIndustry, Service trade,Warehouse, Transportusage, Car wash,Restaurant, Publicparking, Industrialhive, Service station,Public garage,Transmission tower,Rooftop base station.Shop, Bottle store,Place of instruction,Place of worship,Place of assembly,Adult entertainmententerprise, Funeralparlour, Waste disposalsite, Scrap yard,Recycling plant.
Industrial Zone 3:Risk industryNoxious trade, Riskactivity, Transmissiontower, Rooftop basestation.Industry, Service trade,Warehouse, Scrapyard, Transport usage,Shop, Service station,Waste disposal site,Crematorium, Publicparking, Abattoir,Recycling plant.
Industrial Zone 4:Extractive industryMining, Transmissiontower, Rooftop basestation.Industry, Risk activity.
COMMUNITYPrimary usesConsent uses
Community Zone 1:EducationPlace of instruction.Conference facility,Place of assembly,Place of worship,Institution,Transmission tower,Rooftop base station.
Community Zone 2:WorshipPlace of worship,Religious leader’sresidence,Transmission tower,Rooftop base stationPlace of assembly,Place of instruction,Cemetery, Wall ofremembrance,Institution
Community Zone 3:InstitutionInstitution.Place of assembly,Place of instruction,Transmission tower,Rooftop base station.
AUTHORITYPrimary usesConsent uses
Authority Zone 1:GovernmentAuthority usage,Transmission tower,Rooftop base stationAny use determinedby the municipality.
TRANSPORTPrimary usesConsent uses
Transport Zone 1:Transport usageTransport usage,Public parking,Transmission tower,Rooftop base stationShop, Offices, Hotel,Restaurant, Bottlestore, Warehouse,Industry, Service trade,Service station, Placeof assembly, Place ofentertainment,Institution
TABLE B
ZONING
Transport Zone 2:RoadsPublic street, Privateroad, Public parking,Private parkingAny use determinedby the municipality.
Transport Zone 3:ParkingPublic parking, Privateparking, Transmissiontower, Rooftop basestation.Shop, Businesspremises, Servicestation.
OPEN SPACEPrimary usesConsent uses
Open Space Zone 1:Public open spacePublic open space,Conservation usage,Transmission tower,Rooftop base station.Cemetery, Wall ofremembrance,Camping site, Boatlaunching facility,Racing track
Open Space Zone 2:Private open spacePrivate open space,Conservation usage,Transmission tower,Rooftop base station.Cemetery, Wall ofremembrance,Camping site,4x4 route, Boatlaunching facility,Racing track
Open Space Zone 3:Nature reserveNature reserve,Conservation usage.Tourist facility,Holidayaccommodation,4x4 route,Transmission tower,Rooftop base station,Boat launchingfacility
Open Space Zone 4:CemeteryCemetery, Wall ofremembrance, Privateopen space,Conservation usage.Crematorium, Place ofworship, Funeralparlour.
RESORTPrimary usesConsent uses
Resort Zone: ResortHolidayaccommodation,Conservation usage,Private open space,Lodge.Tourist facility, Resortshop, Conferencefacility, Transmissiontower, Rooftop basestation, Boat launchingfacility.
Leisureaccommodation ZoneHolidayaccommodation,Holiday Housing,Conservation usage,Private open space.Lodge, Tourist facility,Resort shop,Transmission tower,Rooftop base station,Boat launchingfacility
AGRICULTUREPrimary usesConsent uses
Agricultural Zone 1:AgricultureAgriculture, Farmstall.Additional dwellingunit, Guest house,Tourist facility, Farmshop, Aquaculture,Intensive stockfarming, Horticulture,Nursery, Ridingschool, Service trade,Mining, 4x4 routeCommercial petkennel, Bed &breakfastestablishment,Conservation usage,Agri- village,Composting, Racingtrack, Boat launchingfacility, Conferencefacility, Exhibitioncentre, Transmissiontower, Rooftop basestation, Renewableenergy structure
TABLE B
ZONING
Agricultural Zone 2:Agricultural industryAgricultural industry,Transmission tower,Rooftop base stationDwelling house,Tourist facility, Farmstall, Nursery,Intensive stockfarming, Horticulture,Composting.
Agriculture Zone 3:SmallholdingsAgriculture.Additional dwellingunit, Farm stall, Bed& Breakfastestablishment, Touristfacility, Riding school,Nursery, Intensivestock farming,Horticulture,Commercial petkennel, Composting,Food processing,Home occupation,Transmission tower,Rooftop base station.
UNDETERMINEDPrimary usesConsent uses
Undetermined ZoneNone.None.
SPECIALPrimary usesConsent uses
Special ZoneSpecial usage.Any use determinedby the municipality,Trans- mission tower,Rooftop base station
SUB DIVISIONALAREAPrimary usesConsent uses
Sub divisional AreaZoneAll zonings asdescribedAs applicable torelevant zonings.

Chapter 1
RESIDENTIAL ZONES

General Policy Statement:

The following general policies shall apply in the residential zones,except where the policies and principles are superseded by an approved spatial development framework or spatial development plan;
(i)Residential zones are intended to provide neighbourhoods with single family dwelling units with various densities and to protect the character and nature of residential areas. The general purpose of the residential zones is to present a comfortable, healthy, safe and pleasant environment for living and to promote the stability of residential areas by the protection of the character of the areas. There are, however, opportunities under controlled circumstances for work opportunities at home as well as low intensity mixed use development which is normally associated with residential uses, subject to approval by the municipality;
(ii)Opportunities are created under residential zone 3 for innovative design solutions and land use provisions that are specific to the premises to make various life styles, such as residential golf estates, marinas and horse riding estates, possible;
(iii)In recognition of housing backlogs and present socioeconomic realities, provision is made under residential zone 4 for informal housing in specific areas. In such areas building and planning standards are relaxed, but still with the purpose to upgrade them to an acceptable standard as soon as possible. When this standard is reached, the relevant land must be rezoned to residential zone 2.

Residential Zone 1: Low density (R1)

Colour notation: Yellow.Objective:The objective of this zone is to provide low to medium density residential development on relatively large erven and to protect the quality and character of such areas. Limited provision of employment and additional accommodation opportunities are possible as primary and consent uses, provided that the dominant use of the land remains residential and the impact of such use does not adversely affect the surrounding residential area.
1.1.Use of land:The following use restrictions apply to land in this zone:
(a)Primary use: dwelling house.
(b)Consent uses: Second dwelling, double dwelling house, bed-and-breakfast establishment, day care centre, place of instruction, place of worship, home occupation.
(c)Additional use rights: The occupant of a dwelling house may rent out rooms in the dwelling house, subject to paragraph 1.1.5.
1.1.1Land use provisions:The following land use provisions apply:
(a)CoverageSubject to the provisions of paragraph 1.1.4(h):
(i)the maximum coverage for erven with a net area of less than or equal to 1000m² is 50%, and
(ii)the maximum coverage for erven with a net area larger than 1000m² is 500m², subject to the condition that if the municipality is convinced that there will not be any substantial negative impact, the coverage of 500m² for a land unit with an area larger than 1000m² may be increased, provided that such coverage does not exceed 40%.
(b)Height
(i)No building shall exceed a height of two storey’s, provided that where the slope of the grade-line is greater than 1 in 5, the owner may elect to regulate height in accordance with (ii) below;
(ii)Where height is regulated in terms of this sub-section, no point on a building shall exceed a vertical distance of 6m in the case of a flat roofed building, or 8m in the case of a pitched roof building, above a point halfway on the grade line, provided that if it is a pitched roof building, only the roof structure may exceed a height of 6m.
(c)Building lines
(i)Street building lineThe street building line is determined as follows: Where the average depth of the land unit,• does not exceed 20m, the street building line is 3m, or• exceeds 20m and the street building line is a public road, the street building line is 4m.
(ii)Side building lineThe side building line is 1,5m, subject to the provisions applicable in respect of all zones.
(iii)Rear building lineThe rear building line is 2m, subject to the general provisions applicable with respect to all zones.
(iv)Garages and carportsGarages and carports may be erected under the circumstances described in the general provisions, as applicable in respect of all zones.
(v)Exceeding of building linesEaves may exceed the prescribed street or side building line by a maximum of 0,75m, and the municipality may approve of the erection of an outbuilding or second dwelling unit which exceeds a side building line, subject to the following:• that the street building line is adhered to;• that such building may not exceed the height of one storey;• that no doors or windows may be permitted in any wall of such building facing the relevant side boundary, and• that another entrance than through a building will be provided, at least 1m wide, from a street to each unbuilt part of the relevant land unit, excluding a courtyard.
1.1.2Subdivision and density standardsThe following subdivision and density provisions shall apply:
(a)Minimum subdivision size
(i)The zoning map may designate areas within this zone where a minimum subdivision size is specified for a land unit.
(ii)Where a minimum subdivision size is specified in terms of (a)(i) above, the net erf area of erven created by a new subdivision or any remainder to be zoned as residential zone 1, shall not be less than the minimum size specified.
(b)Maximum density
(i)The zoning map may designate areas within this zone where a maximum density is specified for a land unit, area or precinct.
(ii)Where a maximum density is specified in terms of (b)(i) above, the gross density of development on the land unit, area or precinct shall not exceed the maximum density specified.
1.1.3Home occupationThe following provisions shall apply where a portion of a dwelling house or dwelling unit is used for the purposes of home occupation:
(a)the dominant use of the dwelling house or dwelling unit shall be for the living accommodation of a single family;
(b)no portion of such dwelling, and no home occupation, shall be used for the purposes of a noxious trade, a risk activity or the sale of alcoholic beverages;
(c)no goods for sale shall be publicly displayed and no external evidence of the home occupation shall be visible from the street, except for an advertising sign in accordance with (d);
(d)no advertising sign shall be displayed other than a single un-illuminated sign or notice not projecting over a street, and such sign shall not exceed 2000cm² in area and shall indicate only the name, telephone number and profession or occupation of the occupant;
(e)on-site parking must be provided at the satisfaction of the municipality;
(f)the space used for an activity associated with a home occupation shall not occupy more than 25% of the total floor area of the dwelling on the land unit or 50m², whichever is the most restrictive;
(g)no products, goods, or supplies connected with the home occupation may be stored on the land unit outside a building;
(h)no more than four persons in total may be engaged in home occupation activities on a land unit, including the occupant or occupants and any assistants;
(i)no more than one commercial vehicle with a gross weight exceeding 10 000 kg, may be utilised for the home occupation, provided that a vehicle used by an occupant exclusively for personal purposes shall not be regarded as a commercial vehicle;
(j)the hours of operation shall not extend beyond the hours of 07h30 to 17h30, and
(k)any new structure, or alteration to the existing dwelling or outbuilding, shall conform to the residential character of the area concerned.
1.1.4Second dwelling unit, double dwelling houseIn granting its consent for a second dwelling unit or double dwelling house, the municipality may impose, but is not limited to, the following conditions:
(a)total floor space of a second dwelling unit shall not exceed 120m², while the total floor space of a dwelling unit in a double dwelling house is not subject to this restriction;
(b)a second dwelling unit shall be constructed in an architectural style, with external materials, finishes and colours, compatible to the main dwelling house;
(c)a second dwelling unit shall not exceed one storey in height;
(d)both dwelling units in a double dwelling house shall be designed to give the appearance of a single large dwelling house, and both units may have a ground storey or one unit may be on the ground storey and one on the storey above;
(e)the municipality may stipulate minimum subdivision sizes and maximum density ratios for specified areas, as a requirement in granting consent for a second dwelling unit or double dwelling house;
(f)the dwelling units in a double dwelling house may be separately alienated in terms of the Sectional Titles Act;
(g)a second dwelling unit or a dwelling unit in a double dwelling house shall not be deemed as sufficient reason for the municipality to approve subdivision of the land unit containing a second dwelling or double dwelling;
(h)coverage, including all buildings, shall be at most 66%;
(i)at least one additional parking bay shall be provided on the land unit, and
(j)the municipality’s relevant municipal services department has certified that capacity is available on the services network in the area in which such second dwelling or double dwelling house is to be constructed.
1.1.5Bed and breakfast establishment, accommodation of lodgersIn granting its consent for a bed and breakfast establishment, or where rooms are let to lodgers by an occupant of a dwelling house, the municipality may impose, but is not limited to, the following conditions:
(a)the dominant use of the land unit must remain as a dwelling for the living accommodation of a single family;
(b)no more than three rooms per land unit shall be used for bedroom accommodation for paying guests or lodgers, who may be supplied with lodging or meals at any time;
(c)a register of guests and lodgers must be kept, and completed when rooms are let, and the register must be produced for inspection on request by a municipality official;
(d)every guest room must be attached to the dwelling house, or second dwelling unit, whichever is applicable;
(e)guest rooms may not be converted to, or used as separate dwelling units;
(f)only meals which are supplied to guests or lodgers who have lodging at the bed and breakfast establishment, are permitted;
(g)no advertising sign shall be displayed other than a sign or notice not projecting over a public street, and such sign may not exceed 1m² in area;
(h)on-site parking must be provided at the satisfaction of the municipality, subject to the parking areas being provided with a permanent dust free surface whether it be tar, concrete, paving or any other material, as approved by the municipality beforehand, and the parking bays need to be clearly demarcated, and
(i)where a land unit contains both a bed and breakfast establishment and rooms which are available for letting to lodgers, no more than six persons are permitted at any one time, as paying guests or lodgers.
1.1.6Day care centreIn granting approval for a day care centre, the municipality may impose, but is not limited to, the following conditions:
(a)no more than 20 children shall be enrolled at the day care centre at any time, and
(b)a minimum area of indoor play space and outdoor play space shall be provided in accordance with the following table:
Indoor Play SpaceOutdoor Play Space
1.8m² per child, of which not morethan one third may be enclosedveranda space.4.5m² per child, to be fenced offfrom any public street
1.1.7Places of instruction, places of worshipWith the exception of boundary walls and fences, no building erected or used for these purposes, may be located closer than 10m from any boundary of the land unit.
1.1.8Places of worship: parkingThe requirement in respect of the minimum provision of onsite parking which is prescribed for places of assembly in the business zone is applicable and must be observed.

Residential Zone 2: Medium density (R2)

Colour notation: Yellow.Objective:The objective of this zone is to provide development on relatively small erven and to protect the quality and character of such areas. Limited provision of employment and additional accommodation opportunities are possible, provided that the dominant use of the land remains residential and the impact of such uses does not adversely affect the surrounding residential area.
1.2Use of land:The following use restrictions apply to land in this zone:
(a)Primary use: dwelling house.
(b)Consent uses: second dwelling, bed and breakfast establishment, day care centre, guest house, house shop, house tavern, home occupation.
(c)Additional use rights: The letting out of rooms in the dwelling house by an occupant of the dwelling house subject to paragraph 1.2.5.
1.2.1Land use provisions:The following land use provisions apply:
(a)CoverageThe maximum coverage is 60%.
(b)Height
(i)The maximum height of buildings is two storey’s, provided that where the slope of the grade-line is greater than 1 in 5, the owner may elect to regulate height in accordance with sub-section (ii) below;
(ii)Where height is regulated in terms of this sub-section, no point on a building shall exceed a vertical distance of 6m in the case of a flat roofed building, or 8m in the case of a pitched roof building, above a point halfway on the grade line, provided that if it is a pitched roof building, only the roof structure may exceed a height of 6m.
(c)Building lines
(i)Street building lineThe street building line is 2m and is subject to the general provisions applicable to all zones.
(ii)Side building lineThe side building line is 1m and is subject to the general provisions applicable to all zones.
(iii)Rear building lineThe rear building line is 1m and is subject to the general provisions applicable to all zones.
(d)Window and door placementAny portion of a building which contains a window or door facing directly onto a side or rear boundary, shall comply to the safety distance as determined by the National Building Regulations. The portion of the building required to be placed back from the boundary shall include the window or door, together with such additional length of wall as is required to make up a total length of at least 3m.
(e)Garages and carportsGarages and carports may be erected under the circumstances described in the general provisions applicable to all zones.
(f)Parking and accessParking and access must be provided on the land unit in accordance with the provisions of paragraph 13.1 applicable to all zones.
1.2.2Subdivision and density standardsThe following subdivision and density provisions shall apply:
(a)Minimum subdivision area
(i)The zoning map may designate areas within this zone where a minimum subdivision size is specified for a land unit;
(ii)Where a minimum subdivision size is specified in terms of (a) (i) above, the nett erf area of erven created by a new subdivision or any remainder to be zoned as residential zone 2, shall not be less than the minimum size specified.
(b)Maximum density
(i)The zoning map may designate areas within this zone where a maximum density is specified for a land unit, area or precinct;
(ii)Where a maximum density is specified in terms of (b)(i) above, the gross density of development on a land unit, area or precinct shall not exceed the maximum density specified.
1.2.3Second dwelling unit, double dwelling houseThe land use provisions applicable to a second dwelling unit and double dwelling house in this zone shall be the same as those applicable in the residential zone 1.
1.2.4Home occupationThe land use provisions applicable to home occupation in this zone shall be the same as those applicable in residential zone 1; provided that no more than 4 persons in total may be engaged in home occupation activities on a land unit, including the occupant or occupants and any assistants.
1.2.5Bed and breakfast establishment, accommodation of lodgersThe land use provisions applicable to a bed and breakfast establishment and lodgers in a residential zone 1 shall also apply in this zone.
1.2.6Day care centreIn granting its consent for a day care centre, the municipality may impose, but is not limited to, the following conditions:
(a)no more than 20 children may be enrolled with the day care centre at a time.
(b)a minimum area of indoor play space and outdoor play space shall be provided in accordance with the following table:
Indoor Play SpaceOutdoor Play Space
1.8m² per child, of which not moreveranda space.4.5m² per child, to be fenced offfrom any public street
1.2.7House shopIn granting its consent for a house shop, the municipality may impose, but is not limited to, the following conditions:
(a)the extent and position of the retail component must be clearly defined on a plan, and shall not exceed 25m² or 50% of total floor space (excluding any toilet, change room and storeroom), whichever is the lesser area;
(b)in addition to the house shop, the land unit must contain a dwelling house which shall be occupied by the owner of the house shop;
(c)any new structure, or alteration to the existing dwelling or outbuilding, shall conform to the residential character of the area concerned;
(d)no more than three persons, including the occupant of the dwelling house, are permitted to be engaged in retail activities on the land unit;
(e)only one sign shall be permitted and shall not exceed 1m² in area, and shall not exceed the land unit boundaries with any part of it, while it shall indicate only the name of the owner, name of the business and nature of the retail trade;
(f)the following are not permitted in a house shop:
(i)sale of liquor or alcoholic beverages;
(ii)storage or sale of gas and gas containers;
(iii)vending machines;
(iv)video games, and
(v)snooker or pool tables, and
(g)permission to operate a house shop is granted to a particular operator who operates from a particular land unit, and is not transferable.
1.2.8House tavernIn granting its consent for a house tavern, the municipality may impose, but is not limited to, the following conditions:
(a)the extent and position of the house tavern must be clearly identified on a plan to be approved by the municipality, and the municipality may restrict the floor area or specific location of the house tavern on the land unit;
(b)in addition to the house tavern, the land unit must contain a dwelling house which shall be occupied by the owner of the house tavern;
(c)the municipality may restrict the maximum number of patrons, operating hours, number of staff and signage relating to the house tavern;
(d)the municipality may require structural alterations to the land unit for fire or health reasons, and to ensure that the impact of the house tavern on neighbouring uses is minimized;
(e)the owner of the house tavern must obtain a liquor license in terms of the relevant legislation, and in the event of the liquor license being withdrawn or suspended, the municipality’s consent for the operation of the house tavern shall automatically lapse, and;
(f)only one sign shall be permitted, and shall not exceed 1m² in area, and shall not exceed the land unit boundaries with any part of it, while it shall indicate only the name of the owner, name of the business and nature of the retail trade.

Residential Zone 3: High density (R3) Estate housing

Density: 40 units per hectare gross.Colour notations: Yellow.Ojective:The objective of this zone is to provide a high degree of flexibility for low to medium density residential projects which have integrated site and design features, and which require individual design solutions and individually tailored development control provisions. This zone does not accommodate a resort, but is particularly suitable for residential estates that are governed by a home owners’ association, with access control and co-ordinated design requirements (such as golf estates, equestrian estates and residential marinas).
1.3Use of land:The following use restrictions apply to land in this zone:
(a)Primary uses: dwelling house, private open space.
(b)Consent uses: group housing, town housing, flats, hotel, restaurant, place of assembly, home occupation.
1.3.1 Land use provisions:The following land use provisions shall apply:
(a)the municipality may stipulate conditions with regard to the use of buildings and land, density, height, coverage, layout, building design, open space, landscaping, parking, access and environmental management;
(b)a site development plan must be submitted at the satisfaction of the municipality;
(c)the constitution for a home owners’ association must be submitted at the satisfaction of the municipality, and all owners of land within this zone shall be members of an approved home owners’ association;
(d)architectural guidelines and a system of architectural control must be submitted at the satisfaction of the municipality;
(e)an environmental management plan must be submitted at the satisfaction of the municipality, and
(f)the land unit must be developed:
(i)in accordance with the site development plan, architectural guidelines and environmental management plan as approved by the municipality, and
(ii)at the satisfaction of the municipality.
1.3.2Home occupationThe municipality may grant its consent for home occupation in this zone provided that:
(a)no consent application shall be considered unless the owner has obtained the prior written comment of the relevant home owners’ association, and;
(b)if the municipality grants its consent, such consent will be subject to the same conditions applicable in residential zones 1 and 2 relating to a dwelling house or dwelling unit which is used for the purpose of home occupation, and the municipality may also impose additional conditions which may be even more restrictive.

Residential Zone 4: Incremental housing (R4)

Density: Maximum 100 units per hectare, gross.Colour notation: Yellow.Objective:The objective of this zone is to allow for upgrading and incremental housing transforming informal settlements into formal settlements. In recognition of the realities of poor and marginalized communities, land use provisions are not restrictive and local employment generation is encouraged within this zone. Once the upgrading of an area has reached an appropriate stage, as determined by the municipality, it is contemplated that the area may be rezoned to a residential zone 2 zone or another such zone.
1.4 Use of land:The following use restrictions apply to land in this zone:
(a)Primary uses: dwelling house, second dwelling unit, bed and breakfast establishment, shelter.
(b)Consent uses: double dwelling house, day care centre, place of instruction, house tavern, house shop, home occupation.
1.4.1Land use provisions:The following land use provisions shall apply:
(a) CoverageThe maximum coverage is 80%.
(b)HeightNo building shall exceed a height of two storey’s.
(c)Building lines
(i)Street building lineThe street building line is 1m.
(ii)Side building lineIf the municipality is satisfied that adequate fire protection measures exist, a land unit may have a zero side building line on one side boundary, provided that there is at least a 1m side building line on the other side boundary, and that the combined distance between two structures on adjacent land units amounts to 2m. If, in the municipality’s opinion, there are inadequate fire protection measures on the land unit, the side building line shall be at least 1m from both side boundaries.
(iii)Rear building lineThe rear building line is 1m, provided further that if a mid-block sewerage system is installed, a rear building line of 2m may be imposed by the municipality.
(d)Garages and carportsGarages and carports may be erected under the circumstances described in the general provisions, as applicable in respect of all zones.
(e)Parking and access
(i)Parking shall be provided on the land unit in accordance with the following table:
Use of land or buildingParking standard
ShelterNo parking required
Dwelling house, double dwellinghouseOne parking bay if required by themunicipality
Second dwelling unit, homeoccupation, bed and breakfastestablishmentAs required by the municipality
Place of instruction, place ofworship, House shop, house tavernAs required by the municipality
(ii)Land units in this zone are exempt from the requirements of paragraph 13.1 relating to parking and access.

Chapter 2
GENERAL RESIDENTIAL ZONES

General Policy Statement:The following general policies and principles shall apply in the General Residential Zones unless these policies and principles are superseded by an approved spatial development framework or spatial development plan:(i)Higher density residential development needs to be encouraged in suitable areas to help manage the pressure of urban growth and reduce urban sprawl. The general residential zones aim to provide a healthy, safe and pleasant environment for urban living at higher densities;(ii)The general residential zones are designed to provide opportunities for multi-family residential development at a variety of densities;(iii)Within the general residential zones there are controlled opportunities for home occupation and low intensity mixed use development. However, it is important to balance these needs with the need to protect the character and amenity of the residential area.General Residential Zone 1: Group housing (GR1)Density: Maximum 30 units per hectare gross.Colour notation: Orange.Objective:The objective of this zone is to encourage residential development of a medium density, with a co-ordinated design, and to accommodate group housing where special attention is given to aesthetics, architectural form and the interrelationship between components of the group housing scheme.
2.1.Use of land:The following use restrictions apply to land in this zone:
(a)Primary use: group housing, dwelling house.
(b)Consent use: home occupation.
2.1.1Land use provisions:The following land use provisions shall apply to group housing sites:
(a)Design principles
(i)The principles that are reflected in the definition of "group housing", must be closely followed and implemented;
(ii)Special attention must be given to aesthetics, architectural co-ordination, urban design and landscaping.
(b)Density
The maximum gross density for group housing sites shall be 30 dwelling units per hectare.
(c) Height
(i)No building shall exceed a height of two storey’s, provided that where the slope of the grade-line is greater than 1 in 5, the owner may elect to regulate height in accordance with (ii) below;
(ii)Where height is regulated in terms of this sub-section, no point on a building shall exceed a vertical distance of 6m in the case of a flat roofed building, or 8m in the case of a pitched roof building, above a point halfway on the grade line, provided that if it is a pitched roof building, only the roof structure may exceed a height of 6m.
(d)Open space
(i)Each dwelling unit shall have access to an outdoor living area, which may include private, public or communal open space but excludes roads, service yards and parking areas;
(ii)A minimum outdoor living area of 50m2 per dwelling unit shall be provided on the erf containing the dwelling unit, and a minimum of 50m2 per dwelling unit shall be provided as public or communal open space within the group housing site;
(iii)Where there is no distinction between public or communal open space, and an outdoor living area is provided on each erf, the open space requirements shall be replaced by a combined open space requirement of at least 100m2 per dwelling unit within the group housing site;
(iv)If, in the opinion of the municipality, sufficient outdoor living area has been provided on each erf, where public or communal open space has been provided appropriately in the environment (partly or completely), the minimum requirements for public or communal open space per dwelling unit may be decreased.
(e)Service yard
A service yard shall be provided for each dwelling unit, or a combined service yard may be provided for several units. Service yards shall be of an adequate area and screened by a wall, at the satisfaction of the municipality.
(f)Store room
A store room with a minimum inner floor space of 2m2 must be provided on each group erf if no lock-up garage is provided on the erf.
(g)Building lines
(i)Street building lines shall be 2m to ensure safe parking and traffic circulation;
(ii) Side and rear building lines• Internal side and rear building lines may be zero unless the municipality requires a building line for firefighting purposes, and• where a group housing site abuts on another zone or another group housing site, the side and rear building lines shall be 2m.
(h)Parking and access
(i)Parking and access shall be provided in accordance with paragraph 13.1;
(ii)at least two parking bays are required per group house; both can be provided at such group house, or some of the required number of parking bays at some of the group houses and the rest in the form of communal parking for the relevant group housing scheme, or the total requirement in the form of communal parking.
(i)Internal street widthThe minimum internal road reserve width is 8m, provided that the municipality may require a greater road reserve width where it is of the opinion that the vehicular use or length of road justifies greater road reserve width.
2.1.2Site development plan
A site development plan of the proposed group housing scheme, must be submitted at the satisfaction of the municipality, and the municipality’s approval in respect of the proposed development must be attained in terms of paragraph 12.6.
2.1.3Proximity of group housing schemes
The municipality shall not approve the establishment of an additional group housing scheme adjacent to, or in close proximity to, an existing group housing scheme unless, in its opinion, the following minimum conditions are adhered to:
(a)Adequate provision must be made outside any walls surrounding the additional group housing scheme for landscaping, either on the group housing site, in the road reserve, or on public open space in the vicinity of the group housing site;
(b)any boundary walls or fences situated between the additional group housing site and a public street, must be designed and constructed to allow adequate visual contact between the additional group housing site and the public street, and
(c)a plan, acceptable to the municipality, must be prepared, which co-ordinates the provision of public amenities, including community facilities, public streets, public open space and public transport requirements.
2.1.4Home occupation
The municipality may grant its consent for home occupation in this zone, provided that:
(a)no consent application shall be considered unless the owner has obtained the prior written comment of the relevant home owners’ association, and
(b)if the municipality grants its consent, such consent will be subject to the same conditions applicable to single residential zones 1 and relating to a dwelling house or dwelling unit which is used for the purpose of home occupation, and the municipality may also impose additional conditions which may be even more restrictive.
General Residential Zone 2: Town housing (GR2)Density: Maximum 50 units per hectare gross.Colour notation: Orange with black hatching.Objective:The objective of this zone is to encourage residential development of a greater density than for general residential zone 1 while retaining the emphasis on design co-ordination and a modest scale in terms of height. Opportunities are also provided for small-scale integration of flats within the co-ordinated scheme.
2.2Use of land:The following use restrictions apply to land in this zone:
(a)Primary use: town housing, dwelling house.
(b)Consent uses: flats, home occupation.
2.2.1Land use provisions:The following land use provisions shall apply to town housing development:
(a)Design principles
(i)The principles which are reflected in the definition of "town housing", shall be closely followed and implemented;
(ii)Special attention shall be given to aesthetics, architectural co-ordination, urban design and landscaping.
(b)Density
The maximum gross density for town housing sites shall be 50 units per hectare.
(c)Coverage
The maximum coverage is 50%.
(d)Height
(i)No building shall exceed a height of 3 storey’s, provided that where the slope of the grade-line is greater than 1 in 5, the owner may elect to regulate height in accordance with (ii) below;
(ii)Where height is regulated in terms of this sub-section, no point on a building shall exceed a vertical distance of 9m in the case of a flat roofed building, or 11m in the case of a pitched roof building, above a point halfway on the grade line, provided that if it is a pitched roof building, only the roof structure may exceed a height of 9m.
(e)Building lines
(i)Street building lines shall be 2m to ensure safe parking and traffic circulation;
(ii)Side and rear building lines• internal side and rear building lines may be zero except if the municipality requires a building line for firefighting purposes, and• where a town housing site abuts another zone or another town housing site, the side and rear building lines shall be 2m
(f)Parking and access
(i)Parking and access shall be provided in accordance with paragraph 13.1;
(ii)at least two parking bays are required per town house; both can be provided at such town house, or some of the required number of parking bays at some of the town houses and the rest in the form of communal parking for the relevant town housing scheme or the total requirement in the form of communal parking.
(g)Internal street width
The minimum internal road reserve width is 8m provided that the municipality may require a greater road reserve width where it is of the opinion that the vehicular use or length of road justifies such greater road reserve width.
2.2.2Site development plan
A site development plan of the proposed town housing scheme must be submitted to the municipality and the municipality’s approval thereof, in terms of paragraph 12.6, obtained.
2.2.3Home occupation
The municipality may grant its consent for home occupation in this zone provided that:
(a)no consent application shall be considered unless the owner has obtained prior written comment of the relevant home owners’ association, and
(b)if the municipality grants its consent, such consent will be subject to the same conditions applicable in single residential zones 1 and relating to a dwelling house or dwelling unit which is used for the purpose of home occupation, and the municipality may also impose additional conditions which may be even more restrictive.
General Residential Zone 3: Flats (GR3)Density: Maximum floor factor of 2.0.Colour notation: Orange with black cross hatching.Objective:The objective of this zone is to encourage higher density residential development and multi-family buildings of medium height.
2.3Use of land:The following use restrictions apply to land in this zone:
(a)Primary uses: flats, guest house, boarding house, dwelling house, group housing, town housing.
(b)Consent uses: shop, lodge, institution, place of instruction, place of assembly, home occupation, transmission tower, rooftop base station.
2.3.1Land use provisionsThe following land use provisions shall apply to flats, boarding houses and guest houses.
(a)Floor factor
The floor factor shall not exceed 2.0.
(b) Coverage
The maximum coverage is 40%.
(c)Height
No building shall exceed a total height of 21m.
(d)Building lines
(i)Street building lineThe street building line is 5m.
(ii)Side and rear building linesSide and rear building lines shall be 5m.
(e)Open space
(i)Every block of flats, boarding house, lodge, guest house or, for any other land use in this zone, each dwelling unit, shall have access to an outdoor living area, which may include private or communal open space but excludes roads, service yards and parking areas;
(ii)A minimum outdoor living area of 10% of the gross land unit area shall be provided;
(iii)The outdoor living area may include an open courtyard within the complex and shall have reasonable dimensions and be situated where it can be used equitably by all occupants.
(f)Parking and access
Parking and access shall be provided on the land unit in accordance with paragraph 13.1.
2.3.2Site development plan
The municipality may require a site development plan to be submitted to its satisfaction in terms of paragraph 12.6 for consideration and approval, provided that the municipality may require amendments to the site development plan to address reasonable concerns relating to access, parking, architectural form, urban design, landscaping, engineering services or similar matters.
2.3.3Group housing
The land use provisions applicable to group housing in general residential zone 1 shall also apply to group housing in this zone.
2.3.4Town housing
The land use provisions applicable to town housing in the general residential zone 2 shall also apply to town housing in this zone.
2.3.5Institutions, places of instruction, places of assembly
The land use provisions which respectively apply to an institution, place of instruction and a place of assembly in community zone 1 shall also apply in this zone. However, in cases where the institution, place of instruction or place of assembly is situated within a building that is also used for flats or a boarding house, the coverage, height and building line requirements for the flats or boarding house shall apply.
2.3.6Home occupation
The municipality may grant its consent for home occupation in this zone provided that:
(a)no consent application shall be considered unless the owner has obtained the prior written comment of the relevant home owners’ association, and
(b)if the municipality grants its consent, such consent will be subject to the same conditions applicable in single residential zones 1 and 2 relating to a dwelling house or dwelling unit which is used for the purpose of home occupation, and the municipality may also impose additional conditions which may be even more restrictive.
2.3.7Shop
The municipality may grant a consent use for a shop to be incorporated within the ground floor of a block of flats, provided that the gross leasable area of the shop does not exceed 500m² or 25% of the floor space of the ground floor, whichever is the lesser.
2.3.8Rooftop base station
A rooftop base station’s antenna support structure or equipment room that is not part of the building may not extend more than 2,5m in height above the top of the building to which it is attached without the prior approval of the municipality, within any zone in terms of this zoning scheme.

Chapter 3
BUSINESS ZONES

General Policy Statement:The following general policies and principles shall apply in the business zones unless these policies and principles are superseded by an approved spatial development framework or spatial development plan:(i)The business zones are designed to provide locations for a wide range of economic activities, and to include mixed land uses such as residential and community development. Different business zones permit different levels of development intensity;(ii)Provisions are included to encourage, where appropriate, the use of detailed urban design criteria to achieve specific urban environments and mix of uses;(iii)The business zones are intended to be in context with the scale and intensity of development in the surrounding area. Low intensity business zones are appropriate for local neighbourhood shops, while high intensity business centres are appropriate for a central business district that accommodates a full range of compatible land uses;(iv)Particular business zones are provided for petrol filling stations and associated development because of important road access implications.Business Zone 1: General business (BZ1)Colour notation: Blue.Objective:The objective of this zone is to provide for mixed use development, general business activities and intensive business opportunity with relatively few restrictions in order to promote urban viability and economic growth.
3.1. Use of land:The following use restrictions apply to land in this zone:
(a)Primary uses: business premises, flats, offices, office park, restaurant, service trade, public parking, animal hospital, nursery, transmission tower, rooftop base station, wine shop.
(b)Consent uses: service station, hotel, funeral parlour, car wash, residential building, place of assembly, place of entertainment, adult entertainment enterprise, institution, bottle store.
3.1.1Land use provisions:The following land use provisions apply:
(a)Floor factor
The floor factor of the land unit shall not exceed 3.0.
(b)Coverage
The maximum coverage is 100%.
(c) Height
(i)No building may exceed a height of 6 storey’s;
(ii)Notwithstanding the definition of a "storey", the ground storey of a building in business zone 1 may extend 4m from the surface of the ground floor to the surface of the next floor above.
(d)Setback
(i)The municipality may require that all buildings or structures on the land unit are set back at least 8m from the centre line of the abutting public street or streets;
(ii)The provisions of paragraph 12.1 shall apply.
(e) Street building lineThe street building line is zero subject to the following:
(i)the setback regulation;
(ii)a 5m street building line may be required where the street boundary abuts a declared road, and
(iii)minor architectural and sun screen features may project or extend beyond the street building line provided that such features are situated above the ground storey and do not project more than 1000mm into the street.
(f)Side and rear building lineThe side and rear building lines may be zero, provided that:
(i)a building or portion of a building which is erected on the side boundary of a land unit shall have no doors, windows, ventilation openings or other openings inserted in any wall on such boundary, unless the municipality is satisfied that such opening will not adversely affect any future development on adjacent land units, and
(ii)where the side boundary of a business zone 1 land unit abuts a residential zone land unit, the side building line on the business zone 1 shall be 3m from that side of the rear or side boundary, subject to paragraph 12.1.
(g)Canopies or balconies
The municipality may require, and may permit, a canopy or balcony projection over the street boundary in accordance with the conditions stipulated for a canopy or balcony projection in business zone 2.
(h)Projection over the street boundaryNotwithstanding the street building line, the municipality may permit a projection of the building over the street boundary subject to the following conditions:
(i)The projection may not encroach over the 1,5m street boundary;
(ii)The projection may extend from the building at a level between the ground storey and the storey above that, or if not, then one storey higher;
(iii)The ground floor level of the projection shall be used exclusively as a public pedestrian way, with or without a colonnade;
(iv)The projection shall provide at least 2,8m clearance above the level of the pavement,
(v)The floor space of the additional storey that may be erected over the ground floor level of the projection shall not be included in the calculation of maximum floor space.
(i)Public pedestrian way along the street boundary
If the owner provides a public pedestrian way of at least 3m wide on the land unit, which is situated alongside the street boundary, is open to a public street and is accessible to the public at all times, the maximum floor space of a building which contains a public pedestrian way, may be increased by twice the area of the public pedestrian way.
(j)Street corners
The municipality may require that the owner of a building, situated at a public street corner which the municipality considers to be significant, shall incorporate in the building architectural features which focus visual interest on the corner, and which emphasize the importance of pedestrian movement around the corner. Such features may include building cut-offs, walkthrough covered arcades, plazas or other elements.
(k)Parking and access
(i)Parking and access shall be provided on the land unit in accordance with paragraph 13.1. Primary use, excluding places of assembly: 4 parking bays per 100m² of the total floor space shall be provided;
(ii)Places of assembly: one parking bay for every 4 seats provided in the building.
For the purpose of loading and off-loading goods from vehicles, space or spaces shall be provided on the site and at the satisfaction of the municipality as follows:
Total floor space of building (tonearest m²)Required loading and off-loadingarea
0– 2 500m²1 loading bay
2 501– 5 000m²2 loading bays
5 001–10 000m²3 loading bays
Each additional 10 000m² orportion thereof1 additional loading bay
(l)Screening
The municipality may require screening in accordance with the conditions stipulated in business zone 2.
3.1.2Site development plan
The municipality may require a site development plan to be submitted to its satisfaction in terms of paragraph 12.6 for consideration and approval, provided that the municipality may require amendments to the site development plan to address reasonable concerns relating to access, parking, architectural form, urban design, landscaping, engineering services or similar matters.
3.1.3Office park, industrial hiveThe following land use provisions and design principles shall apply to an office park:
(i)The principles reflected in the relevant definition shall be closely followed and implemented;
(ii)Special attention shall be given to aesthetics, architectural co-ordination, urban design and landscaping;
(iii)A site development plan of the proposed development must be submitted at the satisfaction of the municipality in terms of paragraph 12.6.
Business Zone 2: Neighbourhood business (BZ2)Colour notation: Blue with black cross hatching.Objective:The objective of this zone is to provide for low intensity commercial and mixed-use development which satisfies the needs of the local precinct for commodities and personal services. Such development should be limited in extent and must be able to integrate with the adjacent precinct without adversely affecting the amenities of the residential precinct.
3.2Use of land:The following use restrictions apply to land in this zone:
(a)Primary uses: business premises, flats, public parking, transmission tower, rooftop base station, wine shop.
(b)Consent uses: offices, place of assembly, place of entertainment, restaurant, bottle store, service trade, car wash, nursery, lodge.
3.2.1Land use provisions:
The following land use provisions apply:
(a)Floor factor
No building in this zone may exceed a floor factor of 1,5 whereby not less than 0,75 may be used for dwelling purposes above the ground floor.
(b)Coverage
The maximum coverage is 75%.
(c)Height
(i)No building shall exceed a height of 2 storey’s;
(ii)Notwithstanding the definition of "storey", the ground storey of a building in business zone 2 may extend to 4m from the surface of the ground floor to the surface of the next floor above.
(d)Setback
(i)The municipality may require that all buildings or structures on the land unit are setback at least 6,5m from the centre line of the abutting street or streets;
(ii)The provisions of paragraph 12.1 shall apply.
(e) Street building line
(i)The street building line is subject to:• the setback regulation, and• a 5m street building line that may be required where the street boundary abuts a declared road;
(ii)Minor architectural and sun screen features may project or extend beyond the street building line provided that such features are situated above the ground storey and do not project more than 1000mm beyond the street boundary.
(f)Side building lineThe side building lines may be zero, provided that:
(i)a building or portion of a building which is erected on the side boundary of a land unit shall have no doors, windows or ventilation or other openings inserted in any wall on such boundary, unless the municipality is satisfied that such opening will not adversely affect any future development on adjacent land units, and
(ii)where the side boundary of a business zone 2 land unit abuts a single or general residential zone land unit, the side building line on the business zone 2 land unit shall be 3m, subject to paragraph 12.1.
(g)Rear building line
The rear building line is 3m, subject to paragraph 12.1.
(h)Canopies and balconiesThe municipality may require, and may permit, a canopy or balcony projection over the street boundary in accordance with the following condition:
(i)the canopy shall not project nearer than 1000mm to a vertical plane through the street boundary or proposed kerb line;
(ii)no portion of a canopy projection shall be less than 2,8m above the pavement, and
(iii)the municipality may lay down more restrictive requirements relating to the dimensions, design and materials of the canopy or balcony.
(i)Street corners
The municipality may require that the owner of a building, situated at a public street corner which the municipality considers to be significant, shall incorporate in the building architectural features which focus visual interest on the corner, and which emphasize the importance of pedestrian movement around the corner. Such features may include building cut-offs, walkthrough covered arcades, plazas or other elements.
(j)Parking and access
(i)One parking bay per 25m2 of the total floor space is required in respect of all the primary and consent uses, however with the exception of dwelling units and places of assembly;
(ii)One point two five (1.25) parking bays for every dwelling unit and 1 additional parking bay for every 4 dwelling units. Of the parking bays described above, one uncovered parking bay for every 4 dwelling units must be provided on the premises and demarcated clearly and appropriately by means of a notice board, at the satisfaction of the municipality, and be indicated for use by visitors to the premises;
(iii)Places of assembly: a minimum-area shall be provided on the basis of one parking bay for every 4 seats which are provided in the building;
(iv)As an alternative to the stated parking requirement, the owner may, with the consent of the municipality, if the municipality is of the opinion that it is undesirable or impractical from a planning point of view to provide all the parking bays on the site, acquire a prescribed area of land for the relevant parking facilities elsewhere in a position approved by the municipality, provided that he registers a notarial deed of servitude for such land to the effect that the municipality and the public shall have free access thereto for the purpose of parking, and that the owner is obliged to level this land, to provide it with a surface and to maintain it at the satisfaction of the municipality, and that the costs of registration of the servitude shall be borne by the owner.
(k)ScreeningThe municipality may require that:
(i)any part of the land unit which is used for the storage or loading of goods, shall be screened with a suitable brick wall or concrete wall or suitable landscaping, and
(ii)any external utility service or equipment which is required for a building, whether on the roof, side of the building or ground, shall be appropriately screened from view, and such screening shall be integrated with the building in terms of materials, colour, shape and size and shall be to the municipality’s satisfaction.
(l)Advertising
Advertising must occur by means of advertisement signs and no pictures on walls will be allowed.
3.2.2Site development plan
The municipality may require that a site development plan be submitted to its satisfaction in terms of paragraph 12.6 for consideration and approval, provided that the municipality may require amendments to the site development plan to address reasonable concerns relating to access, parking, architectural form, urban design, landscaping, engineering services or similar concerns.Business Zone 3: Service station (BZ3)Colour notation: Blue with black hatching.Objective:The objective of this zone is to provide opportunities in urban areas, for the erection of service stations, motor repair garages and associated facilities.
3.3Use of land:The following use restrictions apply to land in this zone:
(a)Primary uses : service station, car wash, transmission tower, rooftop base station.
(b)Consent uses : shop, business premises, restaurant, wine shop.
3.3.1Land use provisions:The following land use provisions apply:
(a)Floor factor
The maximum floor factor on the land unit is 2.5.
(b) Coverage
The maximum coverage is 75%.
(c)Height
No building may exceed a height of three storey’s and no structure, including a billboard, shall exceed a height of 10m measured from a point halfway on the grade-line.
(d)Setback
(i)The municipality may require that all buildings or structures on the land unit are set back at least 8m from the centre line of the abutting public street or streets;
(ii)The provisions of 1.1 shall apply.
(e)Street building line
The street building line is 5m in the case of a declared road and 3m in the case of other roads, subject, however, to the provisions of paragraph 12.1.
(f)Side and rear building lineThe side and rear building lines may be zero, provided that:
(i)a building or portion of a building which is erected on the side boundary of a land unit shall have no doors, windows or ventilation or other openings inserted in any wall on such boundary, unless the municipality is satisfied that such opening will not adversely affect any future development on adjacent land units, and
(ii)where the side boundary of a business zone 3 land unit abuts a residential zone land unit, the side building line on the business zone 3 shall be 3m from that side of the side or rear boundary, subject to paragraph 12.1.
(g)Parking
At least 4 parking bays per repair bay and one parking bay per activities shall be provided, with a minimum of eight parking bays 50m² of the gross leas able area devoted to spares and sales on the land unit.
(h)Site access requirements
(i)The total width of vehicle carriageway crossings shall, where they cross the street boundary, not exceed 10m, regardless of whether such vehicle carriageway crossings are separate or combined;
(ii)A wall, at least 100mm thick and 200mm high, shall be erected on the street boundary between different vehicle carriageway crossings. The wall shall continue along such boundary unless the land unit is otherwise enclosed;
(iii)Vehicle carriageway crossings shall be limited to two per site, unless the total length of a street boundary exceeds 30m, in which case one additional carriageway crossing may be permitted;
(iv)Notwithstanding the provisions of (iii), where the total length of the street boundary exceeds 30m, one additional entrance and exit or one additional combined entrance and exit will be allowed;
(v)At the point where the street boundary is crossed, a vehicle carriageway crossing or combined vehicle carriageway crossing, may not be located closer than:• 30m to the intersection of a declared road with any other road of a like status;• 30m to the nearest point of an intersection where traffic is controlled, or is proposed to be controlled, by a traffic signal or traffic island, and• 10m from the corner of an intersection not referred to above, if such intersection is not splayed or 5m from the point where the splay meets the road boundary if such intersection is splayed.
(i)Screening
Any part of a land unit where a service station which is used for the repair of motor vehicles, or for the storage of inoperable motor vehicles, of parts of motor vehicles, of empty containers such as oil drums and packing cases, or of any other scrap whatsoever, is located, shall be enclosed with a brick or concrete screen wall, at the satisfaction of the municipality, at least 1,8m high, or shall be contained in a building.
(j)Advertising
Advertising must occur by means of advertisement signs and no pictures on walls will be allowed.
3.3.2Site development plan
The municipality may require a site development plan to be submitted to its satisfaction in terms of paragraph 12.6 for consideration and approval, provided that the municipality may require amendments to the site development plan to address reasonable concerns relating to access, parking, architectural form, urban design, landscaping, engineering services or similar matters.Business Zone 4: Petroport (BZ4)Colour notation: White with blue outline.Objective:The objective of this zone is to make petro ports possible, to provide facilities for motorists along main routes in order to prevent exhaustion of drivers and to provide facilities for long distance road users.
3.4Use of land:The following use restrictions apply to land in this zone:
(a)Primary uses: petroport, shop, restaurant, transmission tower, rooftop base station.
(b)Consent uses: Public garage, tourist facility, holiday accommodation, lodge, wine shop.
3.4.1Land use provisions:The following land use provisions apply:
(a)Site development planA site development plan must be submitted in terms of paragraph 12.6 for consideration and approval, provided that:
(i)the site development plan shall give particular attention to vehicle carriageway crossings and circulation, vehicle and pedestrian safety, risk management of fuel pumps and fuel tanks, the screening of areas used for storage purposes, visual impact on the surrounding rural environment, aesthetics, landscaping, impact softening on adjoining land uses, and location of buildings, indicators and structures, and
(ii)the site development plan shall comply with the development parameters as stipulated hereunder.
(b)Coverage
The maximum coverage is 50%.
(c) Height
No building may exceed a height of 2 storey’s.
(d)Street building line
The street building line is 10m.
(e)Side and rear building lines
The side and rear building lines are 3m.
(f)Parking
Parking shall be provided as follows: In the case of:
(i)public garages: 4 parking bays per repair bay, and
(ii)all other uses: one parking bay per 25m² building area plus 8 additional parking bays.
(g)Lighting
Lighting shall be provided in a manner that shall not adversely affect the safety of the users of the abutting street. Parking areas shall be lit at the satisfaction of the municipality.
(h)Billboards and advertising boards
Billboards and advertising boards shall be restricted to signs directly related to the activities of the petroport. The height of the signs on the site shall be restricted to 12m.
(i)Retail component
Retail facilities and associated storage areas shall not exceed 100m² per fuel pump.
(j)Landscaping plan
A landscaping plan shall be submitted to the municipality for approval. At least 20% of the land unit, which may include picnic areas, shall be set aside for landscaping purposes.

Chapter 4
INDUSTRIAL ZONES

General Policy Statement:The following general policies and principles shall apply in the industrial zones unless these policies and principles are superseded by an approved spatial development framework or spatial development plan.(i)The industrial zones are designed to accommodate manufacturing and related industrial processes. These cover a wide range of uses, from light industrial uses which have limited impact on surrounding areas, to hazardous or noxious uses which have a potentially high impact and need to be carefully managed;(ii)The different zones are based on the degree of potential impacts resulting from the different activities and processing of materials, including impacts associated with noxious, risk and extractive processes;(iii)Industrial development often has particular requirements in terms of road and waste infrastructure, and it is important for industrially zoned land to remain reserved for industrial purposes so that optimal utilisation of this infrastructure can be ensured;(iv)Limited opportunities are given for consent uses associated with industrial areas, such as factory shops.Industrial Zone 1: Light industry (IND1)Colour notation: Purple with black hatching.Objective:The objective of this zone is to accommodate industrial uses and service trades that may be exercised without nuisance to other land or the general public. Such uses may be located next to business uses and in close proximity to residential areas, and do not present a potentially negative impact on the character or amenity of such areas.
4.1.Use of land:The following use restrictions apply to land in this zone:
(a)Primary uses: service trade, industrial hive, warehouse, car wash, restaurant, service station, public parking, transmission tower, rooftop base station.
(b)Consent uses: industry, public garage, shop, bottle store, offices, office park, adult entertainment enterprise.
(c)Additional use rights:
The occupants of industrial or service trade premises may sell goods which have been completely or partially manufactured on the land unit, and such other goods as the municipality may permit, provided that:
(i)the total floor space devoted to the sale of goods shall not exceed 10% of the total floor space of all the buildings on the land unit, and
(ii)such other goods that are offered for sale but that have not been manufactured on the land, are connected with the goods that are manufactured or partially completed on the land.
4.1.1Land use provisions:
The following land use provisions apply (except in regard to service stations and industrial hives):
(a)Floor factor
The floor factor on the land unit shall not exceed 1.5.
(b)Coverage
The maximum coverage is 75%.
(c) Height
(i)No height restriction applies to an industry, service trade, or warehouse;
(ii)Other buildings shall not exceed 10m in height measured from a point halfway on the grade-line, provided that where a greater height is shown to be important for the function of a building, the municipality may grant permission for such greater height.
(d)Street building line
The street building line is 5m, subject to paragraph 12.1.
(e)Side building line
(i)Where an external wall is constructed of brick, cement bricks or concrete and there are no openings in such external wall, and the land unit abuts another industrial zone, a zero building line is permitted;
(ii)Where the land unit abuts a zone that is not an industrial zone, a 3m side building line or the building line as applicable in that specific zone, whichever is the largest, shall apply;
(iii)In all other cases a 3m side building line shall apply.
(f)Rear building line
(i)No building shall be erected closer than 3m to the rear boundary;
(ii)In cases where a building extends to both side building lines, and there is no other means of obtaining access to the rear of the land unit, other than through the building, at least one opening in the external wall of the building shall be provided to the rear boundary, and such opening shall be protected by automatic fire shutters at the satisfaction of the municipality.
(g)Boundary walls
Where a land unit has a common boundary with another land unit that is not zoned for industrial purposes, the municipality may require a 1,8m high wall to be erected along the boundary to its satisfaction.
(h)Parking and access
Parking shall be provided in accordance with the following table as well as paragraph 13.1:The number of parking bays to be provided on the premises, shall bare relation to the total floor area of the building and the total number of employees on the premises or a part thereof:
Parking bays in relation to the floor area of the building
1 Parking bay for every 100m² floor area or part thereof up to 1 500m²,and
1 Parking bay for every 200m² floor area or part thereof above 1500m².
25% of the abovementioned parking bays shall be set aside for use byvisitors and must be indicated as such by means of road signs.
Parking bays in relation to the number of employees on thepremises
Up to 25 employees.1 parking bay for every 4 personsor part thereof
Thereafter, for the next 25Employees.1 parking bay for every 5 personsor part thereof.
Thereafter, for the next 50Employees1 parking bay for every 10 personsor part thereof.
Thereafter, for any further numberof employees1 parking bay for every 25 personsor part thereof.
As an alternative for the stated parking requirement, the owner may, with the consent of the municipality, if the municipality is of the opinion that it is undesirable or impractical from a planning point of view to provide the required parking bays on the site, acquire a prescribed area of land for the relevant parking facilities on nearby premises in a position approved by the municipality, provided that a notarial deed is registered for such land to the effect that the municipality and the public shall have free access thereto for the purpose of parking, and that the owner is obliged to level this land, provide it with a surface and maintain it at the satisfaction of the municipality. The cost of registration of the notarial deed shall be borne by the owner. These conditions may only be amended with special approval by the municipality.
(i)Loading bays
Loading bays shall be provided in accordance with the following table as well as paragraph 13.2:
Total floor space of building (tonearest m²)Required loading and off-loadingarea
0–2 500m²1 loading bay
2 501–5 000m²2 loading bays
5 001–10 000m²3 loading bays
Every additional 10 000m² orportion thereof1 additional loading bay
Such a loading bay shall measure at least 7m x 4.5m and shall have a vehicle exit to the street (which shall be at the satisfaction of the municipality and not less than 5m wide, and if it passes through a building, not less than 3m high).
(j)Screening
The municipality may require any part of a land unit which is used for storage or the loading of goods, to be enclosed with a suitable brick or concrete screen wall to the municipality’s satisfaction.
4.1.2Storage of hazardous substances
No activity which includes storage of on-site hazardous substances shall be permitted unless a risk management and prevention plan has been approved by the municipality.
4.1.3Site development plan
The municipality may require a site development plan to be submitted to its satisfaction in terms of paragraph 12.6 for consideration and approval, provided that the municipality may require amendments to the site development plan to address reasonable concerns relating to access, parking, architectural form, urban design, landscaping, engineering services or similar matters.
4.1.4Industrial hive
The following land use provisions shall apply to an industrial hive:
(a)Design principles
(i)The principles which are reflected in the definition of Industrial Hive shall be closely followed and implemented;
(ii)Special attention shall be given to aesthetics, architectural co-ordination, urban design and landscaping.
(b)Site development plan
A site development plan of the proposed industrial hive shall be submitted at the satisfaction of the municipality in terms of paragraph 12.6 for consideration and approval.
(c)Parking and access
Parking and access shall be provided in accordance with paragraph 13.1.
(d)Mix of retail and industrial development
(i)The municipality may impose conditions specifying limits on the mix of retail and manufacturing activities;
(ii)In the absence of conditions referred to in (i), not more than 50% of the total floor space allocated to retail activities in an industrial hive may be used for shops or associated uses.
4.1.5Service stations
The land use provisions that apply to service stations in business zone shall apply to a service station in this zone.Industrial Zone 2: General industry (IND2)Colour notation: Purple.Objective:The objective of this zone is to accommodate all forms of industry,except noxious trades and risk activities, in order to promote the manufacturing sector of the economy. Allowance is made for non-industrial activities, but these should not compromise the general use of the area zoned for industry. It is accepted that the intensive nature of the industrial activity or the scale of the operation could generate some negative impact on adjacent land.
4.2Use of land:The following use restrictions apply to land in this zone:
(a)Primary uses: industry, service trade, warehouse, transport usage, car wash, restaurant, public parking, industrial hive, service station, public garage, transmission tower, rooftop base station.
(b)Consent uses: shop, bottle store, place of instruction, place of worship, place of assembly, adult entertainment enterprise, funeral parlour, waste disposal site, scrap yard, recycling plant.
(c) Additional use rights:
The occupant of an industry or service trade may sell goods which have been completely or partially manufactured on the land unit, and other such goods as the municipality may permit, provided that:
(i)the total floor space devoted to the sale of goods shall not exceed 10% of the total floor space of all the buildings on the land unit, and
(ii)such other goods that are offered for sale but that have not been manufactured on the land unit, are connected with the goods that are manufactured or partially manufactured on the land unit.
4.2.1Land use provisions:The following land use provisions apply (service stations and industrial hives are not included):
(a)Floor factor
The floor factor on the land unit shall not exceed 2.0.
(b)Coverage
The maximum coverage is 75%.
(c)Height
(i)No height restriction applies to an industry, service trade, warehouse or transport usage;
(ii)Other buildings shall not exceed 21m in height measured from a point halfway on the grade-line, provided that where a greater height is shown to be important for the function of a building, the municipality may grant a departure for such greater height.
(d)Street building line
The street building line is 5m subject to paragraph 12.1.
(e)Side building lines
(i)Where an external wall is constructed of brick, cement brick or concrete, and there are no openings in such external walls, and the land unit abuts another industrially-zoned land unit, a zero building line is permitted;
(ii)Where the land unit abuts a zone that is not an industrial zone, a 3m side building line or the more restrictive building line as applicable in the other specific zone, whichever is the larger, shall apply;
(iii)In all other cases a 3m side building line shall apply.
(f)Rear building lines
(i)No building shall be erected closer than 3m to the rear boundary of a land unit, subject to paragraph 12.1;
(ii)In cases where a building extends to both side boundaries of the land unit, and there is no other means of obtaining access to the rear of the land unit, other than through the building, at least one opening in the external wall of the building shall be provided to the rear boundary, and the municipality may require that such opening shall be protected by automatic fire shutters at the satisfaction of the municipality.
(g)Boundary walls
Where a land unit has a common boundary with another land unit that is not zoned for industrial purposes, the municipality may require a 1,8m high wall to be erected along the boundary to its satisfaction.
(h)Parking and access
Parking shall be provided in accordance with the following table:The number of parking bays to be provided on the premises, shall be in relation to the total floor area of the building and the total number of employees on the premises or a part thereof:
Parking bays in relation to floor area of the building
1 Parking bay for every 100m² floor area or part thereof up to 1 500m²,and
1 Parking bay for every 200m2 floor area or part thereof above 1 500m²
25% of the abovementioned parking bays shall be set aside for use byvisitors and must be indicated as such by means of road signs.
Parking bays in relation to the number of employees on thepremises
Up to 25 employees1 parking bay for every 4 personsor part thereof
Thereafter, for the next 25Employees1 parking bay for every 5 personsor part thereof
Thereafter, for the next 50Employees1 parking bay for every 10 personsor part thereof
Thereafter, for any further numberof employees1 parking bay for every 25 personsor part thereof
As an alternative for the stated parking requirement, the owner may, with the consent of the municipality, if the municipality is of the opinion that it is desirable or practical from a planning point of view to provide the required parking bays on the site, acquire the prescribed area of land for the relevant parking facilities on nearby premises in a position approved by the municipality, provided that he registers a notarial deed against such land to the effect that the municipality and the public shall have free access thereto for the purpose of parking, and that the owner is obliged to level this land, to provide it with a surface and to maintain it at the satisfaction of the municipality. The cost of registration of the notarial deed shall be borne by the owner. These conditions may only be amended with special approval by the municipality.
(i)Loading zones
Loading bays shall be provided in accordance with the following table:
Total floor space of building (tonearest m²)Required loading and off-loadingarea
0–2 500m²1 loading bay
2 501–5 000m²2 loading bays
5 001–10 000m²3 loading bays
Every additional 10 000m² orportion thereof1 additional loading bay
Such a loading bay shall measure at least 7m x 4.5m and shall have a vehicle exit to the street (which shall be at the satisfaction of the municipality and not less than 5m wide, and if it passes through a building, not less than 3m high).
(j)Screening
The municipality may require any part of a land unit which is used for storage or the loading of goods, to be enclosed with a suitable brick or concrete screen wall to the municipality’s satisfaction.
4.2.2Storage of hazardous substances
No activity which includes storage of on-site hazardous substances shall be permitted unless a risk management and prevention plan has been approved by the municipality.
4.2.3Site development plan
The municipality may require a site development plan to be submitted to its satisfaction in terms of paragraph 12.6 for consideration and approval, provided that the municipality may require amendments to the site development plan to address reasonable concerns relating to access, parking, architectural form, urban design, landscaping, engineering services or similar matters.
4.2.4Industrial hive
The same land use provisions which apply to an industrial hive in an industrial zone 1 shall apply to an industrial hive in this zone.
4.2.5Service station
The same land use provisions which apply to a service station in business zone 3 shall apply to a service station in this zone.
4.2.6Scrap yard
Premises or a portion of premises used as a scrap yard, must be fenced or screened entirely or in relation to that portion of the premises used as a scrap yard, as the case may be, with a suitable brick or concrete wall at least 1,8m high, measured from the natural height of the land abutting such fence.Industrial Zone 3: Risk Industry (IND3)Colour notation: Purple with black cross hatching.Objective:The objective of this zone is to provide for those industries which are noxious in terms of smell, product, waste or other objectionable consequence of their operation, or which carry a high risk in the event of fire or accident. While other uses are permitted with consent, the municipality must ensure that there is sufficient capacity for noxious trade in the limited areas suitable for this zone. Risk industry should not be located close to residential areas.
4.3 Use of land:The following use restrictions apply to land in this zone:
(a)Primary uses: Noxious trade, risk activity, transmission tower,
rooftop base station.
(b)Consent uses: Industry, service trade, warehouse, scrap yard, transport usage, shop, service station, waste disposal site, crematorium, public parking, abattoir, recycling plant.
(c)Additional use rights:
The occupant of a risk industry may sell goods which have been completely or partially manufactured on the land unit, and such other goods as the municipality may permit, provided that:
(i)the total floor space devoted to the sale of goods shall not exceed ten percent (10%) of the total floor space of all the buildings on the land unit, and
(ii)such other goods that are offered for sale but that have not been manufactured on the land unit, are connected with the goods that are manufactured or partially completed on the land unit.
4.3.1Environmental impact::
(a)No land shall be utilised for industrial zone 3: risk industry, unless an environmental impact assessment has been undertaken, and the municipality is satisfied with the conclusions of the environmental impact assessment;
(b)No activity, which includes storage of on-site hazardous substances, shall be permitted unless a risk management and prevention plan has been approved by the municipality.
4.3.2Land use provisions:
The following land use provisions apply:
(a)Floor factor
The floor factor on the land unit shall not exceed 2.0.
(b)Coverage
The maximum coverage is 75%.
(c)Height
(i)No height restriction applies to a noxious trade, risk activity or industry;
(ii)Other buildings shall not exceed 10m in height measured from a point half-way on the grade line, provided that where a greater height is shown to be important for the function of the building, the municipality may grant permission for such greater height.
(d)Building lines
(i)The street building line is 5m;
(ii)The side and rear building lines are 3m.
(e)Parking and access
Parking shall be provided in accordance with the following table as well as paragraph 13.1:The number of parking bays to be provided on the premises, shall bare relation to the total floor area of the building and the total number of employees on the premises or a portion thereof:
Parking bays in relation to floor area of the building
1 Parking bay for every 100m² floor area of portion thereof up to 1500m², and
1 Parking bay for every 200m² floor area or portion thereof above 1500m²
25% of the abovementioned parking bays shall be set aside for use byvisitors and must be indicated as such by means of road signs
Parking bays in relation to the number of employees on thepremises
Up to 25 employees1 parking bay for every 4 personsor part thereof
Thereafter, for the next 25employees1 parking bay for every 5 personsor part thereof
Thereafter, for the next 50employees1 parking bay for every 10 personsor part thereof
Thereafter, for any further numberof employees1 parking bay for every 25 personsor part thereof
As an alternative for the stated parking requirement, the owner may, with the consent of the municipality, if the municipality is of the opinion that it is not desirable or practical from a planning point of view to provide the required parking bays on the site, acquire the prescribed area of land for the relevant parking facilities on nearby premises in a position approved by the municipality, provided that he registers a notarial deed for such land to the effect that the municipality and the public shall have free access thereto for the purpose of parking, and that the owner is obliged to level this land, to provide it with a surface and to maintain it at the satisfaction of the municipality. The cost of registration of the notarial deed shall be borne by the owner. These conditions may only be amended with special approval by the municipality.
(f)Loading bays
Loading bays shall be provided in accordance with the following table as well as paragraph 13.1:
Total floor space of building (tonearest m²)Required loading and off-loadingarea
0–2 500m²1 loading bay
2 501–5 000m²2 loading bays
5 001–10 000m²3 loading bays
Every additional 10 000m² orportion thereof1 additional loading bay
Such a loading bay shall measure at least 7m x 4.5m and shall have a vehicle exit to the street (which shall be at the satisfaction of the municipality and not less than 5m wide, and if it passes through a building, not less than 3m high).
(g)Screening
The municipality may require any part of a land unit which is used for storage or the loading of goods, to be enclosed with a suitable brick or concrete screen wall to the municipality’s satisfaction.
(h)Boundary walls
Where a land unit has a common boundary with another land unit that is not zoned for industrial purposes, the municipality may require a 1,8m high wall to be erected along the boundary to its satisfaction.
4.3.3Site development plan
The municipality may require a site development plan to be submitted to its satisfaction in terms of paragraph 12.6 for consideration and approval, provided that the municipality may require amendments to the site development plan to address reasonable concerns relating to access, parking, architectural form, urban design, landscaping, engineering services or similar matters.
4.3.4Service stations
The same land use provisions that apply to service stations in the business zone 3, shall apply to a service station in this zone.
4.3.5Scrap yard
Premises or a portion of premises used as a scrapyard, must be fenced or screened entirely or in relation to that portion of the premises used as a scrap yard, as the case may be, with a suitable brick or concrete wall of at least 1,8m high, measured from the natural height of the land abutting such fence.Industrial Zone 4: Extractive Industry (IND4)Colour notation: White with purple outline.Objective:The objective of this zone is to provide for the use of land for the extraction of minerals and other raw materials as well as to allow associated business operations to a limited extent.
4.4Use of land:The following use restrictions apply to land in this zone:
(a) Primary use: mining, transmission tower, rooftop base station.
(b)Consent uses: industry, risk activity.
4.4.1Land use provisions:
The following land use provisions apply:
(a)Application requirements
(i)The owner shall comply with national and provincial statutory requirements applicable to mining, including but not limited to:• the permits and licenses necessary in accordance with the Mineral and Petroleum Development Act, 2002 (Act 28 of 2002);• the authorizations or exemptions necessary in accordance with NEMA;
(ii)Any application to rezone a land unit to accommodate industrial zone 4 shall contain an explanation of the measures that will be implemented to address safety and environmental concerns, including but not limited to:• control of drainage, sedimentation and erosion;• preservation of natural vegetation and wildlife habitats;• protection of surface and subsurface water;• preservation of topsoil;• provision for restoration and the re-use of the site;• provision for noise and visual buffering;• accommodation of heavy traffic and vehicles on roadways, and• provision for a phased programme of commitments and liabilities commensurate with the restoration requirements;
(iii)In the assessment of an application to conduct industrial activities in this zone, particular consideration shall be given to the potential nuisance or risk such activity may pose to the surrounding area and persons or community.
(b)Site development plan
A site development plan shall be submitted at the satisfaction of the municipality in terms of paragraph 12.6 for consideration and approval.
(c)Operational requirements
The following provisions shall apply during the operation of an extractive industry:
(i)The owner or operator of an extractive industry shall:• notify the municipality of any seasonal, temporary or permanent shutdown occurrences;• not increase drainage and water runoff to any adjacent land unit or watercourse, and• provide adequate on-site dust control at the satisfaction of the municipality.
(ii)Haulage routes for vehicles and equipment travelling to and from the site shall be subject to the approval of the municipality;
(iii)The municipality may impose such other conditions and land use provisions, as it deems necessary.

Chapter 5
COMMUNITY ZONES

General Policy Statement:The following general policies shall apply in the community zones except where the policy and principles are subordinate to an approved spatial development framework or spatial development plan:(i)Community zones are designed to accommodate a range of social uses directed at serving local community needs such as educational, religious and health facilities. Provision is also made for higher order facilities that serve the broader community;(ii)The diversity of development requirements for community uses is recognized and land use provisions, including the use of site development plans, are directed at mitigating negative impacts on surrounding areas;(iii)Nevertheless community buildings constitute important social and urban design focal points, and prominent architectural forms should be encouraged.Community Zone 1: Education (CZ1)Colour notation: Light blue with black letter E.Objective:The objective of this zone is to provide for the entire spectrum of educational facilities, together with controlled provision for other reconcilable community uses.
5.1.Use of land:The following use restrictions apply to land in this zone:
(a)Primary use: place of instruction.
(b)Consent uses: conference facility, place of assembly, place of worship, institution, transmission tower, rooftop base station.
(c)Additional use rights: A land unit in this zone may occasionally be used for social functions provided:
(i)the social functions are incidental and related to the activities permitted in this zone, and
(ii)the social functions do not, in the municipality’s opinion, generate excessive or prolonged disturbance such as noise.
5.1.1Land use provisions:The following land use provisions apply:
(a)Floor factor
The floor factor may not exceed 1.0.
(b)Coverage
The maximum coverage is 60%.
(c)Height
No building may exceed a height of 3 storey’s.
(d)Street building line
The street building line is 10m.
(e)Side and rear building line
The side and rear building lines are 5m.
(f)Parking and access
One parking bay per class room shall be provided together with one bus parking bay per 20 learners. One parking bay per 4 seats applicable for other uses.
(g)Site development plan
The municipality may require a site development plan to be submitted in terms of paragraph 12.6 for consideration and approval, provided that the municipality may require amendments to the site development plan to address reasonable concerns relating to access, parking, architectural form, urban design, landscaping, engineering services or similar matters.Community Zone 2: Worship (CZ2)Colour notation: Grey with black cross.Objective:The objective of this zone is to provide for places where communities can congregate and worship according to the custom of their specific faith or religion.
5.2Use of land:The following use restrictions apply to land in this zone:
(a)Primary uses: place of worship, religious leader’s residence,
transmission tower, rooftop base station.
(b)Consent uses: place of assembly, place of instruction, cemetery,
wall of remembrance, institution.
(c)Additional use rights: A land unit in this zone may occasionally be used for social functions provided that:
(i)the social functions are incidental and related to the activities permitted in this zone, and
(ii)the social functions do not, in the municipality’s opinion, generate excessive or prolonged disturbance such as noise.
5.2.1Land use provisions:
The following land use provisions apply:
(a)Floor factor
The floor factor may not exceed 1,0.
(b)Coverage
The maximum coverage is 60%.
(c)Height
No building may exceed a height of 2 storey’s, except for a bell tower, steeple, minaret or similar architectural feature designed to accentuate the significance of the building as a place of worship.
(d)Street building line
The street building line is 10m.
(e)Side and rear building lines
The side and rear building lines are 5m.
(f)Parking and access
One parking bay per 4 seats shall be provided.
(g)Site development plan
The municipality may require a site development plan to be submitted to its satisfaction in terms of paragraph 12.6 for consideration and approval, provided that the municipality may require amendments to the site development plan to address reasonable concerns relating to access, parking, architectural form, urban design, landscaping, engineering services or similar matters.Community Zone 3: Institution (CZ3)Colour notation: Grey with black hatching.Objective:The objective of this zone is to provide health facilities that are located conveniently in relation to the local and general community, but will restrict negative impact on adjoining areas.
5.3Use of land:The following use restrictions apply to land in this zone:
(a)Primary uses: institution.
(b)Consent uses: place of assembly, place of instruction, transmission tower, rooftop base station.
5.3.1Land use provisions:The following land use provisions apply:
(a)Floor factor
The floor factor may not exceed 1.0.
(b)Coverage
The maximum coverage is 60%.
(c) Height
No building may exceed a total height of 21m.
(d)Street building line
The street building line is 10m.
(e)Side and rear building lines
The side and rear building lines are 5m.
(f)Parking and access
One parking bay per bed shall be provided.
(g)Site development plan
The municipality may require a site development plan to be submitted to its satisfaction in terms of paragraph 12.6 for consideration and approval, provided that the municipality may require amendments to the site development plan to address reasonable concerns relating to access, parking, architectural form, urban design, landscaping, engineering services or similar matters.

Chapter 6
AUTHORITY ZONE

General Policy Statement:The following general policies and principles shall apply in the authority zone unless these policies and principles are superseded by an approved spatial development framework or a spatial development plan:(i)Government sites, whether national, provincial or municipal, shall be zoned according to their use, not ownership;(ii)Notwithstanding the above, government activities which cannot be classified into other zones, should be included in this zone;(iii)Certain government or parastatal activities, such as prisons and military bases, may have impacts on adjacent areas that cannot be prevented but should be mitigated.Authority Zone 1: Government (AZ1)Colour notation: Red.Objective:The objective of this zone is to reserve land for uses normally undertaken by central, provincial and municipal government agencies, and which do not fall into another zoning category.
6.1.Use of land:The following use restrictions apply to land in this zone:
(a)Primary use: authority usage, transmission tower, rooftop base station.
(b)Consent uses: any use determined by the municipality.
6.1.1Land use provisions:The following land use provisions apply:
(a)No structure shall be erected nor land used in this zone, unless it is considered by the municipality to be consistent with "authority usage", or a use associated with authority usage;
(b)The municipality shall determine the land use provisions applicable to land units in this zone.

Chapter 7
TRANSPORT ZONES

General Policy Statement:The following general policies shall apply to the transport zones:(i)Transport zones are designed to facilitate efficient operation of the various transport systems. There is a close relationship between transportation and development, and appropriate development can help to promote public transport. Provision is made for controlled mixed use development in certain transport zones, provided that the operation of the transport system is not compromised;(ii)Ideally, transport systems run along defined corridors, and there are opportunities for air rights and underground rights, whereby appropriate development can be constructed at a different level to the transport system without the operation of the system being compromised.Transport Zone 1: Transport Usage (TZ1)Colour notation: Light brown with black hatching.Objective:The objective of this zone is to reserve land for transportation systems, excluding private roads and public streets, but including all other transport undertakings serving the community, such as airports, airfields, heliports, harbours, railway lines, bus depots, taxi ranks, cable car stations, and modal interchanges.
7.1.Use of land:The following use restrictions apply to land in this zone:
(a)Primary uses: transport usage, public parking, transmission tower, rooftop base station.
(b)Consent uses: shop, offices, hotel, restaurant, bottle store, warehouse, industry, service trade, service station, place of assembly, place of entertainment, institution.
7.1.1Land use provisions:The following land use provisions apply:
(a)Floor factor
The floor factor shall not exceed 2.0.
(b)Coverage
The maximum coverage is 80%.
(c)Height
The municipality may determine a height restriction for specific land units in this zone.
(d)Building lines
(i)The street building line is zero, except where the street boundary abuts a declared road, in which case a 5m street building line may be required;
(ii)The side and rear building lines are nil, except where the boundary abuts a zone which is not a transport zone, in which case the side and rear building lines are 3m.
(e)Parking and access
Parking and access shall be provided on the land unit as required by the municipality.
(f)Air rights and underground rights
The municipality may grant permission for air or underground rights above or below land in this zone, provided that:
(i)The municipality is satisfied that the structural components, clearance and operational characteristics are sufficient to ensure safe and efficient operation of the transport usage, and
(ii)an agreement defining the extent of rights, ownership and maintenance obligations relating to such building or premises, is concluded between the parties concerned and is approved by the municipality.
Transport Zone 2: Roads (TZ2)Colour notation: Light brown.Objective:The objective of this zone is to provide for public streets and private roads, whether constructed or still to be constructed.
7.2Use of land:The following use restrictions apply to land in this zone:
(a)Primary uses: public street, private road, public parking, private parking.
(b)Consent uses: any other uses determined by the municipality subject to the following:
(i)such uses do not, in the municipality’s opinion, compromise the movement of vehicles or pedestrians in the vicinity;
(ii)such land should be rezoned if the use constitutes a significant and permanent change from the primary use, and if this Zoning Scheme provide a more suitable alternative zone, and
(iii)any public street, or any portion of land indicated as a public street on an approved plan that has not lapsed, shall be deemed to be zoned as transport zone 2: roads.
7.2.1Land use provisions:The following land use provisions apply:
(a)Street hawkers
Use of the road reserve in a public street for business by street vendors, peddlers or hawkers, is permitted subject to compliance with any applicable municipality by-laws relating to street vendors, peddlers or hawkers.
(b)Construction and deposit of materials
No person shall:
(i)construct a private crossing, bridge or culvert onto or across a public street;
(ii)construct or lay a sidewalk on a public street;
(iii)construct a veranda, a stoep, a wall, steps or any other projection in or over a public street, or
(iv)deposit or leave any goods, articles, building materials or waste in a public street other than for a reasonable period during the course of loading, off-loading or removal thereof.
(c)Air rights and underground rights
The municipality may grant permission for air or underground rights above or below land zoned for transport usage as consent uses, provided that:
(i)the municipality is satisfied that structural components, clearance and operational characteristics are sufficient to ensure safe and efficient operation of the transport usage, and
(ii)an agreement defining the extent of rights, ownership and maintenance obligations relating to such building or premises is concluded between the parties concerned and is approved by the municipality.
(d)Proposed public street, street widening and street closure
Any reference on the zoning map to proposed public streets, proposed street widening or proposed street closure shall be subject to paragraph 12.7.Transport Zone 3: Parking (TZ3)Colour notation: Light brown with black letter P.Objective:The objective of this zone is to provide for parking of operable motor vehicles on a temporary basis in order to meet a parking demand, with or without a fee. Such parking may be provided in buildings as well as open parking lots, and may be privately or publicly owned.
7.3Use of land:The following use restrictions apply to land in this zone:
(a)Primary uses: public parking, private parking, transmission tower, rooftop base station.
(b)Consent uses: shop, business premises, service station.
7.3.1Land use provisions:The municipality shall determine the land use provisions applicable to land units in this zone, in accordance with the objective of this zone.

Chapter 8
CONSERVATION AND OPEN SPACE ZONES

General Policy Statement:The following general policies and principles shall apply in conservation and open space zones unless these policies and principles are superseded by an approved spatial development framework or spatial development plan:(i)Provision is made for different types of open space, depending on the different functions of those open spaces. Public open space has a particularly important status because of its contribution to the general public interest and the difficulty of replacing public open space once lost. For these reasons, public open space needs to be differentiated from private open space, and the status of public open space should not be changed without very careful consideration;(ii)Certain open spaces have special significance as nature areas, whether public or private, and need to be clearly identified in terms of the zoning map. These areas may also be subject to other requirements in terms of environmental legislation regarding their use;(iii)Cemeteries have sometimes been included in the public open space zone, but they have a different function and characteristics, and should rather be zoned separately. A zone is created for this purpose in this Zoning Scheme.Open Space Zone 1: Public open space (OS1)Colour notation: Dark green.Objective:The objective of this zone is to provide for active and passive recreational areas on public land, in order to promote recreation, enhance the aesthetic appearance of an area, maintain fauna and flora and protect areas of undeveloped landscapes, including forest areas, hills, swamps and the coast line.
8.1.Use of land:The following use restrictions apply to land in this zone:
(a)Primary uses: public open space, conservation usage, transmission tower, rooftop base station.
(b)Consent uses: cemetery, wall of remembrance, camping site, boat launching facility, racing track.
8.1.1Land use provisions:The municipality shall determine the land use provisions applicable to land units in this zone, in accordance with the objective of this zone.Open Space Zone 2: Public Open Space (OS2)Colour notation: Light green.Objective:The objective of this zone is to provide for active and passive recreational areas on private land, in order to promote recreation, enhance the aesthetic appearance of an area, maintain fauna and flora and protect areas of undeveloped landscapes, including forest areas, hills, wetlands and the coast line.
8.2.Use of land:The following use restrictions apply to land in this zone:
(a)Primary uses: private open space, conservation usage,
transmission tower, rooftop base station.
(b)Consent uses: cemetery, wall of remembrance, camping site, 4x4 route, boat launching facility, racing track.
8.2.1Land use provisions:The municipality shall determine the land use provisions applicable to land units in this zone and in accordance with the objective of this zone.Open Space Zone 3: Nature reserve (OS3)Colour notation: Light green with black hatching.Objective:The objective of open space zone 3: nature reserve is to provide for nature reserves owned publicly or privately, which have been proclaimed as such in terms of any law.
8.3Use of land:The following use restrictions apply to land in this zone:
(a)Primary uses: nature reserve, conservation usage.
(b)Consent uses: tourist facility, holiday accommodation, 4x4 route, transmission tower, rooftop base station, boat launching facility.
8.3.1Land use provisions:The following land use provisions apply:
(a)An environmental management plan shall be prepared at the satisfaction of the municipality, and
(b)The municipality shall determine the land use provisions for the land unit, based on the aims of this zone and the particular circumstances of the land, and in accordance with an approved environmental management plan.
Open Spae Zone 4: Cemetery (OS4)Colour notation: Light green with black letter C.Objective:The objective of this zone is to provide for land that is reserved for the burial of the dead, and associated activities.
8.4Use of land:The following use restrictions apply to land in this zone:
(a)Primary uses: cemetery, wall of remembrance, private open space, conservation usage.
(b)Consent uses: crematorium, place of worship, funeral parlour.
8.4.1 Land use provisions:The following land use provisions apply:
(a)The municipality shall determine the land use provisions applicable to land units in this zone, in accordance with the objective of this zone;
(b)Parking shall be provided on the land unit in accordance with paragraph 13.1.

Chapter 9
RESORT ZONES

General Policy Statement:The following general policies and principles shall apply in the resort zones and the objective of this zone is to promote tourist and holiday facilities in areas with special environmental or recreational attributes, and to encourage access to these facilities by the general public. At the same time care is needed to minimise potential negative impacts of development on fragile environments. The guiding principle should be that a resort must not detract from the amenity that attracted the holiday facilities in the first place, nor should it cause a public nuisance for other people living and working in the vicinity. This zone should only be used in exceptional cases and is normally applied to tourist developments outside established built up areas.Resort zone: Resort (RE)Colour notation: Pink.Objective:The objective of this zone is to promote tourist and holiday facilities in areas with special environmental or recreational attributes, and to encourage access to these facilities by the general public. At the same time care is necessary to minimize potential negative impacts of development on fragile environments.The guiding principle should be that a resort must not detract from the pleasantness that attracted the holiday facilities in the first place, nor should it cause a public nuisance for other people living and working in the vicinity.
9.1. Use of land:The following use restrictions apply to land in this zone:
(a)Primary uses: holiday accommodation, conservation usage, private open space, lodge.
(b)Consent uses: tourist facility, resort shop, conference facility, transmission tower, rooftop base station, boat launching facility.
9.1.1Land use provisions:The following land use provisions apply:
(a)The municipality shall stipulate development parameters with regard to density, height, coverage, layout, building design, landscaping, parking, access and the use of buildings or land;
(b)A site development plan shall be submitted at the satisfaction of the municipality in terms of paragraph 12.6;
(c)A landscape plan and environmental management plan shall be prepared to the municipality’s satisfaction;
(d)The municipality may require that a qualified landscape architect forms part of the design team that prepares the site development plan, and to supervise implementation of the landscape proposals;
(e)The municipality may require an environmental management plan to form part of any civil and building contracts for development on the land.
Leisure Accommodation Zone: Liesure accommodation (LA)Colour notation: Pink with black cross hatching.Objective:The objective of this zone is to allow small-scale tourist and holiday facilities in areas with special environmental or recreational attributes.
9.3Use of land:The following use restrictions apply to land in this zone:
(a)Primary uses: holiday accommodation, holiday housing, conservation usage, private open space.
(b)Consent uses: lodge, tourist facility, resort shop, transmission tower, rooftop base station, boat launching facility.
9.3.1 Land use provisions:The following land use provisions apply:
(a)The municipality shall stipulate development parameters with regard to density, height, coverage, layout, building design, landscaping, parking, access and the use of buildings or land;
(b)A site development plan shall be submitted at the satisfaction of the municipality in terms of paragraph 12.6;
(c)A landscape plan and environmental management plan shall be prepared to the municipality’s satisfaction;
(d)The municipality may require that a qualified landscape architect forms part of the design team that prepares the site development plan, to supervise implementation of the landscape proposals, and
(e)The municipality may require an environmental contract to form part of any civil and building contracts for development on the land.

Chapter 10
AGRICULTURE AND RURAL ZONES

General Policy Statement:The following general policies shall apply in the agricultural zones:(i)Agricultural land must generally be protected against development that renders the land less suitable for agriculture, or detracts from its aesthetic or cultural value. Undesirable subdivision of farms must not be permitted and economically viable units must be maintained. Subdivision and rezoning of agricultural land should only be considered when this will help to promote sustainable development;(ii)Bona fide agricultural activities should not be subject to unreasonable limitations, because the economic viability of the agricultural sector is important. Complementary activities to conventional agriculture will also assist with the viability of the sector. To this end compatible uses, listed as consent uses, can be considered to enhance economic viability of farms;(iii)Aside from sustaining a valuable economic resource, preservation of agricultural land can help to promote stability of the urban edge, conserve wetlands and other naturally sensitive areas, as well as maintain rural characteristics that are valued by the community.Agricultural zone 1: Agriculture (AGR1)Colour notation: Dark green with thick black hatching.Objective:The objective of this zone is to promote and protect agriculture on large farms as an important economic, environmental and cultural resource. Limited provision is made for non-agricultural uses to provide rural communities in more remote areas with the opportunity to increase the economic potential of their land, provided that these uses do not present a significant negative impact on the primary agricultural resource.
10.1.Use of land:The following use restrictions apply to land in this zone:
(a)Primary use: agriculture, farm stall.
(b)Consent uses: additional dwelling unit, guest house, tourist facility, farm shop, aquaculture, intensive stock farming, horticulture, nursery, riding school, service trade, mining, 4x4 route, commercial pet kennel, bed and breakfast establishment, conservation usage, agri-village, composting, racing track, boat launching facility, conference facility, exhibition centre, transmission tower, rooftop base station, renewable energy structure.
10.1.1Land use provisions:The following land use provisions apply:
(a)Floor space:
No farm shop may exceed a floor space of 500m², provided that the municipality may relax this requirement if the municipality is of the opinion that this would be necessary due to the extent or nature of products offered.
(b)Building line:
The building line restriction is 30m in respect of all boundaries.
(c)Parking:
Parking and access shall be provided in accordance with 13.1.
(d)Height:
(i)Dwelling houses shall not exceed a height of 2 storey’s, provided that, where the slope of the grade line is greater than 1 in 5, the owner may elect to have height regulated in accordance with (ii) below;
(ii)Where the height is regulated in terms of this subparagraph, no point on a building shall exceed a vertical distance above a point half-way on the grade line, of 6m in the case of a flat roofed building, or 8m in the case of a pitched roof building, provided that if it is a pitched roof building, only the roof structure may exceed a height of 6m;
(iii)Agricultural buildings other than dwelling houses shall not exceed 12m in height above a point half-way on the grade line to the ridge of the roof, provided that where the municipality is satisfied that a greater height is necessary for the functioning of the building, it may permit such greater height.
10.1.2Site development planThe municipality may require that a site development plan be submitted to its satisfaction in terms of paragraph 12.6 in respect of consent uses.
10.1.3Bed and breakfast establishmentThe land use provisions applicable to a bed and breakfast establishment in the residential zone 1 shall also apply in this zone.
10.1.4Home occupationThe municipality may grant its consent for a home occupation in this zone provided that:
(a)no consent application shall be considered unless prior written consent from the relevant owner has been obtained, and
(b)if the municipality grants consent, such consent will be subject to the same conditions applicable in single residential zones 1 and 2 relating to a dwelling house or dwelling unit which is used for the purpose of home occupation, and the municipality may also impose additional conditions which may be less restrictive or more restrictive.
10.1.5Renewable energy structureSpecial provisions applying to a Renewable Energy Structure:
(a)Definitions applicable to these measures ;
(i)"Appurtenant structure" means any structure or accessory necessary for, or directly associated with generation of renewable energy;
(ii)"Site"means the land utilised for Renewable energy structures, regardless of cadastral boundaries, and inclusive of Renewable energy structures.
(b)Land use restrictions
(i) Height:• A maximum height of 200m for a wind turbine, measured from the mean ground level of the footprint of each structure to the highest point of the blade;• The height of a structure for solar generation facilities will be technology-dependent;• The height of buildings is restricted to a maximum of 8.5m and is measured from the mean ground level of the footprint of the building to the highest point of the roof.
(ii) Setback:In the case of a wind turbine, a distance equal to 1,5 times the overall blade tip height of the turbine, measured from:• the nearest residential, commercial or critical agricultural structures such as animal housing, outbuildings, store rooms, but excluding structures such as water troughs, feed dispensers and windmills;• the cadastral boundary of the land unit;• any public road or private or public right of way; and• any electrical infrastructure.This setback requirement does not apply to a cadastral boundary in the case of a renewable energy site which straddles such cadastral boundary. Setbacks are required for safety reasons and may not be deviated from.
(c)Additional requirements
(i)Site Development Plan (SDP):• As part of the application or as a condition of approval, a Site Development Plan (SDP) must be submitted to the competent authority. The site must be surveyed and the exact delineation of the construction footprint must be shown in the SDP;• To the extent necessary, any relevant measures contained in this zoning scheme must be incorporated into a Site Development Plan.
(ii)Initial measure in the event of failure:As a condition of consent use approval, the owner must make financial provision, to the satisfaction of the competent authority, for protection against failure at any time after site construction has started for the rehabilitation or management of negative environmental impact of decommissioning or of abandonment in the case of the owner not being financially able to fulfil any obligations in this regard.If the owner fails as contemplated above, the competent authority may, after written notice to the owner, use all or part of the financial provision to rehabilitate or manage negative environmental impact in question or to remove the facility.
(iii)Visual and environmental impact:Visual and environmental impacts must be taken into account for height determination and in general, to the satisfaction of the competent authority.
(iv)Land clearing, soil erosion and habitat impact:• The clearing of natural vegetation is limited to that which is necessary for the construction, operation and maintenance of the Renewable energy structure as regulated by the applicable Environmental Legislation;• Wind turbines, solar structures, access roads and other infrastructure must be located to minimise damage to natural vegetation, water courses and wetlands;• All land cleared and which does not form part of the footprint of a Renewable energy structure, must be rehabilitated according to a rehabilitation plan for the land concerned, approved by the competent authority;• Soil erosion may not take place, and the rehabilitation of any high risk erosion area, at the satisfaction of the competent authority, is essential;• The applicant must prove, to the satisfaction of the competent authority, that all impacts in respect of, and necessary distances which should be maintained from, wetlands, water bodies, threatened ecosystems, mountains, ridges, hills, coastal buffers, settlements, telecommunication towers, transmission towers and power lines, have been considered and accounted for;• The exact co-ordinates in the above regard must be provided to determine possible environmental impacts.
(v)Noise, Air Quality and Nuisance:The development must be compliant with regulations controlling pollution, including:• the National Environmental Management Act, 1998 (Act 107 of 1998);• provincial regulations in force; and• municipal by-laws.
(vi)Finishing and Colour:• A wind turbine structure must be treated with a neutral, non-reflective exterior colour designed to blend in with the surrounding natural environment, to the satisfaction of the competent authority;• A solar structure may not cause any adverse effects due to its reflective nature and must be designed and erected accordingly, as required by the competent authority.
(vii)Appurtenant Structures:• All appurtenant structures to a Renewable energy structure prescribed by the competent authority, concerning bulk, height, yard sizes, building lines, open space, parking and building coverage requirements, must be subject to regulations;• Appurtenant structures, including, but not limited to, equipment shelters, storage facilities, transformers and sub-stations, must be architecturally compatible with the receiving environment as required by the competent authority, and contained within a Renewable energy structure Site Development Plan as part of the approval;• Appurtenant structures shall only be used for the storage of equipment or other uses directly related to the operation of the particular facility;• Appurtenant structures must be screened from view by indigenous vegetation and/or located in an underground vault, or be joined and clustered to avoid adverse visual impacts.
(viii)Lighting:• A Renewable energy structure or any part thereof may only be lit for safety and operational purposes and the lighting must be appropriately screened from abutting land units.• The lighting requirements of the South African Civil Aviation Authority in accordance with aeroplane safety standards must be adhered to.
(ix)Signage and Advertising:Signs on Renewable energy structures must comply with national and local signage regulations and must be limited to:• those necessary to identify the operator;• provide 24 hours emergency contact numbers; and• warning of any danger.No commercial advertising, including in respect of the provider and operator, may be displayed on Renewable energy structures.
(x)Maintenance:The owner is responsible to maintain a Renewable energy structure in a good condition. Maintenance must include, but is not limited to:• painting;• structural repairs;• rehabilitation measures; and• the upkeep of security and safety measures.The owner is responsible for the cost of maintaining the facility and any access road, unless deemed as a public way, and for the cost of repairing any damage resulting from construction or operation.
(xi)Modification:Any modification, excluding inconsequential in situ technical improvements to a Renewable energy structure made after approval and which is not largely in accordance with the approval, requires authorisation from the competent authority within the parameters of this zoning scheme by means of:• departure;• amendment of conditions;• new consent use approval;• amendment of the Site Development Plan;• amendment of the building plan.
(xii)Decommissioning:• Any Renewable energy structure and associated infrastructure, including buildings, power lines, cables and roads which has reached the end of its productive life or has been abandoned must be removed;• When a Renewable energy structure is scheduled to be decommissioned or operations have been discontinued or it has been abandoned, the land owner must notify the competent authority within 30 days after the operation seized by by registered mail of the proposed or past date concerned, and of plans for removal;• The owner is responsible for the removal of the structure in all its parts, within 150 days after the date of discontinued operation or as agreed upon by the competent authority after submission of a plan for decommissioning. The competent authority, where justifiable in its opinion, may grant extension of time for removal of the structure. The land must then be rehabilitated, to the satisfaction of the competent authority, to the condition prescribed in the approved Environmental Management Plan and the approved decommissioning plan;• Decommissioning must include, inter alia:• the removal of all wind turbines, solar voltaic structures and appurtenant structures, including equipment, bases, foundations, security barriers and transmission lines;• disposal of all solid and hazardous waste in accordance with provincial and local waste disposal regulations; and• the stabilisation and re-vegetation of the site to minimise erosion;• The competent authority may, in order to minimise erosion and disruption to natural vegetation and habitats, grant approval to the owner not to remove landscaping or underground foundations, or other underground components which do not cause any pollution as contained in the decommissioning plan;• If the owner fails to remove the structure or parts thereof in accordance with the requirements of this zoning scheme within 150 days of abandonment or the date of decommissioning or an approved extension time, the competent authority may enter the property and remove the structure or parts thereof. All removal costs in such a case may be recovered from the owner.
(xiii)Abandonment:A Renewable energy structure shall be considered abandoned in the event of the structure failing to continuously operate for more than one year, or when part or all of the structure is confirmed as a hazard and no remedial action has been undertaken, unless the owner can prove otherwise.
Agricultural Zone 2: Agricultural industry (AGR2)Colour notation: Green with thick purple hatching.Objective:The objective of this zone is to make provision for the processing of agricultural products on farms or portions of farms where such processing may, in the municipality’s opinion, potentially impact negatively on the amenity of the surrounding area in terms of the size or intensity of the activity, but for reasons of efficiency these activities are best situated within an agricultural area, as opposed to an urban or industrial area. The use category "agricultural industry" has a different meaning to "agriculture" to protect the agricultural resource base and amenities of agricultural areas.
10.2Use of land:The following use restrictions apply to land in this zone:
(a)Primary use: agricultural industry, transmission tower, rooftop base station.
(b)Consent uses: dwelling house, tourist facility, farm stall, nursery, intensive stock farming, horticulture, composting.
10.2.1Token zoning
The municipality may approve rezoning of a portion of a land unit that is otherwise zoned, to agricultural zone 2, provided that the area affected by the agricultural zone 2 zoning is clearly identified on a survey diagram or other plan prepared by a suitably qualified person to the municipality’s satisfaction.
10.2.2Land use provisions:
The following land use provisions apply:
(a)Floor space:
The municipality may stipulate additional floor space limitations taking into account the character of the area and operational requirements of a particular agricultural industry.
(b) Coverage
The maximum coverage for all buildings on an area earmarked as a token zoning, or a land unit zoned, for agricultural zone 2, is 80 %.
(c)Building linesA building line restriction of 10m shall apply around agricultural industry improvements.
(d) Parking
(i)At least 1 parking bay per 200m2 of the total floor space shall be provided;
(ii)For the purposes of loading and off-loading goods from vehicles, at least two loading bays shall be provided for every 50m² or portion thereof, of the floor space used for the agricultural industry;
(iii)The municipality may impose additional parking and loading requirements to provide for the operational requirements of a particular agricultural industry.
(e)Height
The municipality may determine a height limitation in response to the operational requirements of a particular agricultural industry.
10.2.3Site development plan
The municipality may require a site development plan, to its satisfaction, and in line with paragraph 12.6 for consideration and approval, for all new development and extensions of existing development within this zone. Upon the rezoning of land to agricultural zone 2, the municipality may prescribe any special conditions in respect of permitted uses, parking and loading requirements, access, fencing and aesthetics so that the use will have the minimum possible influence on the environment.Agricultural Zone 3: Smallholdings (AGR3)Colour notation: Green with thick yellow hatching.Objective:The objective of this zone is to accommodate smaller agricultural land units which may be occupied as places of residence for people who seek a rural lifestyle. Such land units often occur adjacent to towns and villages.
10.3Use of land:The following use restrictions apply to land in this zone:
(a)Primary use: agriculture.
(b)Consent uses: additional dwelling unit, farm stall, bed and breakfast establishment, tourist facility, riding school, nursery, intensive stock farming, horticulture, commercial pet kennel, composting, food processing, home occupation, transmission tower, rooftop base station.
10.3.1Land use provisionsThe following land use provisions apply:
(a) Building lines
The building lines are 10m in respect of all boundaries.
(b)Parking
Parking and access shall be provided on the land unit in accordance with paragraph 13.1.
(c)Height
(i)No building may exceed a height of two storey’s, provided that where the slope of the grade-line is greater than 1 to 5, the owner may elect to have height regulated in accordance with (ii) hereunder;
(ii)Where the height is regulated in terms of this sub-paragraph, no point on a building shall exceed a vertical distance above a point half-way on the grade line, of 6m in the case of a flat roofed building, or 8m in the case of an inclined or pitched roof building, provided that if it is an inclined or pitched roof building, only the roof structure may exceed a height of 6m.
10.3.2Minimum subdivision size
No land unit zoned Agriculture zone 3 shall have an extent of:
(i)less than 2ha, if no minimum subdivision size is specified on the zoning map, or
(ii)less than the specified minimum size if the zoning map specifies a minimum subdivision size for a land unit in this zone.
10.3.3Site development plan
The municipality may require that a site development plan for a consent use be submitted to its satisfaction in terms of paragraph 12.6 for consideration and approval.

Chapter 11
ALTERNATIVE ZONES

General Policy Statement:The following general policies and principles shall apply to land in the alternative zones, except where the policies and principles are superseded by an approved spatial development framework or spatial development plan:(i)This chapter deals with three zones, named undetermined, special and sub divisional area. The undetermined zone enables the municipality to defer a decision regarding a specific land use and land use provisions until the circumstances affecting the land unit, have been properly investigated, or until the owner of the land makes an application for rezoning or a zoning determination is made by the municipality;(ii)The special zone provides the municipality with a mechanism whereby special or site specific directives, land use parameters and design parameters may be established for a land unit or area. The special zone can be applied by the stipulation of these special measures in an annexure to this Zoning Scheme, or in terms of an approved site development plan;(iii)In applying the special zone, the municipality must bear in mind the objectives of this Zoning Scheme and of any applicable integrated development plan. The technique can be used to generate appropriate responses to local or site specific issues, but should be used responsibly;(iv)The sub divisional area zone provides the municipality with a mechanism where special or unique factors justify the use of different zonings within a specific site without creating a new zone in this Zoning Scheme.Undetermined zone (UN)Colour notation: Dark brown.Objective:The objective of this zone is to enable the municipality to defer a decision regarding a specific land use and land use provisions until the circumstances affecting the land unit have been properly investigated, or until the owner of the land makes an application for rezoning, or a zoning determination is made by the municipality.
11.1Use of land:The following use restrictions apply to land in this zone:
(a)Primary uses: none.
(b)Consent uses: none.
11.1.1Land use provisionsNew development shall not be permitted on any land in this zone, unless the land is rezoned to a zone which permits such new development, either as a token zoning or the entire land unit.Special zone (SZ)Colour notation: White with light blue outline.Objective:The objective of this zone is to provide for circumstances where special or unique factors justify the creation of a new zone on the zoning map for specific land without justifying the creation of a new zone in this Zoning Scheme. In addition, an opportunity is provided for the introduction of collaborative planning techniques into the development process, whereby a negotiated settlement between the municipality and the applicant is possible in the interest of sustainable development. The mechanism provides for unforeseen or special circumstances where it is not possible or expedient to accommodate the use or activity in an existing use zone, and it allows for innovative design, architectural styles, building forms and site relationships. As one of the key aims of the Zoning Scheme is to provide clarity and consistency, special zones should be used sparingly.
11.2Use of landThe following use restrictions apply to land in this zone:
(a)Primary use: special usage.
(b)Consent uses: any use determined by the municipality, transmission tower, rooftop base station.
11.2.1Alternative methods of development management
(a)The municipality may, at its discretion, employ one of the following methods of development management in this zone:
(i)Special land use provisions may be determined by the municipality and described as a separate special zone in an annexure to this Zoning Scheme. This method is known as the special zone annexure;
(ii)The land use provisions may also be determined by the municipality by means of a site development plan. This method is known as the special zone site development plan;
(iii)The municipality may combine both the special zone annexure method and the special zone site development plan method.
(iv)When a land unit be zoned special zone, special zone annexures and special zone site development plans may be adopted and amended by Council in terms of a standing council resolution, and the formal amendment of the by-law is not required.
(b)The special zone annexure mechanism is suitable for land where:
(i)the land use provisions can be clearly determined, but the development proposals require some flexibility; or
(ii)the size of the proposed development, number of land units or range of uses is such that the proposed development, in the opinion of the municipality, could not readily be categorized into an existing zoning, and special zoning would be the most appropriate option.
(c)The special zone site development plan mechanism is suitable for sites where:
(i)the land use proposals are reasonably fixed and only limited flexibility is required; or
(ii)the size of the proposed development, number of land units or range of uses is such that the municipality considers this method to be the most appropriate for development management.
11.2.2Land use provisionsThe following land use provisions apply:
(a)General
(i)If special and unique factors justify the creation of special land use provisions for land without the creation of a major new zone in this Zoning Scheme being justified, such land may be zoned as a special zone;
(ii)When considering the rezoning of land to this zone, the municipality shall determine land use provisions in accordance with the procedures stipulated in (b) or (c) below;
(iii)Any rezoning to a special zone will be deemed to be a zoning scheme amendment, unless the proposed parameters of a particular rezoning already exist with regard to another special zone governed by this zoning scheme that has already been approved.
(b)Special zone annexure
(i)When the municipality employs the special zone annexure method of development management, it shall identify the area concerned on the zoning map by way of a separate number, and shall stipulate the land use provisions for that area as a separate special zone in an annexure to this Zoning Scheme;
(ii)Each special zone, where the management provisions differ from those of another special zone, shall be given a separate number, and each number with the accompanying land use provisions, shall be described as a separate special zone in an annexure to this Zoning Scheme;
(c)Special zone development plan
(i)Where the municipality employs the site development plan method of development management, it shall require a site development plan to be submitted in terms of paragraph 12.6;
(ii)The reference number of a site development plan approved by the municipality shall be recorded in the register.
Sub divisional Area zone (OZ)Colour notation: White with red outline.Objective:The objective of this zone, is to provide for circumstances where special or unique factors justifies the creation of a sub divisional area,where interactive orientated planning techniques whereby a negotiated agreement between the municipality and the applicant in the interest of sustainable development is possible, be brought into the development process. This leaves space for innovative design, architectural styles, building forms and site scales. Future subdivision and development rights are granted subject to conditions including the submission of a detailed subdivision application. This zone confirms only the principle of subdivision, not the detail which will be determined when an actual application for subdivision is approved.
11.3Use of landThe following use restrictions apply to land in this zone:
(a)Primary uses: all zonings as depicted in this zoning scheme.
(b)Consent uses: as applicable to the various zoning categories.
11.3.1Alternative methods of development managementThe municipality may according to its discretion apply one of the following methods of development management in this zone:
(i)Special development management provisions may be determined by municipality and described as a separate special zone in an annexure to this zoning scheme. This method is known as a special zone annexure;
(ii)The development management provisions may also be determined by municipality by means of a site development plan. This method is known as the special zone site development plan;
(iii)The zoning of the land unit as Sub Divisional Area, shall not exempt an owner from compliance with the provisions of relevant planning laws that govern the subdivision of land;
(iv)The density requirement and other conditions that are laid down at the time of approval of the rezoning to Sub divisional Area shall apply;
(v)Such conditions may include, but are not limited to, requirements for a development framework, environmental management plans, traffic impact assessments, landscape master plans, precinct plans or site development plans;
(vi)At the confirmation of a subdivision for land that has been zoned as Sub Divisional Area, the zoning parameters approved by the municipality as part of the subdivision approval shall be deemed to be a substitution scheme.

Chapter 12
general provisions applicable to all zones

12.1BUILDING LINES
12.1.1Encroachment of building linesThe following additional land use provisions apply in the case of encroachment on building lines:
(a)Notwithstanding the building line regulations set out elsewhere, the following structures or portions of structures may be erected within the prescribed building lines:
(i)boundary walls and fences;
(ii)open and uncovered stoeps;
(iii)entrance steps, landings and entrance porches;
(iv)eaves projecting no more than 0,75m from the wall of the building;
(v)cornices, chimney breasts, flower boxes, water pipes, drain pipes and minor decorative features not projecting more than 500mm from the wall of the building;
(vi)screen-walls not exceeding 1,8m in height above the natural level of the ground, provided that no screen-wall shall be erected over the street building line without the municipality’s consent;
(vii)swimming pools not closer than 1m from any boundary;
(viii)drying yards, provided that no drying yard shall be erected over the street building line without the municipality’s consent, and
(ix)a basement, provided that the basement ceiling does not project above ground level.
(b)The municipality may permit the erection of an outbuilding or additional/ second dwelling unit which encroaches onto the side or rear building line.
(c)When an outbuilding, additional/ second dwelling unit or building is permitted within a side or rear building line, the following conditions shall apply:
(i)no building shall exceed a height of 1 storey;
(ii)no door or window shall be permitted in any wall which is closer than 1m to the side or rear boundary concerned and must comply with the safety distance as specified by the National Building Regulations;
(iii)an access way, other than through a building and at least 1m wide, shall be provided from a public street to every vacant portion of the land unit concerned, other than a courtyard,and
(iv)no runoff of rainwater from the roof shall be discharged onto any adjoining land unit.
(d)In circumstances where there is a zero side or rear building line, the following provisions shall apply:
(i)no door or window shall be permitted in any wall which is closer than 1m to the side or rear boundary concerned and must comply with the safety distance as specified by the National Building Regulations, and
(ii)no runoff of rainwater from the roof shall discharge onto any adjoining land unit.
(e)The municipality may relax the street building line under the following circumstances:
(i)in the case of a garage or carport subject to 12.1.2;
(ii)if, in its opinion, the architectural effect of the building line relaxation will enhance the appearance of a public street, or
(iii)if, in its opinion, there are other special circumstances such as the topography of the site.
12.1.2Garages and carports within building linesThe following additional land use provisions apply with regard to garages and carports within building lines:
(a)The municipality may permit the erection of a garage within the street building line if, in the municipality’s opinion, the garage cannot reasonably be sited at the prescribed distance due to the slope of the land unit, or for other reasons provided that the height of such garage from the finished floor level to the top of its roof shall not exceed 4m.
(b)A carport may be erected on the erf boundary provided that:
(i)the width of such carport measuring the roofing and guttering edge to edge and parallel to the street boundary, shall not exceed 6,5m;
(ii)the roof of the carport shall be supported by metal or wrought timber posts or brick, concrete or masonry pillars;
(iii)the carport shall not be enclosed on any side except by:• a boundary wall or fence;• a wall which forms an external wall to the building, or• another wall or fence, which does not exceed 1,25m in height;
(iv)The height of such carport from the floor to the highest point of its roof shall not exceed 3m, and
(v)The edges of the roof sheeting shall be neatly trimmed with a facia board not less than 150mm in depth.
12.1.3SetbackThe portions of a land unit falling within the setback area, shall be excluded for the purpose of determining coverage and the maximum floor space on the land unit.
12.2OUTDOOR STORAGE AND MOBILE HOMES
12.2.1Outdoor storage and placement of vehiclesThe following land use provisions apply in all zones with regard to outdoor storage and placement of vehicles in the residential zones:
(a)Motor vehicles owned by the occupants of a dwelling unit, and used for commercial activities conducted away from the dwelling unit, may be parked on the land unit concerned, provided that:
(i)no more than one commercial vehicle per dwelling shall be parked on the land unit, and
(ii)the gross weight of any such commercial vehicle shall not exceed 10 000 kg;
(b)A recreation vehicle, such as a caravan, may not be used for habitation by the occupant or guests visiting the occupant of the land unit, for more than 60 days during any 12 month period;
(c)No area visible from a public street shall be used for the outdoor storage of inoperable vehicles;
(d)No area visible from a public street shall be used for the outdoor storage of building material, appliances or similar items except:
(i)when being temporarily stored for the purpose of construction in accordance with a valid building plan approval, and
(ii)in conjunction with a yard or garage sale with a duration of not more than two consecutive days.
12.2.2Mobile homesThe following land use provisions shall apply with regard to mobile homes:
(a)Mobile homes which are to be situated in a mobile home park are subject to any municipality by-law relating to mobile homes;
(b)The municipality may specify categories of mobile homes that may be placed on a land unit zoned for community purposes;
(c)Mobile homes complying with specifications approved by the municipality in terms of (b) above, shall be subject to the following requirements:
(i)The mobile home shall be sited on a foundation slab and anchored to the municipality’s satisfaction;
(ii)Solid perimeter skirting, of material and colour complementary to the mobile home, shall be provided from the bottom of the mobile home to the ground surface;
(iii)The roof and exterior siding of the mobile home shall be of a non-reflective material, and
(iv)Any structural additions shall be of materials which, in the opinion of the municipality, are compatible with the mobile home.
12.3SIGNS AND OUTDOOR ADVERTISEMENTSGeneral Policy Statement:The following general policies and principles shall apply with regard to signage and outdoor advertising unless these policies and principles are superseded by by-laws or policies approved by the municipality:
(i)The environmental impact of outdoor advertising may be controlled and managed in order to preserve the visual quality of the landscape and townscape, and for considerations of road safety;
(ii)The visual impact of outdoor advertising varies according to the type of environment, and the type of advertisement. Some areas are highly sensitive while others are not particularly sensitive and may accommodate outdoor advertising with limited negative effects;
(iii)In general natural and rural areas are highly sensitive to negative visual impacts from outdoor advertising. Urban areas may include places of high sensitivity such as heritage areas and scenic routes, places of some sensitivity such as most residential neighbourhoods, and places of lesser sensitivity such as business districts and industrial areas;
(iv)The municipality may regulate outdoor advertising in a manner that differentiates between environmental quality and the sensitivity of different parts of the municipal area. The general approach should be to regulate the most sensitive areas more strictly, and less sensitive areas less strictly. The potential for outdoor advertising should be determined by linking the area of control with the landscape type and the sign type.
12.3.1 Objective:The objective is to provide minimum provisions for the regulation of large advertisements and signs that are visible from any public street in natural, rural and urban areas, and include all types of billboards and tower structures intended predominantly for advertising purposes. In addition, provision is made for the municipality to designate different control areas where the degree of control is matched with the sensitivity of the environment.
12.3.2Application to display a new sign or alter an existing signThe following provisions shall apply:
(a)Notwithstanding the provisions of the Advertising on Roads and Ribbon Development Act, no person may display a new sign or alter an existing sign which is visible from a public street, and which is equal to or greater than 4,5m2 in area, without prior written approval from the municipality;
(b)In granting its approval, the municipality may impose conditions relating to, but not limited to, the following:
(i)the shape, size and height of the sign;
(ii)colour and texture of the sign;
(iii)the location and orientation of the sign in relation to the road;
(iv)illumination and animation of the sign;
(v)road safety considerations;
(vi)the design and construction of the sign, and
(vii)general maintenance of the sign;
(c)The municipality may require that an impact assessment (as prescribed by NEMA legislation) be conducted by the applicant for any outdoor advertising sign and shall require such impact assessment with regard to an application to display any billboard or sign with an area in excess of 36m². The impact assessment shall include but is not limited to:
(i)a visual impact assessment, and
(ii)a traffic safety assessment;
(d)In granting its approval, the municipality shall limit the period for display of the sign to no longer than 5 years, after which a new application must be submitted.
12.3.3Declaration of areas of controlThe municipality may declare areas of control for signs and outdoor advertisements, and should be guided by the principles and guidelines contained in the South African Manual for Outdoor Advertising Control with regard to the delimitation and management of such areas.
(a)Areas of maximum control
(i)In areas of maximum control the municipality shall strictly regulate all outdoor advertising so that such advertising does not intrude upon, dominate or derogate in any way the character or quality of the environment;
(ii)The municipality may indicate the type of signage that is permitted, is excluded or requires further approval in areas of maximum control;
(iii)All natural and rural areas shall be deemed to be areas of maximum control;
(iv)The following urban areas are deemed to be areas of maximum control:• public open spaces;• urban conservation areas;• scenic drives and vistas from important view points, and• areas of historic or architectural significance, provided that the responsible roads authority may, after an impact assessment, identify areas along main roads where a relaxation may be allowed, in which case these areas will be indicated as areas of partial control.
(b)Areas of partial control
(i)In areas of partial control the municipality shall regulate signage to achieve integration between signage and surrounding land uses, while recognising greater freedom with regard to the size, number and position of such signs;
(ii)The municipality may indicate the type of signage which is permitted, is excluded or requires further approval in areas of partial control;
(iii)The following areas are deemed to be areas of partial control:• high density mixed use areas, including high density residential areas;• medium density residential areas in transition to become office and commercial uses;• local neighbourhood centres, suburban shopping centres and office parks;• ribbon development along main streets;• educational institutions, sports fields and commercialized squares, and• government usage and civic amenities.
(c)Areas of minimum control
(i)In areas of minimum control the municipality shall regulate signage to generally permit signs except for high impact signage;
(ii)The municipality may lay down conditions relating to high impact signage including, but not limited to, the shape, size and height of the sign, colour and texture, the location and orientation of the sign in relation to the road, illumination and animation, road safety considerations, the design and construction of the sign, and general maintenance of the sign;
(iii)The following areas are deemed to be areas of minimum control:• business districts, commercial shopping centres and office precincts;• industrial areas and industrial parks, and• prominent public transport nodes such as railway stations, large bus stations and taxi ranks, airports and harbours, provided that areas of historical, cultural and architectural value shall be excluded from areas of minimum control.
(iv)Areas of control shall be indicated in the appropriate by-law.
12.4PUBLIC NUISANCE AND NOISESubject to the municipality’s by-law relating to Public Nuisances, no person may cause a public nuisance in the municipal area.The municipal manager may cause a noise impact assessment to be undertaken by a suitably qualified person and if the results of such assessment show that the Noise Control Regulations promulgated in terms of NEMA are being contravened, the expenses incurred in respect thereof shall be recoverable as specified above.Any person who fails to comply with any order served on such person in terms of this section or with any condition imposed by the municipal manager in the exercise of his or her powers or the performance of his or her duties there under, shall be guilty of an offence.
12.5ANIMALSBesides the provisions of any by-laws or policy decisions of the municipality which may exist with regard to keeping animals, including poultry, the following additional provisions shall apply in the residential zones, and in the case that any provision contained herein contradicts the provisions of the preceding by-laws or policy decisions, the provisions of such by-laws or decisions shall apply.
(a)No animals may be kept for business purposes on a land unit in residential zones;
(b)Horses and donkeys may be kept for the personal use of the owner or occupier of a land unit and his dependants provided that:
(i)no horses or donkeys shall be kept on a land unit which is less than 8 000m2 in extent, unless the municipality is satisfied that special factors exist, such as the availability of suitable land in the vicinity for grazing and exercising, or poverty on the part of the person concerned;
(ii)an application for a permit to keep horses or donkeys shall be submitted by the applicant and may be approved or refused by the municipality, and such permit shall not be renewed if the applicant has given cause for justifiable and substantial complaint relating to the keeping of horses or donkeys, from neighbours or residents living in the area;
(iii)the applicant shall submit plans to the municipality concerning stables and shall construct the stables in accordance with the municipality’s requirements, and
(iv)stables must be properly maintained, and manure must be handled, to the municipality’s satisfaction so as not to cause any public nuisance.
(c)Poultry, rabbits and other small animals may be raised for domestic, non-commercial use in residential areas.
(d)No person may keep on any land unit in the residential zones,cattle, sheep, goats, pigs, birds, indigenous mammals or wild animals, without the permission of the municipality, notwithstanding whether such animals are kept for commercial or domestic purposes.
12.6.SITE DEVELOPMENT PLANSThe following provisions shall apply with regard to site development plans:
(a)A site development plan shall contain the information specified in the definition of "site development plan"unless the municipality agrees to waive certain requirements;
(b)If considered necessary by the municipality, or required by a competent provincial authority, the submission of a site development plan shall be accompanied by a traffic impact assessment or a traffic impact statement or other additional information considered necessary;
(c)The municipality may approve a site development plan which is submitted for its approval, or may require amendments, or may refuse to approve the site development plan;
(d)In circumstances where a site development plan is required in terms of this Zoning Scheme, no application for subdivision of land, or for building plan permission in terms of the National Building Act, shall be approved by the municipality, unless a site development plan has first been approved;
(e)The land shall be developed in accordance with the site development plan as approved by the municipality, and at the satisfaction of the municipality;
(f)Application may be submitted to the municipality for amendment of an approved site development plan;
(g)The municipality shall process an application to approve or amend an approved site development plan in accordance with its policy for transparency, public participation and administration of such applications;
(h)When approving a site development plan or an amendment to a site development plan, the municipality may impose conditions of approval.
12.7PROPOSED NEW STREETS, STREET WIDENING AND STREET CLOSUREThe municipality may indicate on its zoning map:
(a)new public streets which it proposes to establish;
(b)public streets which it proposes to widen, and
(c)public streets which it proposes to close.
Such indications are intended for the information of the public, and to assist the municipality in achieving its general planning and development principles. The zoning of the land in question does not change until the new public street, street widening or street closure has been approved in terms of the relevant legislation as well as any additional legislative procedures concerning the rezoning.

Chapter 13
Parking, loading and nfrastructure

General Policy Statement:The approach adopted is that off-street parking is preferred in order to maximize operational and safety efficiencies on arterials. In addition, off-street parking should be provided and laid out in a manner that facilitates easy access and avoids back-up into the street system. It is, however, recognized that on-street parking is desired in many cases although this has been shown to reduce road capacity and road safety and poses a risk to pedestrians, in particular children, emerging between parked vehicles.
13.1Parking, loading and accessThe following parking requirements shall apply to all zones except residential zone 4 (incremental housing):
13.1.1Off-street parking requirementsIn cases where parking requirements are not stipulated for a particular use or in terms of a specific condition imposed by the municipality, parking shall be provided in accordance with the attached Table B "Off-Street Parking Requirements". The municipality shall determine off-street parking requirements for land uses not stipulated in Table B. The column in Table B which is headed ‘Normal Areas"refers to standard requirements which apply to areas where public transport is not being specifically promoted.
13.1.2Alternative parking requirementsAs an alternative to compliance with the required off-street parking referred to in paragraph 13.1.1 above, the owner may with the approval of the municipality:
(a)acquire the prescribed area of land for the required parking facilities elsewhere in a position approved by the municipality, and
(b)shall register a notarial deed against such land, the latter which must be within one hundred metres (100m) from the closest point of the land on which the building is erected for the purpose of the application, to the effect that the municipality and the public shall have access to the former for the purpose of parking, and that the owner shall be obliged to level, surface and maintain such land at the satisfaction of the municipality, and the cost of registration of the notarial deed shall be borne by the owner. These conditions may only be amended with special approval by the municipality, or else,
(c)as an alternative the owner may, with the consent of the municipality, pay a cash sum to the municipality equal to the estimated market value per m2 of the land on which the building is erected, multiplied by the area in m2 of the land which is required to be provided, in which event the municipality itself shall be responsible for acquiring the necessary land for such parking purposes when and where the municipality desires.
TABLE B: OFF-STREET PARKING REQUIREMENTS
LAND USENORMAL AREAS
Dwelling House2 bays per unit
Double Dwelling House2 bays per unit
Group Unit1.75 bays per unit0.25bays per unit for visitors
Flats1.25 bays per unit0.25 baysbays per unit for visitors
Additional/Second DwellingUnit1 additional bay
Boarding House, Guest House3 bays per 4 bedrooms
Hotel1 bay per bedroom plus 20 bays
Old Age Home1 bay per 2 bedrooms
Hospital (General and Private)1 bay per bed
Clinic& Medical Consulting Rooms4 bays per consulting room
Funeral Parlour1 bay per 4 seats
Single Shops4 bays per 100m² GLA
Shopping Centre6 bays per 100m² GLA
Offices4 bays per 100m² GLA
Industry2 bays per 100m² GLA
Industrial Hive4 bays per 100m² GLA
Service Station4 bays per repair area minimum of8 baysplus 4 bays per 100m² GLA
Places of Assembly AVorship/Entertainment1 bay per 4 seats
Schools1bay per classroom/office plus 1 per 10 students
Placesof Instruction (other than Schools)1bay per classroom/office plus 1 bay per 6 students
Restaurant1 per 25m2 GLA
Recreation, Sport1 bay per 8 seats
Conference Centres8 bays per 10 seats
13.1.3Additional parking and site access requirementsThe following additional parking and site access requirements shall apply to all zones except residential zone 4, business zone 3 and business zone 4:
(a)Vehicular access shall be limited to 1 combined carriageway crossing per site per public street or road abutting the site;
(b)Notwithstanding (a) above, where the total length of any street boundary of a site exceeds 30m in length, one additional carriage-way crossing may be permitted provided that no two carriageway crossings or combined carriageway crossings are closer than 15m to each other;
(c)No carriageway crossing may exceed 4m in width where it crosses the street boundary, and no combined carriageway may exceed 8m in width where it crosses the street boundary;
(d)If the corner at a street intersection is not splayed, vehicle carriageway crossings shall not be closer than 10m to such corner;
(e)If the corner at a street intersection is splayed, vehicle carriage way crossings shall not be closer than 10m from such corner or 5m measured from the point where the splay reaches the road boundary, whichever is the greater distance from the corner;
(f)Parking areas shall be used for the parking of vehicles that are lawfully allowed access to them, and any activity that causes an obstruction for vehicular traffic, such as pedestrians using the sidewalk, is prohibited;
(g)Parking areas shall be constructed at the satisfaction of the municipality;
(h)Notwithstanding conditions (a) to (g), the municipality may lay down more restrictive requirements in connection with parking and site access if deemed necessary from a pedestrian or traffic safety point of view.
13.1.4Parking layout planA parking layout plan must:
(a)be submitted to the municipality for all parking areas in excess of 6 parking bays, or if required by the municipality, for a lesser number of bays;
(b)indicate the way in which it is intended that vehicles shall park, the means of entrance and exit, and landscaping proposals, and
(c)may be approved or refused by the municipality and itmay impose conditions of approval.
13.1.5Motorcycle and bicycle spaces
(a)The municipality may require that parking be provided for motorcycles and bicycles;
(b)For every 4 motorcycle or 6 bicycle parking spaces provided, a credit of one parking bay may be given towards the parking requirements provided that:
(i)the total credit shall not exceed 2,5% of the parking bays required;
(ii)the minimum dimension for a motorcycle space shall be 2,2m in length and 1m in width;
(iii)the minimum dimension for a bicycle space shall be 2m in length and 0,6m in width, and
(iv)bollards and racks, or other devices for storing and protecting bicycles and motorcycles, should be installed at the satisfaction of the municipality.
13.1.6Parking for the physically disabledParking shall be provided to ensure easy and convenient access for physically disabled persons to services and facilities generally open to the public, and the following provisions shall therefor apply:
(i)The municipality may require that at least one parking bay per land unit is capable of use by a physically disabled person;
(ii)in any parking facility serving the public, parking for physically disabled persons shall be reserved as follows:
PHYSICALLY DISABLED ACCESSIBLE PARKING
TOTAL NUMBER OFPARKING BAYSREQUIRED NUMBER OF PARKING BAYSACCESSIBLE TO THE PHYSICALLY DISABLED
1-501
51-1002
101-1503
151-2004
FOR EVERY ADDITIONAL 100BAYS1 ADDITIONAL PARKING BAY
(iii)parking bays for physically disabled persons shall be a minimum of 2,5m in width and 5,5m in length;
(iv)parking bays for physically disabled persons shall be provided with an adjacent access aisle that shall be a minimum of 1,5m in width, and access aisles may be shared between two adjacent bays for physically disabled persons;
(v)parking for physically disabled persons and access aisles shall be level;
(vi)parking bays for physically disabled persons shall be located as near as possible to accessible building or site entrances and shall be located to provide convenient access to kerb ramps;
(vii)each parking bay reserved for physically disabled persons shall be marked on the parking surface with the International Symbol of Accessibility;
(viii)additional signage indicating the parking bay as reserved for exclusive use by physically disabled persons may be required by the municipality, including a sign warning drivers of the possibility of towing due to unauthorised use and providing information regarding the recovery of vehicles;
(ix)where five or less parking bays are provided, at least one bay shall be 4m wide and marked to provide a parking bay of 2,5m with an access aisle of 1,5m, but the bay need not be reserved exclusively for physically disabled persons only, and
(x)parking for the physically disabled provided in terms of this section shall count toward the fulfilling of off-street parking requirements.
13.1.7Combined parking requirementsThe following provisions for combined parking shall apply:
(a)Where two or more land uses share a common parking area, the municipality may reduce the amount of parking bays required for the respective uses, provided that the municipality is satisfied that the utilisation of the parking area by different uses, is not concurrent and that the total number of bays may not be less than the minimum number of bays required for that use, which legally requires the larger number of bays;
(b)Common bays may not subsequently be reallocated to selective uses, without the consent of the municipality.
13.1.8Loading and off-loading facilitiesThe following provisions for loading and off-loading shall apply:
(a)The municipality may, for the purpose of preventing the obstruction of traffic on any public street adjacent to a land unit, require the owner to submit proposals for suitable and sufficient space on the land unit for any loading, off-loading or fuelling of vehicles that are likely to occur under normal circumstances;
(b)No owner or occupant of a land unit referred to in (a) above, shall undertake or knowingly permit loading, off- loading or refueling of vehicles otherwise than in accordance with the proposals as approved by the municipality.
13.2REFUSE DISPOSALSubject to the municipality’s Solid Waste Management By-law, the municipality may, for the purposes of collecting waste/refuse, require the owner or occupant to install a waste/ refuse receptacle on the land unit which shall:
(a)be of sufficient size to accommodate the refuse generated from the land unit for one week;
(b)be located adjacent to a public street or, at the municipality’s discretion, in a position which will provide acceptable access to a refuse collection vehicle;
(c)be designed in a manner that is architecturally compatible with the surrounding structures and screened from public view, and
(d)comply with any other reasonable condition the municipality may impose relating to health, pollution control, safety or aesthetics.
13.3ANTENNAE SYSTEMSGeneral Policy Statement:The following general policies and principles apply in all zones unless these policies and principles are superseded by a municipal policy or by-law:
(i)A wide range of service providers are involved in the telecommunications and cellphone industry, which has lead to a proliferation, and even duplication of masts and antennae. However, former parastatal service providers have traditionally not been subject to the same approval processes as the private industry. There is a need for a uniform set of rules to apply to all service providers in order to minimise negative impacts;
(ii)While this use needs to be regulated, telecommunication masts are becoming part of the urban and rural landscape and the regulation should not adversely affect the delivery of an efficient telecommunication service;
(iii)The municipality should seek to strike a balance between antenna infrastructure and economic development on the one hand, and the conservation of visual, tourist, environmental and heritage characteristics on the other;
(iv)The municipality should ensure that precautionary measures with regard to the health of the relevant community and security of the base station and antennae as prescribed per NEMA Record of Decision, are established and complied with;
(v)Masts tend to have less impact in areas with high visual absorption potential, such as urban or industrial areas, than in areas with high visual sensitivity and low visual impact absorption potential such as residential, rural and wilderness areas;
(vi)Attention is required, not only to the appearance of the masts themselves, but also to the visual impact of prefabricated containers and related mechanical services. Access roads, power lines, fencing and signage at base stations often add to the visual impact;
(vii)Alternative site locations should be explored early in the planning process in order to minimise the impact of the antenna support structure, rather than relying on camouflage to reduce the impact;
(viii)The municipality should encourage and facilitate the co-location of cellular telecommunication infrastructure where possible, in order to limit proliferation, ameliorate visual impact and facilitate effective control.
Objective:The objective of this section is to provide the municipality with minimum requirements that need to be complied with, in the absence of a by-law dealing with cellular telecommunication infrastructure and other private and commercial antennae systems.
13.3.1Application for commercial antenna
(a)No commercial antenna may be erected, modified or have its radio-frequency emissions altered without the prior written approval of the municipality;
(b)An application for the municipality’s approval to erect a commercial antenna shall include the following information:
(i)a locality plan of the proposed site, indicating the land unit number as registered with the Registrar of Deeds, street address/ geographic locality, the current zoning of the site, and the land uses of the subject and surrounding land;
(ii)information about the type of proposed antenna, including a dimensioned plan of the structure and relation to the site boundaries, a front and side elevation of the structure to scale including any other buildings or structures on the site, and proposed lighting of the structure;
(iii)a site development plan including proposed mitigation measures, and
(iv)if required by the municipality, a visual impact assessment of the proposal, including photographic material in order to adequately evaluate the proposal;
(c)The municipality may request the applicant to provide information about technically viable alternative sites or structures, and to fully motivate any failure, if so, for co-location to be provided at such sites or structures;
(d)In the event of an application by a person other than the land owner, the applicant shall submit a duly executed power of attorney to the municipality;
(e)The applicant shall comply with the requirements as determined in terms of NEMA;
(f)The municipality may approve the application for a period not exceeding 15 years, and impose conditions including but not limited to:
(i)visual impact mitigation;
(ii)reasonable precautionary measures in regard to the health of the relevant community, and
(iii)security of the base station and antennae.
13.3.2Radio frequency emissionsThe following provisions shall apply in the interests of a healthy environment:
(a)All cellular telecommunication infrastructure or combination of such infrastructure must comply with the ICNIRP public exposure standards;
(b)No cellular telecommunication infrastructure or combination of such infrastructure may at any time operate with radio-frequency emission levels that exceed the ICNIRP public exposure standard, and shall operate below such standard where technically and financially feasible;
(c)If an application is made for a shared site, the total projected radio-frequency emission levels for the entire installation must be submitted to the municipality as part of the application;
(d)The municipality may cause regular measurements to be made to ensure that the operation of all cellular telecommunication infrastructure in its area of jurisdiction complies with the ICNIRP public exposure standard, at the cost of the network/ service providers;
(e)In the event that such measurement shows that the ICNIRP public exposure standard is exceeded, the consent of the municipality shall lapse and the municipality may cause the cellular telecommunication infrastructure to be decommissioned at the cost of the network/service providers.
13.3.3Decommissioned antennaeThe following provisions shall apply with regard to decommissioned antennae:
(a)The owner or operator of the antenna system shall remove all infrastructure relating to the antenna system within one (1) year of the antenna being decommissioned;
(b)Where the site has been disturbed, the owner or operator of the antenna system shall rehabilitate the site to its original state or to a state acceptable to the municipality;
(c)Where the owner or operator fails to comply with (a) or (b) above, the municipality may remove the antenna system and related infrastructure, and rehabilitate the site at the cost of the owner or operator.
13.3.4Satellite dish antenna systemsThe following provisions shall apply with regard to domestic satellite dish antenna systems:
(a)Satellite dish antenna systems that are mounted on the ground shall be placed in a position that minimizes the visual impact on the surrounding area;
(b)Satellite dish antenna systems which are mounted to the side of a building shall be:
(i)placed so that they are not visible from a public street or surrounding area, or
(ii)architecturally screened so as to minimize the impact on the surrounding land units and from the public streets;
(c)Satellite dish antenna systems that are mounted on the roof of a building shall be:
(i)set back as far as practically possible from the edge of the building, and
(ii)architecturally screened so as to minimize the impact on the surrounding land units and from the public streets;
(d)The colour of the satellite dish antenna systems must be a single, non-gloss colour of cream, off-white, beige, dark green, black or grey.

Chapter 14
Subdivision, consolidation, departures, consent uses

14.1Subdivision of land
14.1.1Subdivision applications
The municipality may grant or refuse an application for the subdivision of land in terms of section 30 of the by-law, subject to the conditions applicable to a sub divisional area, as well as an application for the subdivision of land involving no change in zoning.The municipality shall not grant a new subdivision unless it is satisfied that, for each land unit created, there is adequate and lawful means of:
(a)access from a public street;
(b)water supply, if required, and
(c)sewage disposal, if required.
14.1.2Minimum subdivision size
The zoning map may designate areas where a minimum subdivision size is specified for a land unit, in which case the net erf area of a new subdivision and any remainder, shall not be less than the minimum size specified.
14.1.3Subdivision permitting attached dwelling units
Subsequent to the granting of a subdivision permitting two or more adjoining land units with attached dwelling units to be held under separate title, the owners shall:
(a)maintain such part of any retaining wall, roof, pipe, gutter, wiring or other structure that is common to the adjoining land units or attached dwelling units;
(b)permit access to such land units or dwelling units for the purposes of maintaining, repairing, renewing or altering any wall, roof, pipe, gutter, wiring or any other structure, and
(c)not make any alterations to, or demolish any part of the buildings erected on such land units, including boundary walls and fences, or change the exterior colour scheme or materials of such buildings, without the written consent of the municipality.
14.1.4Utility services
Subsequent to the granting of a subdivision, the owner of any land unit must, without compensation, allow:
(a)gas mains, electricity, telephone and television cables, water pipes, foul sewers, storm water pipes, ditches and channels from any other land unit or land units to be conveyed across the land unit concerned, and
(b)installations such as mini-substations, meter kiosks and service pillars to be installed thereon, if considered necessary by the municipality, in such manner and position as may from time to time be reasonably required, and must allow right of access to the land unit at any reasonable time for the purpose of constructing, removing or inspecting any works connected with the above.
14.1.5Bank stability
Subsequent to the granting of a subdivision, the owner of any land unit must, without compensation:
(a)receive such material or permit such excavation on the land unit as may be required to allow the use of the full width of an abutting street and provide a safe and proper slope to its bank necessitated by differences between the level of the street as finally constructed and the level of the land unit, or
(b)alternatively the owner may elect to build retaining walls at the satisfaction of, and within a period to be determined by, the municipality.
14.1.6Subdivision not confirmed
The municipality may permit a building or structure to be erected on a land unit forming part of a subdivision that has not been confirmed.
14.2CONSOLIDATION OF LAND
14.2.1Application of land use provisions to consolidated land units
When two or more individual land units are consolidated, the boundaries of the consolidated land unit shall for the purposes of the administration of this Zoning Scheme, be the new cadastral boundaries as shown on an approved land survey diagram. Former building lines,coverage and other provisions, which previously applied to individual land units, shall not remain in force in respect of those former land units, but shall apply to the consolidated land unit in accordance with this Zoning Scheme.Where two or more individual land units are combined to form a consolidated land unit, and the municipality receives a pre- application enquiry or building plan application, which would, in its opinion:
(i)substantially alter the character of the area, with negative consequences, as a direct result of the size of the consolidated land unit, and
(ii)include a larger surface area of building, larger bulk of structures, or reduction of space between built elements, than would have been possible prior to consolidation due to the building lines, floor space or coverage provisions that formerly applied to the individual land units in terms of this Zoning Scheme,
The municipality may impose additional land use provisions. The additional land use provisions referred to above may:
(i)relate to the bulk, spacing and position of buildings on the consolidated land unit, and
(ii)be more restrictive than the land use provisions that would normally apply to the consolidated land unit in terms of this Zoning Scheme, but
(iii)not be more restrictive than the land use provisions which applied to the former individual land units, prior to consolidation, unless the land is rezoned.
14.3DEPARTURESA municipality, may, in terms of section 30 of this by-law, respectively grant or refuse an application for a departure, or determine an extended period, after which such departure shall lapse;
14.4APPLICATIONS FOR CONSENT USESSubject to the provisions of section 30 of this by-law, the municipality may, where application is made to it for its consent for the erection or utilisation of a building in a zone in which a building of the type proposed may be erected and utilised only with the municipality’s special consent, grant or refuse its consent, and shall in granting its consent be entitled to impose such restrictive conditions as it may deem fit, governing the erection or utilisation of such building.

Chapter 15
Interpretation and definitions

INTERPRETATION
15.1Rules for interpretation:The following rules of interpretation shall apply:
(a)In this zoning scheme, in the register, in any note on the zoning map and in any condition imposed in terms thereof, the words and expressions shall have the meanings assigned to them in accordance with the definitions contained herein except where a contrary interpretation is clear from the context. Interpretation of words not defined herein will have the meanings assigned to them in the "New Shorter Oxford English Dictionary"published by Oxford University Press, except where a contrary interpretation is clear from the context;
(b)Headings contained in this Zoning Scheme shall be used for reference purposes only, and shall not be construed to govern, limit or modify the meaning or intent of any provision of the zoning scheme;
(c)The masculine gender includes the feminine and neuter, and vice versa, and the singular includes the plural, unless the context indicates otherwise;
(d)Whenever reference is made to legislation, the reference applies to all substitutions, amendments and additions thereof;
(e)Whenever reference is made to the use of a building, the reference applies also to the erection of a building, to the use of part of a building and to the use of a land unit, whether a building is erected on the land unit or not;
(f)It is important to note that the terms "must", "shall" and "may not" are mandatory, and the term "may" when used in the positive is not mandatory, unless the context clearly indicates otherwise;
(g)The municipality’s interpretation of the text shall prevail unless the contrary is proven.
15.2.Methods of measuring distances and levelsThe following provisions apply with regard to the method of measuring distances and levels:
(a)Where reference is made or implied to the distance between boundaries or between a building and a boundary, this distance shall be measured in the following manner:
(i)The boundary or boundaries and all points of the building shall be projected onto a horizontal plane, and all measures shall be made in such a plane;
(ii)The distance between a point on a building and a boundary shall be measured at right angles to the boundary;
(b)Where reference is made to a portion of a boundary "opposite"a building, such portion shall be defined by drawing lines in a manner described in (a) from points on such building, at right angles to such boundary;
(c)Where reference is made to a grade-line, or to the level of the ground or of a roof, parapet or other thing, such level shall be calculated in accordance with recognised geometric principles. In any case where the levels involved are so irregular that calculation in accordance with these principles is impractical or leads to a result that is not in accordance with the intent of the Zoning Scheme, the municipality shall determine the level.
15.3.Interpretation of boundariesWhere uncertainty exists as to the boundaries of use zones, the following rules apply in the order listed:
(a)Boundaries shown as following or approximately following any public street or road shall be construed as following the cadastral street boundary;
(b)Boundaries shown as following or approximately following any land unit boundary shall be construed as following such boundary;
(c)Boundaries shown as following or approximately following natural features shall be construed as following such features;
(d)In the event of further uncertainty as to the boundaries of a use zone, the municipality shall make a determination.
15.4Interpretation of categories of use and zoningThe municipality shall determine the category of use or zoning, and its decision shall be final unless the contrary is proven, where:
(a)there is uncertainty or dispute about zoning categories;
(b)there is conflict between the provisions of a zoning map, this Zoning Scheme or the register, or
(c)there is uncertainty or dispute relating to the zoning of land.
OVERLAY ANNEXURESANNEXURE A: SPECIFIC OVERLAY ZONES
1.General Policy Statement:The following general policies and principles shall apply to land affected by an overlay zone unless the policy and principles are subordinate to an approved spatial development framework or spatial development plan:
(a)A range of overlay zones can be used to increase flexibility and provide opportunities for development in response to special circumstances or local conditions. Once an overlay zone is adopted for a particular area, it shall apply in addition to any base zone applicable in that area. An overlay zone provides the municipality with a mechanism whereby directives, land use parameters and design parameters may be established for land, and which will apply over and above the existing zoning or zonings applicable to the land;
(b)In applying the overlay zones, the municipality must bear in mind the objectives of this Zoning Scheme and of any applicable integrated development plan. The techniques can be used to generate appropriate responses to local or site specific issues, but should be used responsibly;
(c)Before an overlay zone is applied to land municipality must follow a transparent process, whether by means of forward planning initiatives, rezoning procedures or decisions in terms of this Zoning Scheme. It should entail a process of co-operation between municipality, the community and land owners.
2.Adoption, Replacement or Amendment of Overlay Zones
(a)Overlay zones, which provide for development directives as contained in the Overlay Zone Annexures, may be adopted, replaced or amended by following the rezoning procedures stipulated in this by-law;
(b)The municipality may grant departures from the development rules or restrictions or provisions of any overlay zone by following the departure procedures stipulated in this by-law;
(c)municipality may adopt an area as an overlay zone and:
(i)must adopt such area as an overlay zone on the zoning map;
(ii)must record such adoption in an annexure together with the cross reference to any design guidelines approved for the designated area;
(iii)must record the land use provisions for every overlay zone area in an annexure to this regulations, and
(iv)may add or omit to this assignment when the procedures as explained in Annexure A has been followed.
3.Identification and Numbering of Overlay Zones
(a)The municipality shall give a distinctive name and number for each overlay zone and any subzone when adopting such overlay zone or sub-zone;
(b)The municipality shall indicate the area of an overlay zone on the zoning map, and;
(i)shall record the existence of an overlay in the annexure to this regulation, with reference to where any detailed provisions of the overlay zone may be found;
(ii)may include any detailed provisions of the overlay zone as an annexure to this regulation, or
(iii)may record the detailed provisions of the overlay zone in a separate document with a cross reference to that document in the annexure concerned.
4.Status of Overlay Zones
(a)An overlay zone does not change the underlying zoning of the properties to which it relates, but may vary the development rules relating to these properties;
(b)The development rules of an overlay zone may be more restrictive or more permissive than the development rules applicable to the underlying zoning of the land concerned as recorded in this regulation;
(c)If the provisions of an overlay zone are different to, or in conflict with, the provisions of a base zone, the more restrictive provisions shall apply, unless stated otherwise in the overlay zone concerned;
(d)The provisions of an overlay zone do not in any way detract from any obligations in terms of national and provincial legislation;
(e)The provisions of more than one overlay zone may apply to a land unit or area.
Annexure A.1: Heritage Area Overlay Zone (HAO)Objective:The objective of the heritage area overlay zone is to guide development in order to protect and enhance the character of an area which has special historical, heritage, cultural or architectural value. In addition, this zone creates the mechanism whereby heritage areas may be protected in compliance with the requirements of Section 37(1) of the Heritage Resources Act.
1.Overlay zone:The provisions of this overlay zone apply in addition to the provisions which apply to the base zone of the land.
1.1Land use provisionsThe following land use provisions apply to this zone:
(a)The municipality’s approval
The municipality’s prior written approval is required for any one or more of the following activities within this overlay zone:
(i)the demolition of a building or structure or part thereof, other than an internal wall or partition;
(ii)the erection of, or alterations to, a building or structure other than an internal wall or partition;
(iii)the erection of a sign, or
(iv)the removal of a mature tree or a mature hedgerow that can be preserved.
(b)Factors which the municipality must consider before granting approval
(i)The municipality shall not grant approval in terms of 1.2(a) above if in its opinion the proposed action would be potentially detrimental to the historical or architectural character of a historic conservation area;
(ii)Before granting its approval, the municipality shall give consideration to the principles contained in Annexure A as well as the general planning and development principles referred to.
1.2Criteria for identification of a heritage areaThe following criteria shall apply to the identification of a heritage area:
(a)the history of settlement in the area;
(b)the conservation worthiness, architectural excellence, cultural value, history and age of buildings, urban spaces or structures in the area, and
(c)the aesthetic value of the landscape, streetscape or townscape of the area.
1.3Grading of buildings, structures or spacesWithin a heritage area overlay zone the municipality may grade a structure or space according to its relative conservation worthiness, in terms of the following criteria:
(a)Grade 1 shall be considered to have qualities so exceptional that they are of special national significance and are proclaimed national monuments or have the potential to be proclaimed a national heritage resource, or which the municipality regards as:• of great architectural, historic or cultural significance, or• rare or outstanding examples of their period in history;
(b)Grade 2 shall be considered to have special qualities which make them significant in the province or region, or which the municipality considers to have a good degree of conservation worthiness because:• of good architectural, historical or cultural significance;• they are landmarks for historical or aesthetic reasons, or• they are good examples of their period in history;
(c)Grade 3 shall include other heritage resources which in the municipality’s opinion are worthy of conservation and which comply with the assessment criteria set out in Section 3(3) of the Heritage Resources Act, or which the municipality considers to have a high value in the greater scheme of things and are regarded as:• of some architectural, historical or cultural significance, and• contributing to the character of the area.
1.4Principles for the control and management of developmentThe municipality’s decisions relating to land use or development in this zone shall take into account the following principles for the control and management of development:
(a)the preservation and restoration of Grade 1 buildings shall be given high priority;
(b)the preservation, restoration and adaptive re-use of Grade 2 buildings shall be encouraged;
(c)the maintenance of the existing building form or envelope of Grade 3 buildings shall be encouraged;
(d)new buildings and existing buildings should be in keeping with the character and heritage of the area without the form, proportion or materials of the proposed development necessarily being limited, and;
(e)The municipality shall, when applying the land use provisions of this zone, endeavour not to diminish the reasonable development potential of a land unit as permitted in terms of the base use zone, while still responding to the objective of this zone.
1.5Conservation and design guidelinesThe municipality may prepare specific guidelines for conservation, design and development within a heritage area overlay zone and shall take such guidelines into consideration before granting permission in terms of Annexure A. Different areas may be subject to different conservation and design guidelines, which may include, but is not limited to, the following:
(a)architectural form and specifications;
(b)urban design;
(c)vistas, and
(d)streetscape.
Annexure A.2: Environmental Protection Overlay Zone (EPO)Objective:The objective of this zone is to protect the special natural and environmental characteristics of an area, to encourage a sensitive form of development for the benefit of the local and general population, including tourists, and to promote sustainable development.
2.General:
(a)Overlay zone
(i)The provisions of this overlay zone are in addition to those provisions applying to the base zone of the relevant land, and
(ii)The provisions of this zone are of a general nature and may be interpreted by the municipality with some flexibility in its application to specific sites, provided that the objective of this zone is respected.
(b)Liability
Any person undertaking development in this zone does so at their own risk, and the municipality accepts no liability for flood damage, erosion damage, landslide damage or other damage that may occur on a land unit.
(c)Application of this Zoning Scheme
(i)The municipality may, at its discretion, employ one of the following methods of development management in an environmental protection overlay zone: the municipality may do so in terms of an approved environmental management plan or in terms of the provisions as specified in this Zoning Scheme for a specific sub-zone;
(ii)The provisions of an approved environmental management plan shall apply as the overlay zone provisions in areas where the municipality has decided to employ such provisions for the purpose of development management;
(iii)In an area where there is no approved environmental management plan, or where such plan does not contain provisions for development management, the municipality may apply the specific provisions stipulated in this overlay zone that relate to the environment or sub-zone of the area concerned, including, but not limited to the following:• a hillside area• a river, wetland or floodway• a coastline• a fire management area, or• another special environmental area.
(d)Site development plan
The municipality may require a site development plan to be submitted to its satisfaction in terms of paragraph 12.6 for all development in the environmental protection overlay zone.
2.1Hillside area provisions:In the absence of an approved environmental management plan, the municipality may apply the following provisions to land situated on a hillside or mountainous area:
(a)Grading and earthworks
(i)No development on any land with a gradient steeper than 1:4 will be considered.
(ii)Grading of any land unit shall conform to the following principles, based on the natural slope of the land, unless the municipality grants its prior written approval to deviate from these principles:• On a slope of less than 1 in 5, any grading should respond to the natural character of the land form, and techniques such as custom foundations, split level designs and stacking of built form are expected to reduce the need for large platforms;• On a slope of between 1 in 5 and 1 in 4, limited grading may occur, but major topographical features shall retain their natural forms, and special hillside or mountainous architectural and design techniques must be used to ensure that structures fit in with the natural land form;
(iii)All graded areas shall be protected from wind and water erosion through slope stabilisation methods acceptable to the municipality, such as planting, walls or netting. The municipality may require submission of an erosion control plan, certified by a registered professional engineer;
(iv)Slopes created by grading of land shall not exceed 1 in 2 unless a soils report and stabilisation report is submitted at the satisfaction of the municipality;
(v)No graded slope shall exceed 10m in height between terraces, provided that the municipality may permit a larger height where the slope will result in a natural appearance and will not, in the municipality’s opinion, create geological or erosion hazards.
(b)Water drainage
(i)If required by the municipality, on-site water catchment basins, siltation basins and water energy absorbing devices shall be provided as a means to prevent erosion and to provide for groundwater rejuvenation;
(ii)Natural drainage courses shall be protected from grading activity;
(iii)Where drainage ditches are required, they should wherever possible incorporate natural plant materials and local rock;
(iv)The maximum average coverage of a land unit by impervious surfaces shall not exceed 40% of the gross erf area.
(c)Vegetation
(i)Indigenous vegetation and mature trees shall be preserved wherever possible and incorporated into the design of buildings or land uses on the land unit;
(ii)Exposed slopes and graded areas shall, where possible, be landscaped with ground cover, shrubs and trees.
(d) Building design and placement
(i)Buildings shall be designed so as to blend into the terrain, to be compatible with the natural surrounds of the area, and shall not impinge on the natural environment;
(ii)Exterior finishes shall blend in with the natural surroundings through the use of earth tones and the avoidance of reflective materials and finishes;
(iii)Buildings shall be sited in a manner that will:• preserve or enhance vistas, particularly those in view from public places;• preserve visually significant rock outcrops, natural water features, indigenous plantcommunities and areas of visual or cultural-historical significance, and• respond sympathetically to existing views from adjoining buildings and land units;
(iv)The highest point of any building shall not project above a ridgeline when viewed from the boundary of the land unit, unless approved by the municipality;
(v)Where a retaining wall faces a public street, the wall shall be clad with aesthetically pleasing material such as the mimicking of natural rock faces, or plant material.
2.2 Floodway area provisionsIn the absence of an approved environmental management plan, the municipality may apply the following provisions to land situated in, or adjacent to, a river, wetland or floodway:
(a)All encroachments into floodways, including fill, new construction, substantial improvements and other development, are prohibited, without the prior written approval of the municipality;
(b)No natural watercourse shall be relocated so as to change its position without the prior written approval of the municipality;
(c)No development which in the municipality’s opinion might adversely affect the water carrying capacity of any floodway, may be undertaken without the prior written approval of the municipality;
(d)The municipality may identify areas of special flood risk or erosion risk related to floods, and may control or prohibit development in such areas. This may include special provisions relating to the area defined by the 1 in 50 year flood line and the area falling between the 1 in 50 year flood line and the 1 in 100 year flood line;
(e)Any new building, and substantial improvement of an existing building, shall have the lowest floor elevated to a level above the base flood level.
2.3Coastal edge provisionsIn the absence of an approved environmental management plan or any other relevant by-laws, the municipality may apply the following provisions to land that are situated adjacent to the high water mark, or adjacent to public open space which is adjacent to the high water mark:
(a)No access for vehicles or boats shall be permitted to the beach or coastline across a side or rear boundary;
(b)No footpath or pedestrian access to the beach or coastline shall be permitted without the prior written approval of the municipality;
(c)Where the municipality grants its approval in terms of (b) above, it may impose conditions in respect of the location, demarcation and construction materials for such footpath or access, together with conditions relating to the conservation of vegetation and stabilization of sand dunes;
(d)A footpath or access, which has not been authorized by the municipality, shall be closed off and vegetation restored by the owner at the satisfaction of the municipality on written demand, failing which the municipality may undertake the necessary work and recover the costs reasonably incurred, from the owner;
(e)The owner or occupant of a land unit shall not destabilize, destroy or harm sensitive natural features of the coastal zone on that land unit, such as frontal dunes, beaches, primary vegetation, wetlands, estuaries, or stream banks, without the prior written approval of the municipality. If the municipality grants its approval, it shall specify requirements to minimize damage to the environment;
(f)If, in the opinion of the municipality, a dune or portion of a dune within a land unit poses a hazard due to its instability or threat of instability, the municipality may require the owner of that land unit to undertake stabilization measures.
2.4Fire management area provisionsThe municipality may stipulate special fire management provisions for an area designated as a fire management area in terms of this overlay zone.
2.5Other special environmental featuresThe municipality may stipulate additional provisions to guide development in an area which is subject to the provisions of an environmental protection zone and which contains special environmental features not covered by the above sections.Annexure A. 3: Special Management Area Overlay Zone (SMAO)Objective:The object of the special management area overlay zone is to provide an opportunity for special management provisions, in particular in agricultural and rural areas, and to accommodate good design or innovative ideas under controlled circumstances in order not to create harmful precedents. The method is supported by the placing of a contractual obligation on land owners to whom additional land use rights have been granted.
3.Overlay zoneThe provisions of this overlay zone are in addition to those provisions which apply to the base zone of the relevant land, and
(a)may be more or less restrictive than the provisions applying to the base zone of the land, and
(b)if the provisions of a special management area overlay zone are in conflict with the provisions of the base zone, the more restrictive conditions apply.
3.1 DesignationSpecial management areas may include important landscapes, environmental areas or cultural areas, such as the following but are not limited to:
(a)agricultural areas showing certain patterns of development and landscapes, such as wine farms with traditional vineyard nodes;
(b)scenic areas which have a special value as tourist attractions due to the pattern of the landscape or the character of settlements in that landscape, and
(c)farming areas containing considerable flora and fauna.
3.2Land use provisions
3.2.1The land use provisions contained in the special management area overlay zone may vary between areas and may include, but are not limited to, the following matters:
(a)provisions to encourage required types of land use and levels of conservation, including the following:
(i)voluntary reserves, where land contains or is suitable for, important eco-systems and habitats, and where owners co-operate to retain the natural character of such reserves;
(ii)management agreement reserves, where land contains areas of rare and threatened habitat and where development rights are restricted, and
(iii)contractual reserves, where land units are sufficiently large to be self-contained ecosystems, and development rights are restricted but conservation and appropriate tourist related uses are encouraged;
(b)provisions to protect and encourage a certain pattern and type of agriculture, and
(c)provisions to protect and encourage a certain pattern and type of settlement.
3.2.2The municipality may place a contractual obligation on a land owner, to whom additional land use rights have been granted, to deal with the following matters:
(a)implementation of an environmental management system to ensure that land use and resources are managed in a manner that promote environmental sustainability and biodiversity;
(b)implementation of a trust fund to ensure that the necessary financial resources are available for effective long term management of the area;
(c)protection or improvement of the aesthetic quality of the area, and
(d)provisions for environmental auditing, monitoring and corrective action.
Annexure A. 4: Bioregional Planning Overlay Zone (BRPO)General Policy Statement:The planning and environmental management approach known as bioregional planning incorporates a process and set of principles to promote biodiversity and sustainable development. The aim of this approach is to facilitate a balanced integration of conservation and development interests, and in particular to support a programme of biosphere reserves throughout the Cape Floral Kingdom, which is internationally recognised and is the smallest of the six floral kingdoms of the world. The Cape Floral Kingdom is characterised by its exceptional richness and diversity, and requires special treatment because of its relatively small geographic area and the development pressures being exerted in this area.The Provincial Government of the Western Cape is actively promoting the biosphere reserve programme and the bioregional planning process. Various mechanisms are available to support this process, such as integrated development plans and this Zoning Scheme which include a range of base zones to help manage sustainable development and conservation. An additional mechanism is the overlay zone which is an enabling mechanism that permits the municipality to implement area specific requirements in support of the bioregional planning approach.Objective:The objective of the bioregional planning overlay zone is to provide a mechanism to support bioregional planning, biodiversity and sustainable development. The overlay zone provides the municipality with the opportunity to determine land use provisions that respond to specific issues and characteristics of different bioregions, including core, buffer and transition areas.
4.Overlay zoneThe provisions of this overlay zone are additional to those provisions which apply to the base zone of the relevant land, and
(a)may be more restrictive or less restrictive than the provisions applying to the base zone of the land, and
(b)if the provisions of a bioregional planning overlay zone are in conflict with the provisions of the base zone, the more restrictive conditions apply.
4.1Land use provisions
4.1.1The bioregional planning overlay zone may be further divided into sub-zones in accordance with established bioregional planning principles, including:
(a)core areas;
(b)buffer areas, and
(c)transition areas.
4.1.2The land use provisions contained in the bioregional planning overlay zone may vary between different bioregions and different sub-zones and may include, but are not limited to, provisions to:
(a)conserve viable natural ecosystems and biodiversity;
(b)promote good environmental management and sustainable land use;
(c)ensure that ecological corridors remain open to support and enhance biodiversity;
(d)promote outdoor recreation and environmental education;
(e)encourage sustainable harvesting of natural resources;
(f)encourage conservation and nature-related economic development;
(g)create effective buffers between core and transition areas;
(h)provide minimum subdivision sizes to maintain ecosystems of sufficient size;
(i)restrict inappropriate consent or secondary uses;
(j)promote appropriate architectural, urban design and place-making principles, and
(k)promote other bioregional planning principles.
Annexure A. 5: Urban Edge Overlay Zone (UEO)General Policy Statement:The following general policies and principles shall apply in the urban edge overlay zone, unless the policy and principles are subject to an approved spatial development framework or spatial development plan:
(i)The urban edge overlay zone is designed to assist the municipality to manage development along the urban edge. The urban edge refers to the transition in land use and socio-economic characteristics, which distinguish between urban and rural areas.
(ii)The urban edge is significant for the following reasons;• it serves as a gateway to urban areas, and accentuates the quality of rural landscapes;• it integrates urban open space systems with the rural hinterland;• it serves as an interface between multiple use urban areas and ecologically sensitive natural areas, whether these are conservation or agricultural areas;• it provides for the protection of resources vital to the functioning of urban areas, such as recreational, agricultural, infrastructural and mineral resources;• it provides amenity spaces around urban areas, and• it provides landscapes for the conservation of certain historical precincts and serves as a significant visual resource;
(iii)In pursuit of sustainable development, the establishment of an urban edge overlay zone provides the municipality with an opportunity to:• contain urban sprawl;• protect significant and sensitive environments and resources;• re-orientate growth expectations;• densify built environments in pursuit of efficiency;• restructure growth patterns, and• rationalise service delivery areas;
(iv)The establishment of the urban edge overlay zone provides the municipality with additional land use provisions to pursue the abovementioned principles.
Objective:The objective of the urban edge overlay zone is to guide development along the urban edge area in order to achieve a sensitive transition between urban and rural environments, to contain urban sprawl and to protect vulnerable rural areas adjacent to urban development.
5.Overlay zoneThe provisions of this overlay zone are additional to the provisions applying to the base zone or zones of the relevant land.
5.1Designation of the urban edge overlay zoneThe urban edge overlay zone shall comprise the following components:
(a)a demarcated line, being the urban edge, that defines the outer limits of urban development over a period of time, and
(b)management zones, on either one or both sides of the urban edge, for which land use provisions are stipulated to direct and control the use of land.
5.2Determination of the urban edgeThe municipality shall consider, but is not limited to, the following factors, when demarcating the urban edge:• the physical environment;• the biophysical and ecological environment;• river and wetland systems;• infrastructure location and capacity;• land use and related patterns;• demographic and socio-economic profiles and trends;• the legal, land use planning and land ownership situation;• the cultural and historic environment, and• visual resource analysis.
5.3Determination of management zonesThe municipality shall, without being limited to, determine the following management sones:
(a)Urban transfer zone
(i)The urban transfer zone must demarcate an area within the urban edge adjacent to existing or planned urban development and associated facilities;
(ii)The municipality may, when an urban transfer zone is demarcated, determine the land use provisions applicable to an urban transfer zone so that it may be more restrictive or less restrictive than the provisions of the base zone;
(iii)The land use provisions applicable to an urban transfer zone may, without being limited to, include measures to:• reduce density, fire risk and the visual impact of development, and• protect natural vegetation, areas of cultural or environmental interest and ecological corridors.
(b)Non-urban zone
(i)The non-urban zone must demarcate an area outside of the urban edge;
(ii)The municipality may, when a non-urban zone being demarcated, determine the land use provisions applicable to the non-urban zone that can be more or less restrictive than the provisions of the base zone;
(iii)The land use provisions applicable to a non-urban zone may, without being limited to, include measure to:• reduce density, fire risk and the visual impact of development, and• protect natural vegetation, areas of cultural or environmental interest and ecological corridors.
(c)Separate management provisions may be determined for:• an urban transition sector;• a non-urban sector, and• different areas along the urban edge in either the urban transition sector or non-urban sector.
5.4Land use provisionsThe municipality may request an applicant to submit a site development plan, to its satisfaction, in terms of paragraph p12.6 for all new development within the urban edge overlay zone.Annexure A.6: Scenic Route Overlay Zone (SDO)General Policy Statement:The visual amenity of the Western Cape is a significant resource that should be protected in order to ensure the quality of the environment as a whole, as well as promote the tourism and the recreational potential of the province. It is therefor important that development, in particular along tourist routes and main transport routes, be managed to prevent development that may detract from the natural beauty of the landscape or from the cultural significance of the built environment.This zone is therefor directed at protecting and maintaining our heritage, while at the same time allowing reasonable development to occur. The scenic route overlay zone should therefor ensure that new development is developed in a sensitive manner so that important views from scenic routes are not impaired.Objective:The objective of the scenic route overlay zone is to conserve the scenic resources adjacent to important tourist and transport routes and to establish a sustainable balance between protection and development.
6.Overlay zoneThe provisions of this overlay zone are in addition to the provisions applying to the base zone of the relevant land.
6.1Designation of a scenic routeThe municipality may designate a public street or road or portion of a public street or road as a scenic route and:
(a)shall designate the scenic route corridor associated with the scenic drive;
(b)may amend the borders of the scenic route corridor after a scenic route corridor study has been done to incorporate other areas with an important visual quality or omit areas that are not important for the visual quality of the scenic route.
6.2Land use provisionsThe municipality may apply the following land use provisions on land in the scenic route corridor:
(a)Site development plan
(i)The municipality may require that a site development plan be submitted to its satisfaction in terms of paragraph 12.6 for consideration and approval;
(ii)In addition to the standard requirements, the site development plan should identify the following on the site development plan without being limited thereto:• the nature of the scenic amenity of the land;• the particular views that need to be preserved and enhanced, and• the location, nature and form of the development, and• indicate compliance with the provisions of (b) and (g) hereunder.
(b)Building placementThe following principles apply to the placement of buildings:
(i)Buildings and structures shall be sited so as to limit tree removal, earthworks and alteration of the natural topography and land forms;
(ii)Buildings shall be designed to blend in with the natural setting, or if applicable, the cultural setting;
(iii)Buildings shall be located to retain existing panoramic and scenic views as seen from the scenic route.
(c)Building height
(i)On the down-slope side of a scenic route, no portion of a building or structure shall project to a height above the level of the footway in the public street, unless the municipality grants its approval on the basis that:• exceptional circumstances exist which directly affect the land, building or use concerned,• the building design is of a unique character or landmark as seen from the scenic route, or• circumstances exist which make it impossible to erect a building on the land unit;
(ii)On the up-slope side of a scenic route, no portion of a building shall project so as to impair the view of the top of a ridge, hill or mountain, identified as significant by the municipality, when viewed from a point 1m above the centre-line of the scenic route at a position or positions determined by the municipality;
(iii)Building heights must, in the municipality’s opinion, be compatible with existing development, and must avoid creating sharp contrasts with neighbouring structures or with the landscape;
(iv)All plumbing, rooftop equipment, air conditioning units, elevator shafts, and other mechanical equipment shall be screened from view from a scenic route.
(d)Buffer areas
(i)Buffer areas shall be provided along any street boundary which abuts a scenic route and the width of the buffer areas shall not be less than:• 5m in urban areas;• 10m in suburban areas, and• 30m in rural areas, and the municipality shall determine which is an urban, a suburban or a rural area;
(ii)Buildings and parking shall not be permitted within the buffer area;
(iii)Any portion of fence or wall which exceeds 1,2m in height shall be constructed in conjunction with the principle of open work which allows visual permeability to the municipality’s satisfaction;
(iv)Berms and soft landscaping may be used to provide privacy and screening without adverse affect on views and scenic amenity of the scenic route.
(e)Parking and loading
(i)For land uses requiring large amounts of parking, the municipality may require that parking areas are broken up into smaller units not exceeding 50 parking bays per area, resulting in a series of smaller parking areas;
(ii)Loading bays, refuse rooms and unsightly accessory equipment shall be located in such a manner as to be screened from view from a scenic route;
(iii)All surface parking areas visible from a scenic route shall include at least one tree for every six parking bays, and such trees shall be located so as to help screen parked vehicles.
(f)Landscaping
(i)Plants, shrubs and trees shall be selected to fit in with the predominant landscape character of the area, with the emphasis on indigenous, low maintenance species or locally appropriate species;
(ii)Significant natural features shall be preserved and the development on a land unit shall respect ridgelines, gullies, streams, wetlands, rock outcrops, endangered species and trees worthy of conservation;
(iii)Where existing trees or shrubs have to be removed, an equivalent number of trees or shrubs shall be replanted on the land unit and the type of plants to be replanted shall be compatible with the surrounding vegetation and micro-climatic conditions to the municipality’s satisfaction.
(g)Exterior lighting
(i)All exterior lighting shall be located and controlled so as to avoid direct illumination, glare or reflection onto any adjoining land unit or scenic route;
(ii)All non-residential exterior lighting shall be turned off during non business hours, except lighting deemed necessary for public safety or for security on the land unit as approved by the municipality.
(h)Earthworks and grading
(i)Grading shall be permitted only to the extent necessary to construct buildings and access roads, and shall not adversely affect views from a scenic route;
(ii)Grading slopes shall be rounded to blend in with the existing topography, to fit in with the natural contours of the land, and to establish a transition between constructed and existing slopes;
(iii)The natural surface drainage system shall be maintained;
(iv)Cut and fill surfaces shall be stabilised by the planting of low maintenance indigenous or locally appropriate ground cover and shrubs.
6.3Alternative land use provisionsAs an alternative for paragraph 6.2, the municipality may formulate and apply special land use provisions for specific scenic route corridors or portions of the corridors.Annexure A. 7: Local Area Overlay Zone (LAO)General Policy Statement:
(a)Although it is one of the purposes of the zoning scheme to introduce equity into the system of land use control, it is also necessary to recognize the diversity which characterizes our society, as well as the diversity of areas and communities it has to accommodate. It should therefor also be recognized that different communities may have different needs, and that local area identities add to the diversity and richness of the urban and social fabric. The local area overlay zone is provided as a mechanism to determine specific local land use provisions to reflect local circumstances;
(b)It is important to note that this zone does not only serve to provide a mechanism whereby more restrictive development control may be exercised. It also creates the opportunity whereby development management parameters may be relaxed in order to promote development and to address socio-economic needs. It may be utilized as a tool to facilitate the implementation of local economic development and urban renewal;
(c)Public participation and consultation is an important component in establishing a local area overlay zone, whether the initiative to establish the local area overlay zone comes from the community or the municipality.
Objective:The objective of the local area overlay zone is to provide the opportunity for communities to determine specific local land use provisions to reflect local circumstances. It is recognised that different communities may have different requirements, and that local area identities add to the diversity and richness of the urban and social fabric. The local area overlay zone also provides the municipality with the opportunity to determine specific local land use provisions to encourage development in support of the local economy.
7Overlay zoneThe provisions of this overlay zone are in addition to those provisions which apply to the base zone of the relevant land, and
(a)may be more or less restrictive than the provisions applying to the base zone of the land, and
(b)if the provisions of a local area overlay zone are in conflict with the provisions of the base zone, the more restrictive conditions apply.
7.2Land Use provisionsThe land use provisions contained in the local area overlay zone may vary between local areas and may include, but are not limited to, the following issues:
(a)requirements for the minimum size of new subdivisions in order to preserve the character of an area;
(b)limitations on the maximum permissible density or maximum permissible floor space of new development in order to preserve the character of an area or to optimise the capacity of utility services;
(c)requirements for a minimum density or minimum permissible floor space of new development in order to promote efficiency or higher density development;
(d)specifications for boundary walls and fences in order to preserve the character of an area, and to maintain a visual relationship between the street and adjacent development;
(e)limitations on the maximum height of buildings in order to preserve the character of an area, protect important views or maintain an appropriate scale of development;
(f)architectural design guidelines required for new development in order to promote good design, to harmonise new development with existing development and to promote the special architectural character of an area;
(g)limitations on the municipality’s discretion to grant specified consent applications within the local area to ensure that such consent uses do not occur within the local area concerned;
(h)policy guidelines and requirements for the approval of consent uses and conditions to be imposed by the municipality, and
(i)limitations and design guidelines for outdoor advertisements within a local area.
Annexure A. 8: Special Planning Area Overlay Zone (SPAO)Objective:The objective of this zone is to provide a mechanism to manage large or strategic projects, and to facilitate agreement about future development, floor space and land use without detailed planning required at the outset. A phased process of planning and approval is instituted, whereby appropriate levels of detail are approved subject to conditions, and through which the project may be managed until there is confirmation of formal land use provisions applicable to particular land units, in terms of the this by-law. The special planning area overlay zone creates a framework for planning and development that is action-oriented, strategic and capable of being updated periodically as circumstances warrant. It does not aim to create a blueprint plan, but to provide a flexible plan, which within prescribed limits, can accommodate emerging needs, respond to market demand, provide the basis for delegation of decisions, and provide the basis for approval of detailed development plans.
8.Designation of a special planning area overlay zoneSubject to the provisions of Annexure A, the municipality may designate an area to be a special planning area overlay zone and shall record the designation in an annexure.
8.1Land use provisionsLand zoned as a special planning area shall be subject to the package of plans approach for the purpose of development management. The municipality may require any or all of the following six components of the package of plans approach to be submitted, for its approval, by an owner or developer of land within the special planning area, and may refuse clearance for transfer of land or building plan approval until the required package of plans has been approved.
8.2Package of plansThe package of plans consists of the following six components that are listed in a hierarchy from higher order to lower order plans.
(a) A contextual framework
The contextual framework lays down broad policy for the special planning area and the surrounding area. It may include principles or heads of agreement summarising the general obligations of the municipality and the developer in relation to the special planning area. The contextual framework may be prepared by the municipality, or by a land owner or development agency under the supervision of the municipality;
(b)A development framework
The development framework shall identify overall policy, broad goals and principles for development within the special planning area as a whole. The development framework shall identify the range of uses, the general spatial distribution of uses and the densities proposed. Major linkages and any limits to development within the special planning area, including but not limited to density and maximum floor space, should be specified;
(c)Precinct plans
Precinct plans apply to areas within the development framework that have common features or functional relationships. There may be several precinct plans that make up the area of the special planning area. While still providing a measure of flexibility, a precinct plan describes in more detail the objectives for a particular precinct, as well as principles for urban design, land use, movement and strategic implementation;
(d)Site development plans
Site development plans depict more detailed design and development parameters for individual land units or groups of land units. These parameters may include, but are not limited to, details relating to land use, floor factor, building lines, height and parking requirements as well as details relating to the position and appearance of buildings, open spaces and movement systems;
(e)Subdivision plans
Subdivision plans, if required, shall be processed in terms of this by-law to establish new cadastral boundaries and facilitate the transfer of land units. Subdivision plans may be approved at any stage after the development framework has been approved. Apart from establishing cadastral boundaries, subdivision approvals may include conditions imposed by the municipality relating to development and zoning restrictions applicable to the particular land unit. At the confirmation of the subdivision plan for land zoned as subdivision area, any zoning parameters approved by the municipality as part of the subdivision approval shall be deemed to be a substitution scheme;
(f)Building plans
Building plans contain the detailed specifications in accordance with which building work may be performed, once approved by the municipality in terms of the National Building Act.
8.3Approval and amendment of plansThe following provisions shall apply to the approval and amendment of plans with the package of plans:
(a)Approval of the development framework shall be the responsibility of the municipality. Applications for approval of precinct plans, site development plans, subdivision plans and building plans shall be directed to the municipality, the municipal manager or other delegated officials to the municipality’s satisfaction;
(b)All plans within the package of plans may be amended from time to time to reflect changing circumstances. Lower order plans should be consistent with the principles established by higher order plans;
(c)Where lower order plans are consistent with the principles established by higher order plans, the municipality may use its discretion to minimise advertisement and procedural delays in processing such lower order plans;
(d)Where a lower order plan differs materially from the principles established in the higher order plans, then the appropriate amendments of the plans are required before development may proceed. To the extent that there is a material conflict, the higher order plans shall prevail over the lower order plans, unless the higher order plans are amended.
8.4ConditionsIn approving the development framework, precinct plans, site development plans and subdivision plans, the municipality may impose conditions as contemplated in this by-law, which may include a requirement that a services agreement be concluded between the two parties concerned.
8.5Services agreementThe municipality may require as a condition of approval of a development framework, precinct plan or site development plan, a binding agreement known as a services agreement, which:
(a)shall identify commitments and obligations that the parties agree to uphold;
(b)may include commitments relating to the provision, phasing and financing of services, and
(c)may include agreements relating to the process of planning, implementation and review and the exercise of management functions.
8.6Allocation of floor spaceIn approving a development framework plan, the municipality may determine the entire development rights or floor space which is permitted within the special planning area, provided that:
(a)the allocation of floor space should take into account the carrying capacity of internal and external infrastructure including roads and utility services, and any urban design principles approved by the municipality as part of a rezoning or contextual framework; and
(b)the floor space within the development framework may be allocated to particular precincts, or may be regarded as floating floor space to be allocated to individual land units or buildings at a later stage, as the development moves from general stages of planning to detailed stages of planning.
Annexure A. 9: Activity Spine Overley Zone (ASO)General Policy Statement:Development frameworks frequently promote concepts such as activity corridors or spines as part of the spatial planning for an area. The activity spine overlay zone provides the municipality with a technique whereby the principles of an activity spine can be promoted and supported through these Zoning Scheme Regulations. These principles include a mix of land uses with a continuity of built form and emphasis on the pedestrian environment.Objective:The objective of this overlay zone is to strengthen and enhance an activity spine which has been designated by the municipality in order to:
(a)create an attractive, enabling environment which is characterized by mixed use activity;
(b)encourage pedestrian activity by creating a positive pedestrian experience, and encourage the use of public transport;
(c)generate pride and confidence through design quality, and
(d)enhance the value and amenity of land through quality control.
9Overlay zone
(a)The provisions of this overlay zone are additional to those provisions applying to the base zone of the relevant land;
(b)The provisions of this overlay zone are general in nature and may be interpreted by the municipality with some flexibility in the application thereof to specific sites, provided that the objectives of this zone are respected.
9.1Land use provisionsThe municipality may apply the following land use provisions to land in the activity spine overlay zone:
(a)Building lines and setbackThe municipality may require that the first 2 storey’s of any building shall be built directly adjacent to the street boundary,unless:
(i)a hard landscaped plaza (for up to 50% of the building face),is provided between the building face and the street boundary;
(ii)it can be demonstrated that the above configuration causes undue hardship, in which case the municipality may require that only 50% of the building face shall be located directly adjacent to the street boundary, or
(iii)The municipality agrees to a negotiated design solution with variable setbacks, pedestrian sidewalks and canopies which require space between the building and the street boundary.
(b)Street corner obligations
Any building located at a corner intersection shall incorporate architectural features at the ground floor which emphasizes the importance of pedestrian movement. These features may include building cut-offs, walk-through covered arcades and other elements that focus visual interest on the corners. Corner intersections include the corner adjacent to a public street, private road, driveway or pedestrian walkway intersection.
(c)Canopies and awnings
(i)Canopies, awnings, trellises and other accessory building structures which are relatively open and do not restrict pedestrian or vehicular movement, may project over the street boundary after the prior written consent of the municipality has been obtained, subject to an encroachment agreement to be concluded between the municipality and the parties concerned;
(ii)Canopies should shelter all openings of each building at the ground floor from sun and rain.
(d)Parking orientation
(i)The municipality may prohibit large parking areas between the street boundary and the main face of the building. Parking should primarily be located to the rear of buildings;
(ii)Vehicular entry points to parking areas shall receive special attention (for example paving thereof) where the carriageway crosses the sidewalk;
(iii)Where parking is permitted between the street boundary and the main face of the building, the municipality may require owners and developers to plant trees and provide hard landscaping elements.
(e)Streetscape improvements
Owners or developers are encouraged to improve the streetscape in front of their buildings with paving, planters, benches, lighting and landscaping.
(f)Plaza provisionsThe building may be set back from the street boundary at ground level if the area is designated as a pedestrian plaza. For land to qualify as a pedestrian plaza, the following specifications shall be incorporated into the design:
(i)the minimum size of the plaza shall be 4m deep for the length of the entire building face which is set back from the street boundary;
(ii)a minimum of 80% of the plaza shall be paved with a decorative paver of textured coloured concrete or brick or as the municipality may approve. Asphalt or plain concrete are considered not acceptable as plaza paving material, and
(iii)landscaping is required in accordance with a landscape plan to be approved by the municipality.
(g)Architectural design
(i)The building face along a public street shall have at least 50% of its ground floor surface area made from a transparent material, such as non-tinted glass, in order to allow pedestrians visual contact with the building;
(ii)Blank solid walls or sidewalls visible from the public street should be avoided. If such walls are necessary for interior reasons, the exterior structure of the wall shall receive some form of articulation such as awnings or cornice bands;
(iii)The facades of adjacent structures shall be considered in the design of new development to avoid clashes in architectural style and materials.
(h)Lighting
(i)The owner or developer is encouraged to install lighting as an element in creating a safe and vibrant night-time environment;
(ii)Exterior lighting shall be designed as part of the overall architectural theme of a building or development. Fixtures, standards and exposed accessories shall be harmonious with the building design, lighting design and characteristics of the adjacent public spaces;
(iii)For safety, identification and convenience, all entrances of buildings, parking areas and plazas shall be well illuminated.
Annexure A. 10: Airport Overlay Zone (AO)General Policy Statement:Airports are an important part of the modern economy and transport system, and require large amounts of capital expenditure to construct and maintain. It is important to manage development around airports to ensure that their operations are not compromised by inappropriate development. At the same time, airports can have significant impacts on surrounding areas, and pose potential risk for development within the flight paths of aircraft. Development around airports should be compatible with airport operations, while the airport operators need to recognize and mitigate the potential impacts of their operations.Objective:The objective of this overlay zone is to promote the safety and general welfare of people living in the vicinity of airports by firstly, reducing human exposure to potential aircraft accidents and high noise levels generated by airport operations, and secondly, by ensuring that development and land uses are compatible with the operation of airports. Land use management in the vicinity of an existing airport should take into account future airport development so that when such development does take place, potential conflicts are minimized. This overlay zone also serves to inform potential residents that they are situated within or in the vicinity of an airport and indicates the area of potential impact and conflict.
10.Application of this Zoning Scheme
(a)The provisions of this overlay zone are in addition to those provisions applying to the base zone of the relevant land;
(b)These provisions do not prejudice any obligations or requirements in terms of national and provincial legislation regarding airports.
10.1Designation of aircraft noise contoursFor the purpose of land use management, the municipality may designate noise contours within the airport overlay zone:
(a)Where noise contours have been designated by the municipality for the existing activities and projected operations for the next 15 years, it shall be depicted on a map;
(b)Noise contours shall be supplied to the municipality by the airport owner or airport operator in accordance with national policy on aircraft noise and engine emissions;
(c)The municipality may adjust the limits of noise contours from time to time after the airport owner or airport operator has been requested to recalculate the noise contours.
10.2Land use provisionsThe municipality may apply the following land use provisions to land in an airport overlay zone:
(a)Use of landAccording to municipality opinion, uses that display the following characteristics shall not be permitted:
(i)concentrated residential uses, work-related uses or concentration of other categories of people for long- term periods;
(ii)uses that concentrate people who are unable to respond to emergency situations, such as children, the elderly, or ill or handicapped persons;
(iii)uses that involve explosives, fire, toxic material, corrosive material or other material that may be hazardous to airport operations, and
(iv)uses that pose significant hazards to aircraft, aircraft communication systems or pilot vision such as those which release emissions, direct light or indirect reflection or that create electronic interference with airport operations.
(b)Bird hazard considerations
In order to discourage large numbers of birds from locating in the vicinity of an airport, the municipality may require that no activities such as piggeries and fruit farming take place within a radius of 3km from an airport and no bird sanctuaries shall be established within a radius of 8km from an airport. Where these operations are permitted within these areas, the municipality may require that the airport owner implement reasonable and practical measures to ensure that the runway and flight paths are kept clear of birds.
(c)Height
In addition to the provisions of this scheme, no structure within an airport overlay zone shall be erected to a height in excess of the applicable height limit set by the South African Civil Aviation Authority.
(d)Noise mitigation
Noise control regulations for the determination of noise levels around airports are regulated in terms of the Noise Control Regulations in the Provincial Government of the Western Cape P.N. 627/1998 Noise Control Regulations, as amended, promulgated in terms of ECA. The noise control regulations refer, inter alia, to the standards set out in the SANS publication (10117— 1974) titled "Code of Practice for the determination and limitation of disturbances around an aerodrome due to noise from aeroplanes". The following table identifies categories of land use that are suitable within different noise contours, and serves as a guide for land use in relation to aircraft noise in the vicinity of airports.
Noise indexAcceptable land use
“65dBAResidential uses
“75dBAResidentialuses with acoustically insulated buildings providing at least a 20dBAreduction of noise between the inside and outside of the building
“85dBAIndustrial and associated uses
>85dBANo development should be permitted
Where buildings can be insulated in a satisfactory manner, with a difference of at least 20dBA between the inside and the outside of the building, they may be permitted within a higher noise contour.The noise control regulations place a general prohibition on the erection of educational, residential, hospital, church or office buildings within the "controlled area", unless acoustic screening measures have been provided to ensure acceptable interior noise levels measured inside the building, to 40dBA. A "controlled area"is defined as an area of land designated by the local authority, in the case of aircraft noise in the vicinity of an airport, projected for a 15-year period, and exceeds 65dBA.
(e)Establishment of an airport environmental committee
(i)The municipality may establish an airport environmental committee in order to advise on development around the airport and to promote public awareness;
(ii)The terms of reference for the airport environmental committee shall be determined by the municipality.

Map of area for the Swartland Zoning Scheme

▲ To the top

History of this document

03 March 2017 this version