- Flynote
-
Construction contract – contract providing for dispute resolution process –
arbitration award final and binding on the parties until and unless set aside on review
– Project Manager refusing to implement some of the findings of arbitrator – dispute2
relating to Project Manager’s refusal to implement arbitrator’s findings referred to
adjudicator for adjudication - adjudicator applying the principles established in
arbitration award – a party to the contract not entitled to ignore the adjudicator’s
decision simply on the ground that it considers it to be invalid – appeal dismissed.