Investeach Lerekat (Pty) Ltd v Morobane (5052/2019) [2023] ZAFSHC 26 (8 February 2023)








IN THE HIGH COURT OF SOUTH AFRICA,

FREE STATE DIVISION, BLOEMFONTEIN



Reportable: NO

Of Interest to other Judges: NO

Circulate to Magistrates: NO

CASE NO: 5052/2019

In the matter between:


INVESTEACH LEREKAT (PTY) LTD Plaintiff


And


MATHEDISO ANNA MOROBANE Defendant




APPLICATION FOR LEAVE TO APPEAL

___________________________________________________________________


JUDGMENT BY: MHLAMBI, J

___________________________________________________________________


DELIVERED ON: This judgment was handed down electronically by circulation to the parties’ legal representatives by email and released to SAFLI. The date and time for the hand-down are deemed to be 8h00 on 08 February 2023




[1] This an application for leave to appeal in terms of section 17(1)(a)(i) which provides that leave to appeal may only be given where the Judge or Judges concerned are of the opinion that the appeal would have a reasonable prospect of success.


[2] The grounds of appeal are stated as follows:

1. The court misdirected itself in finding that the defendant is liable to pay the plaintiff the amount of R 130 339-38, regard being had on the following: -

1.1 The plaintiff’s case was based on the written contract in the amount of R 450 000-00.


1.2 The defendant’s case was that the agreement was that the plaintiff would complete the construction of the housework with the amount of R 334 966-42, which was the balance in her home loan account. The plaintiff vehemently denied any such agreement.



1.3 The court effectively rejected the plaintiff’s version in this regard.


2. The plaintiff failed to prove any amount, if any, owed to it by the defendant.

3. The court failed to take into account that the plaintiff did not comply with the terms of the very same contract he relies upon.



3.1 Mr Komako conceded under cross-examination that the plaintiff did not comply with the terms of clause 1 of the written contract between the parties, in that the plaintiff failed to provide and pay for all the material, tools, equipment and labour required to perform construction work required.


4. The court further failed to take into account the undisputed evidence of the defendant in respect of the further and or more expenses related to the construction of the house she incurred as further fortified by the transactions contained in her bank statements and which amounts were not covered in the plaintiff’s particulars of claim.


4.1 In this regard the court only focused on the deductions contained in the particulars of claim.

5. The court erroneously approached the quantum of the plaintiff’s case by simple method of deducting what was proven by the defendant as her own expenses instead of what the plaintiff could or could not prove as his damages.


6. The court erred in awarding the costs in favour of the plaintiff, regard been had of the following: -



6.1 The court effectively accepted that the intentions of the parties are covered in Exhibit “B”, which was introduced by the defendant and rejected the plaintiff’s version.


6.2 Although the court found that the defendant is indebted to the plaintiff that was not found on the basis of the plaintiff’s own evidence.



6.3 The undisputed evidence of the defendant, that she offered the amount of R 80 000-00, in settlement of the matter before it came to court and there was no evidence and or any plausible explanation why the offer was not accepted.


7. Therefore, leave to appeal to the full court of this Division stands to be granted in that the appeal would have reasonable prospects of success.


[3] In essence, the attack on the judgment is that the court accepted that the parties regulated their contractual relationship by jointly drafting and signing annexure “A” and “B” which related to the completion of the construction work for the balance of R 334 966.42 being the remainder of the bank loan extended to the respondent. Sight has been lost of the fact that the plaintiff testified that he would complete the work with that amount1 and also admitted his signatures to both annexures “A” and “B”2. It was also not in dispute the plaintiff was initially contracted to do the roof as the house was only built up to the “Wall plate level”3 and that the defendant conceded that the plaintiff did furnish her with the engineer’s roof certificate. The amount of R 334 966.42 was released to the defendant on 21 August 2019 and no payment whatsoever was made to the plaintiff.


[4] One of the grounds of appeal is a concession that the undisputed evidence is that the defendant made an offer in the amount of R 80 000.00 to the plaintiff in settlement of the matter. Despite the denial in her papers and in parts of her oral evidence that she did not owe the applicant anything, she testified that she did not refuse to pay the plaintiff. The plaintiff was overhasty to institute a claim against her.


[5] It was argued in the plaintiff’s written heads of argument that the plaintiff’s non-compliance with clause 1 of the original agreement was fatal as it militated against the sanctity and privity of contract. Furthermore, the court had rejected the plaintiff’s reliance on the agreement that was attached to the particulars of claim. The latter submission is misconceived as nowhere in the judgment was it stated that the plaintiff’s reliance on the agreement was rejected. What is clear from the judgment is that the terms of the agreement were modified by virtue of the conclusion of annexures “A” and “B” by the parties.


[6] It is common cause that the plaintiff did not have sufficient funds to complete the project and had to rely on the defendant for financial assistance. It is also undisputed that he had to alienate some of his assets to finance the project because the bank refused to release the money as it felt at risk because of the defendant having changed the building plans. This explained his willingness to conclude exhibits “A” and “B”.


[6] In the circumstances, I am of the opinion that this appeal does not have a reasonable prospect of success and should therefore fail.


[7] I therefore make the following order:


Order:


The application for leave to appeal is dismissed with costs.






_________________

MHLAMBI, J




On behalf of appellant: Adv. F Bester

Instructed by: Horn & Van Rensburg Attorneys

4 Nobel Street

Brandwag

Bloemfontein





On behalf of respondent: Adv. R.J Nkhahle

Instructed by: Mavuya Attorneys Inc.

Suit 201

2nd Floor

Cuthberts Building

78 Charlotte Maxeke Street

Bloemfontein

1 Paragraph 6 of the judgment.

2 Paragraph 7 of the judgment.

3 Paragraph 6 of the judgment.

▲ To the top